417 N MANSFIELD AVE 90036
Certificate Information: 417 N MANSFIELD AVE 90036
- Application / Permit
- 16010-10000-01569
- Plan Check / Job No.
- B16LA05548
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO- STORY SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE .
- Permit Issued
- Issued on 10/14/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2016 | APPLICANT |
| Green Plans Picked Up | 5/27/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2016 | GEORGE BANNING |
| Corrections Issued | 6/15/2016 | GEORGE BANNING |
| Quality Review Completed | 6/27/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 6/29/2016 | APPLICANT |
| Plan Check Approved | 9/6/2016 | GEORGE BANNING |
| Issued | 10/14/2016 | LADBS |
| CofO in Progress | 10/3/2023 | SCOTT FINNILA |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
| CofO Issued | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2016 | VALENTINO PUEBLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2016 | VALENTINO PUEBLOS |
| Hydrant and Access approval | Cleared | 7/1/2016 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 7/1/2016 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 7/1/2016 | VALENTINO PUEBLOS |
| Disturb/Remove Protected Trees | Cleared | 7/21/2016 | ADRIAN SANCHEZ |
| Green Code | Cleared | 8/30/2016 | ALDO UBAU |
| Low Impact Development | Cleared | 8/30/2016 | SAM NAVID |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Benichou, Ety; Lic. No.: S5263 | 600 S CURSON AVE 311 LOS ANGELES, CA 90036 |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2018 | Approved | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 4/18/2019 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 5/9/2019 | Partial Approval | PIERRE VEGA |
| METHANE-Barrier | 5/9/2019 | Not Ready for Inspection | PIERRE VEGA |
| METHANE-Subgrade | 5/9/2019 | Approved | PIERRE VEGA |
| Protected Tree Letter | 5/9/2019 | Not Ready for Inspection | PIERRE VEGA |
| METHANE-Barrier | 6/11/2019 | Approved | DANIEL GONZALEZ |
| METHANE-Rough | 6/11/2019 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 6/20/2019 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 6/20/2019 | Conditional Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 7/10/2019 | Approved | DANIEL GONZALEZ |
| Protected Tree Letter | 7/10/2019 | Approved | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 7/31/2019 | No Access for Inspection | DANIEL GONZALEZ |
| Deputy Steel/Welding | 8/16/2019 | No Access for Inspection | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2019 | Conditional Approval | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2019 | Not Ready for Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2019 | Conditional Approval | DANIEL GONZALEZ |
| Deputy Drilled-In Anchors | 8/12/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 12/14/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 5/17/2021 | No Access for Inspection | ELMER BLAND |
| Structural Steel Frame | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/11/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/11/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/11/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/14/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/16/2021 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 7/16/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/16/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 7/22/2021 | Corrections Issued | SCOTT FINNILA |
| Insulation | 7/26/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 8/6/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/13/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 8/13/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 10/6/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 4/7/2022 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 5/18/2022 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 5/18/2022 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/20/2022 | Not Ready for Inspection | ADAM ESCOTO |
| HVAC-Final | 5/20/2022 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Final | 6/13/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 6/13/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 6/13/2022 | Approved | ADAM ESCOTO |
| Service/Power Release | 7/1/2022 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 8/26/2022 | Conditional Approval | MICHAEL LEWIS |
| Final | 8/26/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/26/2022 | Partial Approval | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 8/26/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/6/2022 | Conditional Approval | JOSEPH MCGARRY |
| Final | 9/6/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 9/6/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/20/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 10/6/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 10/20/2022 | Partial Inspection | MICHAEL LEWIS |
| Final | 1/6/2023 | Corrections Issued | RICHARD DOCKUS |
| Final | 10/3/2023 | OK to Issue CofO | SCOTT FINNILA |