2140 S BUTLER AVE 90025

Certificate Information: 2140 S BUTLER AVE 90025

Application / Permit
16010-10000-00799
Plan Check / Job No.
B16LA02672
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
New 6 story mixed use building over two level basement parking garages. Ground floor Type IA commercial, and the 5 story above, Type IIIA, 77 unit apartments. The project utilizes 1) 35% Density Bonus with 10% [of base density of 66 units] 7 units for VLI Household, and Opting for Parking Option 1 per LAMC 12.22.A.25 providing 142 spaces .2) Two on-menu incentives for 20% yard setback reduction & FAR increase (2.95:1).
Permit Issued
Issued on 9/8/2017
Issuing Office
Metro
Current Status
CofO Issued on 10/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/29/2016 APPLICANT
Assigned to Plan Check Engineer 3/24/2016 KESETE HAREGOT
Disabled Access Plans Picked Up 4/4/2016 APPLICANT
Green Plans Picked Up 4/13/2016 APPLICANT
Corrections Issued 5/16/2016 KESETE HAREGOT
Quality Review Completed 5/25/2016 BILL STUTSMAN
Building Plans Picked Up 5/31/2016 APPLICANT
Applicant returned to address corrections 7/12/2016 KESETE HAREGOT
Applicant returned to address corrections 8/10/2016 KESETE HAREGOT
Applicant returned to address corrections 8/16/2016 KESETE HAREGOT
Applicant returned to address corrections 9/12/2016 KESETE HAREGOT
Applicant returned to address corrections 8/1/2017 KESETE HAREGOT
Plan Check Approved 9/8/2017 KESETE HAREGOT
Issued 9/8/2017 LADBS
TCO Issued (Expire Date: 06-01-2022) 12/3/2021 DAVID TSAU
TCO Issued (Expire Date: 12-24-2022) 6/27/2022 DAVID TSAU
TCO Issued (Expire Date: 07-16-2023) 1/17/2023 HENRY BAGHDASSARIAN
CofO in Progress 9/5/2023 DERRICK SPENCER
Permit Finaled 10/5/2023 HENRY BAGHDASSARIAN
CofO Issued 10/5/2023 HENRY BAGHDASSARIAN
Permit Finaled 10/5/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2016 RAVIL MANAPOV
Low Impact Development Cleared 7/7/2016 MARTIN FRAGOSO
Address approval Cleared 7/19/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 10/25/2016 ROBERT DUFF
Green Code Cleared 12/16/2016 JOHN KLARIN
DAS Clearance Cleared 12/20/2016 KESETE HAREGOT
Fire Marshall Fire Life Safety Cleared 12/20/2016 MENOA AGHAJANI
Highway dedication Cleared 12/20/2016 CHEN ZHANG
CPC Cleared 1/25/2017 ULISES GONZALEZ
Internal circulation Cleared 6/2/2017 EDER ROMERO
Roof/Waste drainage to street Cleared 6/9/2017 KATHLEEN HUGHEY
Sewer availability Cleared 6/9/2017 OSCAR GUTIERREZ
Work Adjacent to Public Way Cleared 6/27/2017 WARREN LIU
"T" removal Cleared 8/2/2017 ULISES GONZALEZ
"Q" conditions Cleared 8/16/2017 ULISES GONZALEZ
DCP conditions approval Cleared 8/16/2017 KENNETH LE
Frnt yard landscape/Water mgmt Cleared 8/16/2017 ULISES GONZALEZ
Housing density bonus Cleared 8/16/2017 KENNETH LE
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Miscellaneous Cleared 8/16/2017 ULISES GONZALEZ
Opn space landscape/Water mgmt Cleared 8/16/2017 ULISES GONZALEZ
CPC Cleared 8/21/2017 ULISES GONZALEZ
Site Plan review Cleared 8/21/2017 ULISES GONZALEZ
Building over 3-story or 36-ft Cleared 8/24/2017 CALOSHA APPROVED
Specific Plan Cleared 8/25/2017 EDER ROMERO
Bicycle Parking Cleared 8/29/2017 OSCAR GUTIERREZ

Contact Information

Architect Ashofteh, Farhad; Lic. No.: C19728 833 HAVERFORD AVENUE      PACIFIC PALISADES, CA 90272
Contractor Hy-Max Building Corp; Lic. No.: 702339-B 28376 CONSTELLATION ROAD      VALENCIA, CA 91355
Engineer Chen, Shaofu; Lic. No.: C76834 5589 CARMELLO COURT      RANCHO CUCAMONGA, CA 91739
Engineer Ghodsi, Afshin; Lic. No.: S3248 3621 HARBOR BL 125      SANTA ANA, CA 92704

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/13/2017 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 4/12/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/25/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/25/2018 Partial Approval DANIEL MC AULIFFE
Green Building Rough 4/26/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 4/26/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 4/26/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 4/27/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/14/2018 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 5/14/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/15/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/16/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/16/2018 Approved DANIEL MC AULIFFE
Piling/Pier/Caisson 5/16/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/17/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/17/2018 Approved DANIEL MC AULIFFE
Green Building Rough 5/17/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 5/17/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 5/17/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/18/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/18/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/22/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/22/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/22/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/23/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/23/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/24/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 5/24/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/24/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/25/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 5/25/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/31/2018 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/1/2018 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/5/2018 Approved DANIEL MC AULIFFE
Green Building Rough 6/5/2018 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 6/5/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 6/5/2018 Not Ready for Inspection DANIEL MC AULIFFE
Pre-Inspection 6/6/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/7/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/8/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/8/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/12/2018 No Result Entered DANIEL MC AULIFF
Deputy Shotcrete 6/12/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/12/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/13/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/14/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/15/2018 Approved DANIEL MC AULIFFE
Deputy Shotcrete 6/15/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/20/2018 Partial Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 6/21/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/22/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/25/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 6/28/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 7/3/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 7/31/2018 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 8/1/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 8/2/2018 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 8/9/2018 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 8/13/2018 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 8/28/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/5/2018 Approved DANIEL MC AULIFFE
Green Building Rough 9/5/2018 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 9/5/2018 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 9/5/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/6/2018 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 9/6/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/12/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/13/2018 Approved DANIEL MC AULIFFE
Green Building Rough 9/13/2018 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 9/13/2018 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 9/13/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/14/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/19/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/19/2018 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/20/2018 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/21/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 9/24/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/25/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/26/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/26/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 9/27/2018 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 9/28/2018 Partial Approval TONY HARTONO
Deputy Reinf. Masonry 10/3/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/4/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/4/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 10/5/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/5/2018 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/12/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/15/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/15/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/16/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/2/2018 Conditional Approval DANIEL MC AULIFFE
Green Building Rough 11/2/2018 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 11/2/2018 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 11/2/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/6/2018 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/6/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/8/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/8/2018 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/14/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/15/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/16/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/16/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/19/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/19/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/20/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/27/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/28/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/28/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/29/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/29/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/30/2018 Conditional Approval DANIEL MC AULIFFE
Green Building Rough 12/3/2018 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 12/3/2018 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 12/3/2018 Partial Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/3/2018 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/4/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/5/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/7/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/7/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 12/7/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/11/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 12/11/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/12/2018 Conditional Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 12/12/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/14/2018 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/19/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 12/19/2018 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/21/2018 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 12/21/2018 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 12/24/2018 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 12/28/2018 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 1/21/2019 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 1/24/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/29/2019 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 2/4/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/8/2019 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/12/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/20/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/20/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 2/21/2019 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 2/27/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 2/28/2019 Approved DANIEL MC AULIFFE
Deputy Reinf. Masonry 3/1/2019 Conditional Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 3/1/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 3/14/2019 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 3/14/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 3/27/2019 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/5/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 4/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 4/16/2019 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/22/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 4/24/2019 Partial Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Partial Inspection DANIEL MC AULIFFE
Wood Frame 5/22/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 5/24/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 5/30/2019 Partial Approval DANIEL MC AULIFFE
Wood Frame 6/18/2019 Not Ready for Inspection TONY HARTONO
Deputy Drilled-In Anchors 6/25/2019 Approved TONY HARTONO
Deputy Steel/Welding 6/25/2019 Conditional Approval TONY HARTONO
Deputy Steel/Welding 6/26/2019 Conditional Approval TONY HARTONO
Wood Frame 6/28/2019 Corrections Issued TED RIES
Deputy Steel/Welding 7/2/2019 Approved TONY HARTONO
Deputy Wood Construction 7/5/2019 Approved DERRICK SPENCER
Wood Frame 7/5/2019 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 7/9/2019 Approved TONY HARTONO
Deputy Steel/Welding 7/9/2019 Conditional Approval JASON BORUTA
Wood Frame 7/9/2019 Corrections Issued TONY HARTONO
Deputy Steel/Welding 7/10/2019 Approved NICK LAROCCA
Deputy Wood Construction 7/11/2019 Approved NICK LAROCCA
Structural Steel Frame 7/11/2019 Partial Inspection NICK LAROCCA
Special/Order Compliance 7/18/2019 Corrections Issued SORIN CIRSTOIU
Wood Frame 7/18/2019 Partial Inspection TONY HARTONO
Wood Frame 8/2/2019 Partial Inspection TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 8/6/2019 Partial Approval TONY HARTONO
Insulation 8/6/2019 Partial Approval TONY HARTONO
Deputy Reinf. Masonry 8/14/2019 Approved TONY HARTONO
Deputy Reinf. Masonry 8/15/2019 Approved NICK LAROCCA
Deputy Reinf. Masonry 8/16/2019 Approved TONY HARTONO
Drywall Nailing 8/16/2019 Partial Approval TONY HARTONO
Insulation 8/16/2019 Partial Approval TONY HARTONO
Special/Order Compliance 8/16/2019 Partial Inspection TONY HARTONO
Wood Frame 8/16/2019 Partial Approval TONY HARTONO
Drywall Nailing 8/23/2019 Partial Approval DERRICK SPENCER
Wood Frame 8/23/2019 Partial Approval DERRICK SPENCER
Wood Frame 9/4/2019 Partial Approval DERRICK SPENCER
Wood Frame 9/11/2019 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/18/2019 Partial Approval DERRICK SPENCER
Wood Frame 9/23/2019 Partial Approval TONY HARTONO
Deputy Reinf. Masonry 9/25/2019 Approved TONY HARTONO
Masonry Wall/Backfill 9/25/2019 Approved JASON BORUTA
Pre-Inspection 9/25/2019 Approved ALAN NOVAK
Pre-Inspection 9/25/2019 Approved JASON BORUTA
Special/Order Compliance 9/25/2019 Corrections Issued TONY HARTONO
Special/Order Compliance 9/25/2019 Partial Inspection JOHN DODGE
Special/Order Compliance 9/25/2019 Partial Inspection PAUL DAVIDSON
Special/Order Compliance 9/25/2019 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 9/30/2019 Partial Approval TONY HARTONO
Insulation 10/3/2019 Partial Approval TONY HARTONO
Drywall Nailing 10/11/2019 Partial Approval TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Partial Approval TONY HARTONO
Insulation 10/16/2019 Partial Approval TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Partial Approval TONY HARTONO
Wood Frame 10/22/2019 Partial Approval TONY HARTONO
Wood Frame 10/25/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 10/29/2019 Approved DERRICK SPENCER
Masonry Wall/Backfill 10/29/2019 Partial Approval DERRICK SPENCER
Insulation 11/19/2019 Partial Approval DERRICK SPENCER
Insulation 11/21/2019 Partial Approval DERRICK SPENCER
Insulation 11/22/2019 Partial Approval DERRICK SPENCER
Drywall Nailing 12/18/2019 Partial Approval DERRICK SPENCER
Insulation 1/6/2020 Partial Approval DERRICK SPENCER
Wood Frame 1/10/2020 Partial Approval DERRICK SPENCER
Insulation 2/4/2020 Not Ready for Inspection DERRICK SPENCER
Insulation 2/11/2020 Partial Approval DERRICK SPENCER
Insulation 2/19/2020 Partial Approval DERRICK SPENCER
Wood Frame 2/19/2020 Partial Approval DERRICK SPENCER
Deputy Wood Construction 3/17/2020 Approved DERRICK SPENCER
Insulation 3/17/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 3/17/2020 Partial Approval DERRICK SPENCER
Drywall Nailing 3/23/2020 Not Ready for Inspection DERRICK SPENCER
Insulation 3/27/2020 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 3/27/2020 Partial Approval DERRICK SPENCER
Drywall Nailing 4/17/2020 Not Ready for Inspection DERRICK SPENCER
Insulation 4/17/2020 Not Ready for Inspection DERRICK SPENCER
Insulation 4/21/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/21/2020 Partial Approval DERRICK SPENCER
Insulation 4/29/2020 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 4/29/2020 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 5/5/2020 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 5/6/2020 Partial Approval DERRICK SPENCER
Insulation 5/12/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/12/2020 Partial Approval DERRICK SPENCER
Insulation 5/14/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/14/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/18/2020 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 6/16/2020 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 6/23/2020 Approved DERRICK SPENCER
Masonry Wall/Backfill 9/22/2020 Partial Approval DERRICK SPENCER
Wood Frame 9/22/2020 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 10/13/2020 Approved DERRICK SPENCER
Drywall Nailing 10/23/2020 Partial Approval JOHN DODGE
Drywall Nailing 12/17/2020 Approved DERRICK SPENCER
T-Bar Ceiling 12/17/2020 Partial Approval DERRICK SPENCER
Grading Pre-Inspection 1/6/2021 Approved DERRICK SPENCER
Masonry Wall/Backfill 2/11/2021 Approved DERRICK SPENCER
Final 5/19/2021 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 5/19/2021 Approved DERRICK SPENCER
Green Building Final 5/19/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 5/19/2021 Approved DERRICK SPENCER
Reinforced Masonry Frame 5/19/2021 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved DERRICK SPENCER
Smoke Detectors 5/19/2021 Approved DERRICK SPENCER
Wood Frame 5/19/2021 Approved DERRICK SPENCER
Final 6/17/2021 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/17/2021 Not Ready for Inspection DERRICK SPENCER
Final 9/16/2021 Not Ready for Inspection DERRICK SPENCER
Green Building Final 9/16/2021 Approved DERRICK SPENCER
Final 9/22/2021 Partial Approval DERRICK SPENCER
Verify Rec and Parks Fee Memo 10/5/2021 Approved DERRICK SPENCER
Final 10/26/2021 Not Ready for Inspection DERRICK SPENCER
Final 11/23/2021 Not Ready for Inspection DERRICK SPENCER
Final 1/7/2022 Not Ready for Inspection DERRICK SPENCER
Final 3/30/2022 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 4/12/2022 Partial Inspection DAVID TSAU
Final 5/4/2022 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 5/4/2022 Approved DERRICK SPENCER
Special/Order Compliance 11/30/2022 Approved DERRICK SPENCER
Special/Order Compliance 6/21/2023 Approved DERRICK SPENCER
Final 9/1/2023 OK to Issue CofO DERRICK SPENCER