6926 W CLINTON ST 90036

Certificate Information: 6926 W CLINTON ST 90036

Application / Permit
16010-10000-01941
Plan Check / Job No.
B16LA06977
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3 Story SFD w. att garage. Sprinklers Small lot subdivision pursuant to Preliminary Parcel Map No. AA-2015-3553-PMLA-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
Permit Issued
Issued on 2/16/2017
Issuing Office
Metro
Current Status
CofO Corrected on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2016 APPLICANT
Assigned to Plan Check Engineer 6/16/2016 HERNAN ARREOLA
Corrections Issued 6/21/2016 HERNAN ARREOLA
Quality Review Completed 6/22/2016 CHAD DOI
Building Plans Picked Up 6/27/2016 APPLICANT
Green Plans Picked Up 8/1/2016 APPLICANT
Applicant returned to address corrections 8/15/2016 HERNAN ARREOLA
Applicant returned to address corrections 1/3/2017 HERNAN ARREOLA
Plan Check Approved 2/13/2017 HERNAN ARREOLA
Issued 2/16/2017 LADBS
CofO in Progress 10/6/2020 BRIAN SULLIVAN
CofO Issued-Status Void 10/13/2020 DEROLD HAUFF
Permit Finaled-Status Void 10/13/2020 DEROLD HAUFF
Re-Activate Permit 11/30/2022 DEROLD HAUFF
Permit Finaled 11/30/2022 DEROLD HAUFF
CofO Corrected 11/30/2022 DEROLD HAUFF
Permit Finaled 11/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/15/2016 ARNULFO NUNO
Permit Cleared 8/15/2016 ARNULFO NUNO
Hydrant and Access approval Cleared 8/16/2016 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 8/18/2016 ARNULFO NUNO
Low Impact Development Cleared 11/3/2016 MARTIN FRAGOSO
Disturb/Remove Protected Trees Cleared 12/7/2016 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 12/7/2016 CELINA MORENO
Sewer availability Cleared 12/8/2016 ROCHELLE DUNGCA
Miscellaneous Cleared 12/30/2016 EDBER MACEDO
Construction near power lines Cleared 2/6/2017 LUCIO FERRER
Green Code Cleared 2/8/2017 DAVID MATSON
Miscellaneous Cleared 2/8/2017 TERRY PHAN

Contact Information

Architect Gibbs, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Ocean Spaulding Inc; Lic. No.: 833486-B 1061 NORTH SPAULDING AVENUE      LOS ANGELES, CA 90046
Engineer Maalouf, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Shubeck, Robert James; Lic. No.: GE773 60 HACKAMORE LANE      BELL CANYON, CA 91307

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/7/2017 Approved BRIAN SULLIVAN
Grading Pre-Inspection 4/25/2017 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 5/16/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Barrier 5/16/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Subgrade 5/16/2017 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 5/18/2017 Approved BRIAN SULLIVAN
Pre-Inspection 5/19/2017 Approved BRIAN SULLIVAN
Special/Order Compliance 6/13/2017 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/27/2017 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/5/2017 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/4/2017 Partial Approval RAUL BARAJAS
METHANE-Barrier 8/4/2017 Not Ready for Inspection RAUL BARAJAS
METHANE-Subgrade 8/4/2017 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 8/18/2017 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 10/3/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Barrier 10/3/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Subgrade 10/3/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 10/4/2017 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/6/2017 Partial Approval BRIAN SULLIVAN
METHANE-Barrier 10/6/2017 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Subgrade 10/6/2017 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 10/12/2017 Partial Approval BRIAN SULLIVAN
METHANE-Barrier 10/12/2017 Approved BRIAN SULLIVAN
METHANE-Subgrade 10/12/2017 Approved BRIAN SULLIVAN
METHANE-Final 10/17/2017 Approved BRIAN SULLIVAN
METHANE-Rough 10/17/2017 Approved BRIAN SULLIVAN
Deputy Methane Barrier 10/18/2017 Conditional Approval BRIAN SULLIVAN
Deputy Methane Barrier 10/19/2017 Conditional Approval BRIAN SULLIVAN
Deputy Methane Barrier 10/20/2017 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/24/2017 Approved CRAIG VAUGHAN
Drywall Nailing 1/16/2018 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 1/16/2018 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/19/2018 Partial Approval TIMOTHY O CONNER
Drywall Nailing 1/24/2018 Partial Approval BRIAN SULLIVAN
Green Building Rough 1/24/2018 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2018 Partial Approval BRIAN SULLIVAN
Drywall Nailing 1/31/2018 Partial Approval BRIAN SULLIVAN
Green Building Rough 1/31/2018 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2018 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2018 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/7/2018 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/6/2018 Not Ready for Inspection LUIS BARRALES
PLUMBING-Rough 6/11/2018 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/21/2018 Partial Approval BRIAN SULLIVAN
HVAC-Rough 6/25/2018 Approved LUIS BARRALES
BUILDING-Rough-Frame 7/11/2018 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 7/11/2018 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/11/2018 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 7/17/2018 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 8/1/2018 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 8/1/2018 Corrections Issued RAUL BARAJAS
Green Building Rough 8/1/2018 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/1/2018 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 8/7/2018 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/9/2018 Conditional Approval BRIAN SULLIVAN
Green Building Rough 8/9/2018 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/9/2018 Approved BRIAN SULLIVAN
Insulation 8/17/2018 Not Ready for Inspection BRIAN SULLIVAN
Insulation 8/20/2018 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/28/2018 Corrections Issued BRIAN SULLIVAN
Drywall Nailing 9/6/2018 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/6/2018 Partial Approval BRIAN SULLIVAN
Shower Pan 9/17/2018 Approved BRIAN SULLIVAN
ELECTRICAL-Final 6/18/2020 Approved BRIAN SULLIVAN
Gas Test 6/18/2020 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 9/15/2020 Approved BRIAN SULLIVAN
Final 9/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 9/15/2020 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/15/2020 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 9/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 9/15/2020 Not Ready for Inspection BRIAN SULLIVAN
Final 9/25/2020 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 9/25/2020 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 9/25/2020 Approved BRIAN SULLIVAN
Final 10/6/2020 OK to Issue CofO BRIAN SULLIVAN
Service/Power Release 10/6/2020 Approved BRIAN SULLIVAN