349 N MARIE AVE 90042
Certificate Information: 349 N MARIE AVE 90042
- Application / Permit
- 16010-10000-01796
- Plan Check / Job No.
- B16LA06422
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, TYPE VB, SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 1/3/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2016 | PRANITA SHAH |
| Corrections Issued | 6/27/2016 | PRANITA SHAH |
| Quality Review Completed | 6/27/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 7/1/2016 | APPLICANT |
| Green Plans Picked Up | 7/1/2016 | APPLICANT |
| Applicant returned to address corrections | 3/8/2017 | PRANITA SHAH |
| Applicant returned to address corrections | 4/5/2017 | PRANITA SHAH |
| Plan Check Approved | 4/18/2017 | PRANITA SHAH |
| No Progress | 1/24/2018 | PRANITA SHAH |
| Plan Check Approved | 11/15/2018 | PRANITA SHAH |
| Issued | 1/3/2019 | LADBS |
| CofO in Progress | 11/5/2020 | ELMER BLAND |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
| CofO Issued | 11/5/2020 | DEROLD HAUFF |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/19/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 10/19/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 10/19/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 10/19/2016 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 10/19/2016 | ROBERT DUFF |
| Permit | Cleared | 10/19/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 10/19/2016 | RAVIL MANAPOV |
| Green Code | Cleared | 2/21/2017 | DAVID MATSON |
| Low Impact Development | Cleared | 2/21/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 2/21/2017 | RAVIL MANAPOV |
| GPI Written Notices | Cleared | 3/8/2017 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 3/8/2017 | PRANITA SHAH |
Contact Information
| Architect | Hannouche, Samir; Lic. No.: C28484 | 20250 ACACIA 130 NEWPORT BEACH, CA 92660 |
| Contractor | Straight Edge Construction Inc; Lic. No.: 929924-B | P O BOX 695 YORBA LINDA, CA 92885 |
| Engineer | De, Leon Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Houshmand, Mohsen; Lic. No.: C42283 | 4143 COSTERO RISCO SAN CLEMENTE, CA 92673 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Geologist | Van, Meter James L.; Lic. No.: EG2031 | 7702 CAPISTRANO AVE WEST HILLS, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/13/2019 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/11/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/11/2019 | Partial Approval | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 4/16/2019 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Masonry | 4/29/2019 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Masonry | 5/1/2019 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/22/2019 | Partial Approval | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/10/2019 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/10/2019 | Partial Approval | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/10/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/15/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/15/2019 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 7/15/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/21/2019 | Conditional Approval | ROBERT VORHIS |
| Drywall Nailing | 9/16/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2019 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 9/16/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 9/16/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/14/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/14/2019 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 11/26/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/26/2019 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/13/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/13/2020 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/13/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 1/24/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/27/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/30/2020 | Approved | BRAD BESCOS |
| Interior/Exterior Lathing | 3/13/2020 | Approved | ENRIQUE MIRELES |
| Final | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/27/2020 | Approved | ENRIQUE MIRELES |
| Gas Test | 4/27/2020 | Approved | ENRIQUE MIRELES |
| Green Building Final | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/27/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Service/Power Release | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 4/27/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/8/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 5/8/2020 | Approved | ENRIQUE MIRELES |
| Sewer | 7/6/2020 | Approved | CRAIG VAUGHAN |
| Final | 10/21/2020 | Corrections Issued | COREY HUPP |
| Green Building Final | 10/21/2020 | Not Ready for Inspection | COREY HUPP |
| HVAC-Final | 10/21/2020 | Partial Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Approved | COREY HUPP |
| Final | 10/28/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 10/28/2020 | Not Ready for Inspection | COREY HUPP |
| Final | 11/5/2020 | OK to Issue CofO | ELMER BLAND |
| Green Building Final | 11/5/2020 | Approved | ELMER BLAND |