2358 W RIVERSIDE DR 90039
Certificate Information: 2358 W RIVERSIDE DR 90039
- Application / Permit
- 16010-10000-01690
- Plan Check / Job No.
- B16LA06020
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 STORY SFD W/ GARAGE
- Permit Issued
- Issued on 2/27/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2016 | APPLICANT |
| Green Plans Picked Up | 6/7/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2016 | HERNAN ARREOLA |
| Corrections Issued | 7/6/2016 | HERNAN ARREOLA |
| Quality Review Completed | 7/7/2016 | CHAD DOI |
| Building Plans Picked Up | 7/12/2016 | APPLICANT |
| Applicant returned to address corrections | 1/3/2017 | HERNAN ARREOLA |
| Plan Check Approved | 2/24/2017 | HERNAN ARREOLA |
| Issued | 2/27/2017 | LADBS |
| CofO in Progress | 8/4/2022 | THOMAS LOGRASSO |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2016 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2016 | JAMES KHO |
| Permit | Cleared | 8/4/2016 | JAMES KHO |
| Sewer availability | Cleared | 8/4/2016 | JAMES KHO |
| Building over 3-story or 36-ft | Cleared | 8/5/2016 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/5/2016 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 8/5/2016 | ROBERT DUFF |
| Green Code | Cleared | 11/8/2016 | BIJAN EGHTESADY |
| Low Impact Development | Cleared | 11/23/2016 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 11/23/2016 | JAMES MORALEZ |
| GPI Written Notices | Cleared | 12/5/2016 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 12/5/2016 | HERNAN ARREOLA |
| Driveway location | Cleared | 2/7/2017 | TAIMOUR TANAVOLI |
| Disturb/Remove Protected Trees | Cleared | 2/10/2017 | ADRIAN SANCHEZ |
Contact Information
| Architect | Murnane, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | Ferrer M Construction Inc; Lic. No.: 936189-B | 227 SPENCER STREET GLENDALE, CA 91202 |
| Engineer | Khoury, Nader Bulos; Lic. No.: C61402 | 3406 LINDA VISTA TER FALLBROOK, CA 92028 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/31/2017 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 4/17/2017 | Partial Approval | DAVID CHAN |
| Piling/Pier/Caisson | 4/17/2017 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 4/26/2017 | Partial Approval | DAVID CHAN |
| Piling/Pier/Caisson | 4/26/2017 | Partial Approval | DAVID CHAN |
| ELECTRICAL-Rough | 5/1/2017 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 5/1/2017 | Partial Approval | DAVID CHAN |
| Rough-Elec/Plmb/HVAC | 5/1/2017 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 5/4/2017 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 11/20/2017 | Partial Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 6/11/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/16/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/25/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Sewer | 7/27/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/1/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 12/15/2020 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 12/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 12/23/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 4/22/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/23/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/4/2021 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 5/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 5/27/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 6/15/2021 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/11/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 8/11/2021 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/11/2021 | Conditional Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/11/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/29/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 10/29/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 11/2/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 4/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 4/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 4/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 4/20/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 4/20/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/23/2022 | No Access for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 5/23/2022 | No Access for Inspection | THOMAS LOGRASSO |
| Final | 5/23/2022 | No Access for Inspection | THOMAS LOGRASSO |
| Green Building Final | 5/23/2022 | No Access for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 5/23/2022 | No Access for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 6/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 6/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/1/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 6/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 7/5/2022 | Approved | THOMAS LOGRASSO |
| Final | 7/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 7/5/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 7/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/3/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/3/2022 | Approved | THOMAS LOGRASSO |