2901 W WAVERLY DR 90039
Certificate Information: 2901 W WAVERLY DR 90039
- Application / Permit
- 16010-10000-01992
- Plan Check / Job No.
- B16LA07115
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FOR CONSTRUCT NEW 3 STORY SFD WITH A 2 CAR GARAGE ON A SMALL LOT SUBDIVISION 8 OF 11
- Permit Issued
- Issued on 6/23/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2016 | DEAN LEE |
| Green Plans Picked Up | 6/20/2016 | APPLICANT |
| Corrections Issued | 6/22/2016 | DEAN LEE |
| Building Plans Picked Up | 6/24/2016 | APPLICANT |
| Quality Review Completed | 7/21/2016 | CHARLES CHANG |
| Applicant returned to address corrections | 8/25/2016 | DEAN LEE |
| Applicant returned to address corrections | 9/7/2016 | DEAN LEE |
| Applicant returned to address corrections | 9/26/2016 | DEAN LEE |
| Applicant returned to address corrections | 10/21/2016 | DEAN LEE |
| Applicant returned to address corrections | 11/3/2016 | DEAN LEE |
| Applicant returned to address corrections | 11/10/2016 | DEAN LEE |
| Applicant returned to address corrections | 4/5/2017 | DEAN LEE |
| Plan Check Approved | 4/12/2017 | DEAN LEE |
| Issued | 6/23/2017 | LADBS |
| TCO Issued (Expire Date: 10-11-2022) | 4/14/2022 | DEROLD HAUFF |
| CofO in Progress | 10/13/2022 | SCOTT FINNILA |
| Permit Finaled | 10/13/2022 | DEROLD HAUFF |
| CofO Issued | 10/13/2022 | DEROLD HAUFF |
| Permit Finaled | 10/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2016 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 8/19/2016 | JOHN DALLAS |
| Opn space landscape/Water mgmt | Cleared | 8/23/2016 | CASSANDRA ZWEEP |
| ZA Case | Cleared | 8/23/2016 | CASSANDRA ZWEEP |
| Encroachment in public way | Cleared | 9/13/2016 | JAMES KHO |
| Work Adjacent to Public Way | Cleared | 9/13/2016 | JAMES KHO |
| Building over 3-story or 36-ft | Cleared | 12/30/2016 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 12/31/2016 | CALOSHA APPROVED |
| Green Code | Cleared | 2/9/2017 | BIJAN EGHTESADY |
| Sewer availability | Cleared | 2/23/2017 | ROCHELLE DUNGCA |
| Tract Map conditions | Cleared | 2/28/2017 | EDBER MACEDO |
| ZI | Cleared | 2/28/2017 | EDBER MACEDO |
| Green Code | Cleared | 3/1/2017 | DEAN LEE |
| Low Impact Development | Cleared | 3/21/2017 | RYAN HUDSON |
| Stormwater Pollution Mitigatn | Cleared | 3/21/2017 | RYAN HUDSON |
| Highway dedication | Cleared | 4/3/2017 | RAVIL MANAPOV |
| Roof/Waste drainage to street | Cleared | 4/3/2017 | DAVID PEREZ |
Contact Information
| Architect | Vanos, Vincent Jay; Lic. No.: C22269 | 2747 MARQUETTE DR TOPANGA, CA 90290 |
| Contractor | Quadrant Inc; Lic. No.: 543948-B | 7586 WOODROW WILSON DR LOS ANGELES, CA 90046 |
| Engineer | Binatli, Aret; Lic. No.: C64448 | 10814 RESEDA BLVD NORTHRIDGE, CA 91326 |
| Engineer | Fischer, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
| Engineer | Hayes, Leonard C; Lic. No.: GE386 | 31225 VILLAGE 31 CAMARILLO, CA 93012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/6/2017 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/12/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 4/17/2019 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/1/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/20/2019 | Corrections Issued | SCOTT FINNILA |
| Reinforced Concrete Frame | 6/24/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Shotcrete | 6/27/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/15/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/22/2019 | Approved | SCOTT FINNILA |
| Deputy Steel/Welding | 1/31/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/6/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/7/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 2/12/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 2/13/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 2/14/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2020 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/9/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 3/9/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 4/13/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 4/14/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/8/2020 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/8/2020 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 5/8/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Drywall Nailing | 5/14/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/14/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 6/24/2020 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | No Access for Inspection | SCOTT FINNILA |
| Wood Frame | 6/24/2020 | No Access for Inspection | SCOTT FINNILA |
| Drywall Nailing | 6/25/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 7/15/2020 | No Access for Inspection | ELMER BLAND |
| Wood Frame | 7/16/2020 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 7/23/2020 | Partial Approval | ENRIQUE MIRELES |
| Drywall Nailing | 7/27/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/27/2020 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 8/20/2020 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/15/2020 | Partial Approval | DONALD CRICHLOW |
| HVAC-Rough | 3/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/5/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/5/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/23/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/23/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 4/23/2021 | Partial Approval | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 4/23/2021 | Approved | SCOTT FINNILA |
| Insulation | 4/29/2021 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/18/2021 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 6/2/2021 | Partial Approval | SCOTT FINNILA |
| Insulation | 6/7/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 6/7/2021 | Approved | SCOTT FINNILA |
| Drywall Nailing | 6/23/2021 | Approved | SCOTT FINNILA |
| Green Building Rough | 6/23/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/27/2021 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 12/28/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/28/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 1/11/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 1/14/2022 | Approved | SCOTT FINNILA |
| Green Building Final | 1/14/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 1/14/2022 | Approved | SCOTT FINNILA |
| Service/Power Release | 1/31/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 2/3/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/9/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/14/2022 | Approved | SCOTT FINNILA |
| Final | 4/18/2022 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | SCOTT FINNILA |
| SUSMP-Std. Urban Storm Water | 4/18/2022 | Approved | SCOTT FINNILA |
| Smoke Detectors | 4/18/2022 | Approved | SCOTT FINNILA |
| Special/Order Compliance | 9/13/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 10/13/2022 | OK to Issue CofO | SCOTT FINNILA |