4850 E FARQUHAR ST 90032

Certificate Information: 4850 E FARQUHAR ST 90032

Application / Permit
16010-10000-01640
Plan Check / Job No.
B16LA05834
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE
Permit Issued
Issued on 5/16/2018
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2016 APPLICANT
Green Plans Picked Up 5/18/2016 APPLICANT
Assigned to Plan Check Engineer 5/26/2016 PRANITA SHAH
Corrections Issued 6/14/2016 PRANITA SHAH
Quality Review Completed 6/17/2016 HOK CHI CHIU
Building Plans Picked Up 6/22/2016 APPLICANT
Applicant returned to address corrections 10/18/2017 PRANITA SHAH
Applicant returned to address corrections 11/7/2017 PRANITA SHAH
Applicant returned to address corrections 4/10/2018 PRANITA SHAH
Plan Check Approved 4/17/2018 PRANITA SHAH
Issued 5/16/2018 LADBS
CofO in Progress 7/21/2025 LILIANA PORTILLO
Permit Finaled 7/24/2025 DEROLD HAUFF
CofO Issued 7/24/2025 DEROLD HAUFF
Permit Finaled 7/24/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/27/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/27/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/27/2016 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/28/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 9/28/2016 RAVIL MANAPOV
Permit Cleared 9/28/2016 CARLOS CUEVA
Sewer availability Cleared 9/28/2016 RAVIL MANAPOV
"D" conditions Cleared 3/22/2017 NICOLE SANCHEZ
"Q" conditions Cleared 3/22/2017 NICOLE SANCHEZ
ZI Cleared 3/22/2017 NICOLE SANCHEZ
Hydrant and Access approval Cleared 4/19/2017 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 4/19/2017 JAMES MORALEZ
Green Code Cleared 6/8/2017 JOHN KLARIN
Excavation more than 5-ft deep Cleared 3/1/2018 CALOSHA APPROVED
GPI Written Notices Cleared 3/1/2018 PRANITA SHAH
Grading Pre-Inspection Cleared 3/1/2018 PRANITA SHAH

Contact Information

Contractor Owner-Builder       ,
Engineer Alvarado, Carlos Humberto; Lic. No.: C19857 745 N WALNUTHAVEN DR      WEST COVINA, CA 91790
Engineer Kim, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2019 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 4/25/2019 Not Ready for Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 5/22/2019 Partial Approval ENRIQUE MIRELES
Grounding or Bonding 5/22/2019 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/18/2019 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 6/25/2019 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/6/2019 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 8/6/2019 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/6/2019 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 8/9/2019 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 8/27/2019 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 8/27/2019 Corrections Issued ENRIQUE MIRELES
Special/Order Compliance 8/27/2019 Partial Inspection RUBEN SALAS
Verify Sprinkler Sign Off 8/27/2019 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 11/25/2019 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 11/26/2019 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/26/2019 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 11/27/2019 No Access for Inspection ENRIQUE MIRELES
Green Building Rough 11/29/2019 Not Ready for Inspection CHARLENE BUSTAMANTE
HVAC-Rough 11/29/2019 Corrections Issued CHARLENE BUSTAMANTE
ELECTRICAL-Rough 12/12/2019 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 12/12/2019 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 12/12/2019 Not Ready for Inspection RUBEN SALAS
Shower Pan 12/12/2019 Not Ready for Inspection RUBEN SALAS
Special/Order Compliance 1/6/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Partial Approval OSVALDO PARAMO
HVAC-Rough 7/23/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/23/2020 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/7/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/7/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 8/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 8/11/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 3/4/2021 Partial Approval COREY HUPP
Verify Sprinkler Sign Off 3/4/2021 Not Ready for Inspection COREY HUPP
Wood Frame 3/8/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 3/10/2021 Corrections Issued COREY HUPP
HVAC-Rough 3/10/2021 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 3/17/2021 Approved COREY HUPP
HVAC-Rough 3/17/2021 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 3/25/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 3/25/2021 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 3/25/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 3/25/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 3/25/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Corrections Issued CRAIG VAUGHAN
Wood Frame 4/7/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Approved OSVALDO PARAMO
Wood Frame 4/15/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 4/21/2021 Approved RUBEN SALAS
Green Building Rough 4/21/2021 Approved RUBEN SALAS
Interior/Exterior Lathing 4/21/2021 Partial Approval RUBEN SALAS
Insulation 4/29/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/29/2021 Approved CRAIG VAUGHAN
Drywall Nailing 5/7/2021 Approved OSVALDO PARAMO
Shower Pan 5/7/2021 Approved OSVALDO PARAMO
Gas Test 7/18/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved AMY COLIN
ELECTRICAL-Final 9/19/2022 No Access for Inspection AMY COLIN
Final 9/29/2022 Corrections Issued AMY COLIN
Green Building Final 9/29/2022 Not Ready for Inspection AMY COLIN
HVAC-Final 9/29/2022 Approved AMY COLIN
PLUMBING-Final 9/29/2022 Approved AMY COLIN
Service/Power Release 9/29/2022 Not Ready for Inspection AMY COLIN
Smoke Detectors 9/29/2022 Approved AMY COLIN
Special/Order Compliance 1/5/2023 Approved AMY COLIN
Final 5/6/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 5/6/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 5/6/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 7/18/2025 Approved LILIANA PORTILLO
Final 7/18/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 7/18/2025 Approved LILIANA PORTILLO
Service/Power Release 7/18/2025 Approved LILIANA PORTILLO