12006 S AVALON BLVD 90061
Certificate Information: 12006 S AVALON BLVD 90061
- Application / Permit
- 16010-10000-01845
- Plan Check / Job No.
- B16LA06591
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NEW 51'1" x 125'0" OFFICE BLDG. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2016 | GUANG MIN TUNG |
| Corrections Issued | 5/31/2016 | GUANG MIN TUNG |
| Quality Review Completed | 6/7/2016 | FELIX FIGUEROA |
| Building Plans Picked Up | 6/21/2016 | APPLICANT |
| Disabled Access Plans Picked Up | 6/21/2016 | APPLICANT |
| Green Plans Picked Up | 6/21/2016 | APPLICANT |
| Plan Check Approved | 1/15/2020 | JEFFREY TANGONAN |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 3/17/2026 | JAMES POWERS |
| Permit Finaled | 3/17/2026 | ERNESTO CORRAL |
| CofO Issued | 3/17/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/17/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 12/23/2016 | EDBER MACEDO |
| Comm Cor/Mini-Mall | Cleared | 12/23/2016 | EDBER MACEDO |
| Address approval | Cleared | 12/27/2018 | ADRIAN SANCHEZ |
| Permit | Cleared | 1/4/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 1/24/2019 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 1/24/2019 | ERIK BEASLEY |
| Green Code | Cleared | 1/25/2019 | MICKEY YAMASHITA |
| DAS Clearance | Cleared | 1/28/2019 | SHINE LIN |
| Highway dedication | Cleared | 11/8/2019 | JAMES MORALEZ |
Contact Information
| Contractor | Smith & Armani Construction; Lic. No.: 513648-B | 9854 NATIONAL BLVD #222 LOS ANGELES, CA 90034 |
| Engineer | Hamilton, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/20/2020 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 5/27/2021 | Partial Approval | JAMES POWERS |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | TED RIES |
| Verify Sprinkler Sign Off | 11/18/2021 | Not Ready for Inspection | TED RIES |
| Wood Frame | 11/18/2021 | Partial Approval | TED RIES |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 1/4/2022 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 1/19/2022 | Approved | TED RIES |
| Footing/Foundation/Slab | 12/8/2022 | Partial Approval | JAMES POWERS |
| Green Building Rough | 10/10/2023 | Approved | JAMES POWERS |
| Light Gage Steel Frame | 10/10/2023 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 10/10/2023 | Not Ready for Inspection | JAMES POWERS |
| T-Bar Ceiling | 4/15/2024 | Approved | JAMES POWERS |
| Final | 6/12/2025 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 6/12/2025 | Approved | JAMES POWERS |
| Green Building Final | 6/12/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 6/12/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/12/2025 | Approved | JAMES POWERS |
| Wood Frame | 6/12/2025 | Approved | JAMES POWERS |
| Final | 3/11/2026 | Not Ready for Inspection | JAMES POWERS |
| Final | 3/17/2026 | OK to Issue CofO | JAMES POWERS |