Pre-Inspection
|
8/31/2017
|
Approved
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
9/1/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
9/11/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Grading Pre-Inspection
|
9/27/2017
|
Partial Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/2/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/5/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Interior/Exterior Lathing
|
10/5/2017
|
Corrections Issued
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/10/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/12/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/17/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/18/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
10/18/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/18/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
10/18/2017
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
10/19/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
10/20/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/20/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
10/23/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Piling/Pier/Caisson
|
10/23/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
10/25/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/30/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
11/8/2017
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
11/9/2017
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
11/13/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
11/14/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/14/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/17/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/21/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/27/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/29/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
12/1/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
12/4/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
12/5/2017
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/8/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/13/2017
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/15/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/21/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
12/26/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
12/28/2017
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
1/4/2018
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
1/9/2018
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/16/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
1/19/2018
|
Partial Approval
|
WINSTON DUNNING
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/25/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
1/29/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/30/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/31/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
2/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
2/6/2018
|
Not Ready for Inspection
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/7/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/9/2018
|
Corrections Issued
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
2/16/2018
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/16/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/22/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/27/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/10/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/23/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/27/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/7/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/9/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/11/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/30/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/27/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/11/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
7/25/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
7/30/2018
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
8/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
8/29/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
9/6/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
9/7/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
9/7/2018
|
Approved
|
ERNESTO CORRAL
|
|
Wood Frame
|
9/7/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
9/14/2018
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
9/18/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
9/18/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/19/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
9/19/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
9/25/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/14/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
1/14/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Interior/Exterior Lathing
|
4/18/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
4/24/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
4/24/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Interior/Exterior Lathing
|
5/7/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
7/1/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
7/1/2019
|
Approved
|
ERNESTO CORRAL
|
|
Insulation
|
7/1/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
8/5/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
8/8/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
9/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
10/11/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
10/16/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/23/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
11/13/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
11/14/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
12/19/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
12/31/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
1/6/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
2/3/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Pre-Inspection
|
2/3/2020
|
Approved
|
ERNESTO CORRAL
|
|
Insulation
|
2/18/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
2/20/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Green Building Final
|
5/15/2020
|
Approved
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
5/20/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
5/20/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/20/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
5/20/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
5/20/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
5/20/2020
|
SGSOV Approved
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
5/20/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/20/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
8/28/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
8/28/2020
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
9/22/2020
|
OK to Issue CofO
|
ERNESTO CORRAL
|