4050 N JENNINGS DR 90032

Certificate Information: 4050 N JENNINGS DR 90032

Application / Permit
16010-10000-01013
Plan Check / Job No.
B16LA03536
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING ( JENNINGS #C ) WITH ATTACHED 2 CAR GARAGE PER LOT SUBDIVISION# AA-2007-1684-PMLA
Permit Issued
Issued on 9/14/2017
Issuing Office
Metro
Current Status
CofO Issued on 4/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2016 APPLICANT
Assigned to Plan Check Engineer 4/21/2016 YOUNG KIM
Green Plans Picked Up 5/10/2016 APPLICANT
Corrections Issued 5/24/2016 NEGAR NEJAD
Quality Review Completed 6/2/2016 BILL STUTSMAN
Building Plans Picked Up 6/6/2016 APPLICANT
Applicant returned to address corrections 10/7/2016 NEGAR NEJAD
Applicant returned to address corrections 6/27/2017 NEGAR NEJAD
Applicant returned to address corrections 8/23/2017 NEGAR NEJAD
Applicant returned to address corrections 8/24/2017 NEGAR NEJAD
Applicant returned to address corrections 8/25/2017 NEGAR NEJAD
Plan Check Approved 9/14/2017 YOUNG KIM
Issued 9/14/2017 LADBS
CofO in Progress 3/19/2021 COREY HUPP
CofO in Progress 3/19/2021 COREY HUPP
Permit Finaled 4/6/2021 DEROLD HAUFF
CofO Issued 4/6/2021 DEROLD HAUFF
Permit Finaled 4/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/2/2016 DAVID MATSON
Address approval Cleared 12/6/2016 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 12/6/2016 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 12/6/2016 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 12/6/2016 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 12/6/2016 ROCHELLE DUNGCA
BHO/Hillside ordinance Cleared 12/6/2016 ROCHELLE DUNGCA
Disturb/Remove Protected Trees Cleared 1/25/2017 ADRIAN SANCHEZ
"D" conditions Cleared 3/2/2017 NICOLE SANCHEZ
"Q" conditions Cleared 3/2/2017 NICOLE SANCHEZ
ZI Cleared 3/2/2017 NICOLE SANCHEZ
Hydrant and Access approval Cleared 6/21/2017 JOHN CONNEALLY
CPC Cleared 7/17/2017 HERMAN VAN BUREN
Landscape for retaining wall Cleared 7/17/2017 HERMAN VAN BUREN
Eng Process Fee Ord 176,300 Cleared 7/24/2017 RAVIL MANAPOV
Sewer availability Cleared 7/24/2017 RAVIL MANAPOV
Permit Cleared 7/28/2017 CRISTIAN GUERRERO
Roof/Waste drainage to street Cleared 7/31/2017 ARMENIA AGUILAR
GPI Written Notices Cleared 8/17/2017 NEGAR NEJAD
Grading Pre-Inspection Cleared 8/17/2017 NEGAR NEJAD
Miscellaneous Cleared 8/17/2017 CRISTIAN GUERRERO
Miscellaneous Cleared 8/17/2017 CRISTIAN GUERRERO
Low Impact Development Cleared 8/21/2017 SAM NAVID
Tract Map conditions Cleared 8/25/2017 JUSTIN BILOW
Excavation more than 5-ft deep Cleared 9/14/2017 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 9/14/2017 BOK GOH

Contact Information

Architect Kivotos, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Engineer Darvasan-Stanciu, George; Lic. No.: L7884 825 E COLTON AVE      REDLANDS, CA 92374
Engineer Haddad, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nazemi, Hassan Steve; Lic. No.: C44100 45 SOLSTICE      IRVINE, CA 92602
Engineer Zhong, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Geologist Barrett, Mark A; Lic. No.: EG2088 11966 HONEYBROOK CT.      MOORPARK, CA 93021

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2018 Approved ENRIQUE MIRELES
Pre-Inspection 9/6/2018 No Access for Inspection ENRIQUE MIRELES
Pre-Inspection 9/7/2018 Approved ENRIQUE MIRELES
Pre-Inspection 3/1/2019 Approved ENRIQUE MIRELES
Piling/Pier/Caisson 4/24/2019 Corrections Issued ENRIQUE MIRELES
Structural Steel Frame 6/7/2019 Partial Approval ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/21/2019 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/25/2019 Partial Approval ENRIQUE MIRELES
Deputy Reinf. Concrete 6/27/2019 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/11/2019 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 7/22/2019 Partial Approval ENRIQUE MIRELES
Deputy Reinf. Concrete 7/23/2019 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 9/16/2019 Approved ENRIQUE MIRELES
Underground Mechanical 10/11/2019 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 10/18/2019 Partial Approval ENRIQUE MIRELES
Deputy Drilled-In Anchors 12/19/2019 Approved ENRIQUE MIRELES
Wood Frame 3/27/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 4/9/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 4/9/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 4/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 4/13/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/13/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 4/15/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 4/15/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/15/2020 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/15/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 4/23/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 8/4/2020 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 8/4/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/7/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Approved ENRIQUE MIRELES
HVAC-Rough 8/7/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/7/2020 Approved ENRIQUE MIRELES
Insulation 8/10/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/13/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 8/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 8/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 8/17/2020 Partial Approval JOSEPH MCGARRY
Drywall Nailing 8/19/2020 Approved DAVID MATSON
Interior/Exterior Lathing 8/20/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/28/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/11/2020 Approved COREY HUPP
Footing/Foundation/Slab 12/11/2020 Approved COREY HUPP
Green Building Rough 12/11/2020 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Not Ready COREY HUPP
Verify Sprinkler Sign Off 12/11/2020 Approved COREY HUPP
Sewer 12/15/2020 Not Ready for Inspection COREY HUPP
Final 2/23/2021 Corrections Issued COREY HUPP
Green Building Final 2/23/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved COREY HUPP
Smoke Detectors 2/23/2021 Approved COREY HUPP
Final 3/2/2021 Corrections Issued COREY HUPP
Green Building Final 3/2/2021 Approved COREY HUPP
Service/Power Release 3/2/2021 Not Ready for Inspection COREY HUPP
Final 3/10/2021 Not Ready for Inspection COREY HUPP
Service/Power Release 3/10/2021 Not Ready for Inspection COREY HUPP
Final 3/16/2021 Corrections Issued COREY HUPP
Service/Power Release 3/16/2021 Approved COREY HUPP
Final 3/18/2021 OK to Issue CofO COREY HUPP