15214 W EARLHAM ST 90272
Certificate Information: 15214 W EARLHAM ST 90272
- Application / Permit
- 16010-10000-01548
- Plan Check / Job No.
- B16LA05464
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ROOF DECK, 1 LEVEL BASEMENT AND ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/29/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2016 | APPLICANT |
| Green Plans Picked Up | 5/10/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2016 | HERNAN ARREOLA |
| Corrections Issued | 5/24/2016 | RICARDO SUPAN |
| Quality Review Completed | 5/31/2016 | HOK CHI CHIU |
| Building Plans Picked Up | 6/9/2016 | APPLICANT |
| Applicant returned to address corrections | 7/20/2017 | RICARDO SUPAN |
| Applicant returned to address corrections | 11/14/2018 | RICARDO SUPAN |
| Applicant returned to address corrections | 12/24/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/6/2020 | HERNAN ARREOLA |
| Plan Check Approved | 1/16/2020 | HERNAN ARREOLA |
| Issued | 1/29/2020 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/6/2018 | GILBERT URREA |
| Coastal Zone | Cleared | 4/24/2018 | NOAH MCCOY |
| Frnt yard landscape/Water mgmt | Cleared | 4/24/2018 | NOAH MCCOY |
| Landscape for retaining wall | Cleared | 4/24/2018 | NOAH MCCOY |
| Miscellaneous | Cleared | 4/24/2018 | NOAH MCCOY |
| Miscellaneous | Cleared | 4/24/2018 | NOAH MCCOY |
| ZA Case | Cleared | 4/24/2018 | NOAH MCCOY |
| ZI | Cleared | 4/24/2018 | NOAH MCCOY |
| ZI | Cleared | 4/24/2018 | NOAH MCCOY |
| Address approval | Cleared | 9/4/2018 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 11/14/2018 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/29/2019 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 2/7/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 2/7/2019 | NOAH MCCOY |
| Low Impact Development | Cleared | 2/28/2019 | MITESH PATEL |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 3/13/2019 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 3/13/2019 | DENNIS BRAGIN |
| Work Adjacent to Public Way | Cleared | 3/13/2019 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 4/5/2019 | MAHELET GEBEYHU |
| Building over 3-story or 36-ft | Cleared | 5/16/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/16/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/16/2019 | RICARDO SUPAN |
| Grading Pre-Inspection | Cleared | 5/16/2019 | RICARDO SUPAN |
| Green Code | Cleared | 12/19/2019 | MICKEY YAMASHITA |
| Drainage to Storm Drain | Cleared | 1/10/2020 | TAO YANG |
Contact Information
| Architect | Olfati,, Ali; Lic. No.: C22217 | 5199 EAST PACIFIC COAST HWY # 611 LONG BEACH, CA 90804 |
| Contractor | Owner-Builder | , |
| Engineer | Kamboj,, Naresh Chander; Lic. No.: C21893 | 7838 QUIMBY AVE CANOGA PARK, CA 91304 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2020 | Approved | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/11/2020 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 3/12/2020 | Corrections Issued | ANDREW NAVE |
| Piling/Pier/Caisson | 3/16/2020 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 3/17/2020 | Not Ready for Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 3/17/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 3/18/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/19/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/25/2020 | Approved | ANDREW NAVE |
| Piling/Pier/Caisson | 3/25/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/26/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/27/2020 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 3/27/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/31/2020 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 3/31/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/1/2020 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 4/1/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/3/2020 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 4/3/2020 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Partial Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 6/9/2020 | Partial Inspection | ANDREW NAVE |
| PLUMBING-Rough | 9/21/2020 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 9/21/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 9/24/2020 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 9/24/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 9/24/2020 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 11/2/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/4/2020 | Corrections Issued | ANDREW NAVE |
| Deputy Shotcrete | 11/4/2020 | Corrections Issued | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/6/2020 | Approved | ROBERT SHELLY |
| Deputy Shotcrete | 11/6/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 12/15/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 12/15/2020 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/15/2020 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 12/15/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 12/16/2020 | Approved | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 1/6/2021 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 2/5/2021 | Approved | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 3/17/2021 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 6/1/2021 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 3/10/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 4/27/2022 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 4/27/2022 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 5/4/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 5/4/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 5/9/2022 | Partial Inspection | JOHN KIDWELL |
| Wood Frame | 5/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/21/2022 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 6/21/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Conditional Approval | ANDREW NAVE |
| HVAC-Rough | 6/24/2022 | Approved | ANDREW NAVE |
| Insulation | 6/24/2022 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 6/24/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 7/19/2022 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 8/1/2022 | Approved | BRENDAN LOONEY |
| Shower Pan | 8/16/2022 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/20/2022 | Partial Approval | ANDREW NAVE |
| Shower Pan | 9/28/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/11/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Shower Pan | 10/11/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | EVAN COOPER |
| Sewer | 11/6/2023 | Approved | EVAN COOPER |
| Underground Mechanical | 11/15/2023 | Partial Approval | JESUS RODRIGUEZ |
| Enclosure/Fence | 9/20/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 9/20/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 9/20/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 9/20/2024 | Not Ready for Inspection | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 9/20/2024 | Approved | EVAN COOPER |
| Green Building Final | 10/2/2024 | Approved | EVAN COOPER |
| HVAC-Final | 10/2/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/24/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 10/24/2024 | Approved | EVAN COOPER |
| Service/Power Release | 12/11/2024 | Approved | KENNETH NAGLE |