1941 N MOUNT OLYMPUS DR 90046

Certificate Information: 1941 N MOUNT OLYMPUS DR 90046

Application / Permit
16010-10000-01895
Plan Check / Job No.
B16LA06769
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW CONSTRUCTION OF SINGLE FAMILY RESIDENCE (TWO STORY WITH BASEMENT) WITH ATTACHED GARAGE AND ATTACHED RECREATION ROOM
Permit Issued
Issued on 1/24/2017
Issuing Office
Metro
Current Status
Issued on 1/24/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2016 APPLICANT
Assigned to Plan Check Engineer 6/9/2016 ERIC CABRERA
Corrections Issued 6/15/2016 ERIC CABRERA
Quality Review Completed 6/16/2016 HOK CHI CHIU
Green Plans Picked Up 6/30/2016 APPLICANT
Building Plans Picked Up 7/30/2016 APPLICANT
Plan Check Approved 11/14/2016 GEORGE BANNING
Issued 1/24/2017 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/9/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2016 ADRIAN SANCHEZ
CPC Cleared 8/9/2016 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 8/9/2016 ADRIAN SANCHEZ
Highway dedication Cleared 8/9/2016 ADRIAN SANCHEZ
Miscellaneous Cleared 8/9/2016 MARITZA PRZEKOP
Miscellaneous Cleared 8/9/2016 MARITZA PRZEKOP
Miscellaneous Cleared 8/9/2016 MARITZA PRZEKOP
Miscellaneous Cleared 8/9/2016 MARITZA PRZEKOP
Permit Cleared 8/9/2016 ADRIAN SANCHEZ
Tract Map conditions Cleared 8/9/2016 MARITZA PRZEKOP
Work Adjacent to Public Way Cleared 9/22/2016 ARNULFO NUNO
Hydrant and Access approval Cleared 10/14/2016 VIDAL GARCIA
Excavation more than 5-ft deep Cleared 11/3/2016 CALOSHA APPROVED
GPI Written Notices Cleared 11/3/2016 ERIC CABRERA
Grading Pre-Inspection Cleared 11/3/2016 ERIC CABRERA
Green Code Cleared 11/8/2016 JOHN KLARIN
Landscape for retaining wall Cleared 11/9/2016 JOHN DACEY
Low Impact Development Cleared 11/9/2016 RYAN HUDSON
Excavation more than 5-ft deep Cleared 11/14/2016 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 11/14/2016 ROCHELLE DUNGCA
Sewer availability Cleared 1/20/2017 ROCHELLE DUNGCA

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Guivatchian, Mohammad; Lic. No.: C36510 4720 DEGOVIA AVENUE      WOODLAND HILLS, CA 91364
Engineer Zweigler, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Cugno, Giuseppe; Lic. No.: EG1804 J. BYER GROUP, THE   1461 E CHEVY CHASE DR, #200    GLENDALE, CA 91206

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/25/2017 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 10/31/2017 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/17/2017 Approved RAUL BARAJAS
Footing/Foundation/Slab 11/29/2017 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/30/2017 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/19/2017 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 12/20/2017 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/22/2017 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 12/27/2017 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/12/2018 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/24/2018 Corrections Issued RAUL BARAJAS
Deputy Reinf. Concrete 1/26/2018 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/26/2018 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 1/29/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 1/31/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/12/2018 Partial Approval LUIS BARRALES
Excavation/Setback/Form/Re-Bar 2/15/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/16/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/21/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/2/2018 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 3/5/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/6/2018 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 3/19/2018 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 4/27/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 4/27/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/30/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/18/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 6/7/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/31/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/11/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 9/11/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/13/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/14/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 10/23/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/14/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/21/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/28/2018 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 12/17/2018 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 12/28/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 1/7/2019 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/29/2019 Corrections Issued RAUL BARAJAS
Deputy Reinf. Concrete 9/6/2019 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/6/2019 Partial Approval RAUL BARAJAS
Special/Order Compliance 10/1/2019 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 10/24/2019 Partial Inspection RAUL BARAJAS
Green Building Rough 3/3/2020 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 3/3/2020 Corrections Issued RAUL BARAJAS
Verify Sprinkler Sign Off 3/3/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 3/9/2020 Conditional Approval RAUL BARAJAS
Pre-Inspection 9/3/2020 Partial Inspection RAUL BARAJAS
Pre-Inspection 9/14/2020 Partial Approval RAUL BARAJAS
Pre-Inspection 9/30/2020 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Corrections Issued RAUL BARAJAS
Pre-Inspection 8/19/2021 Corrections Issued RAUL BARAJAS
Structural Steel Frame 8/19/2021 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Corrections Issued RAUL BARAJAS
Wood Frame 1/14/2022 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/9/2022 Partial Inspection RAUL BARAJAS
Deputy Wood Construction 8/9/2022 Conditional Approval RAUL BARAJAS
Green Building Rough 8/9/2022 Partial Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/9/2022 Not Ready for Inspection RAUL BARAJAS
Special/Order Compliance 3/11/2024 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 3/6/2026 Corrections Issued BRIAN SULLIVAN