616 N BELMONT AVE 90026
Certificate Information: 616 N BELMONT AVE 90026
- Application / Permit
- 16010-10000-00320
- Plan Check / Job No.
- B16LA01245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW CONSTRUCTION FREE STANDING STATE APPROVED MODULAR STRUCTURES. SMALL LOT DEVELOPMENT VTT 73020. (LOT #1)
- Permit Issued
- Issued on 4/18/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2016 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 2/16/2016 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 2/17/2016 | JAMESON LEE |
| Building Plans Picked Up | 2/18/2016 | APPLICANT |
| Applicant returned to address corrections | 4/19/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/25/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/3/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/25/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/20/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/20/2016 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/19/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/31/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/1/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/8/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/24/2017 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 4/28/2017 | APPLICANT |
| Applicant returned to address corrections | 2/21/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/15/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/10/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/12/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 4/16/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 4/18/2018 | KAMRAN GHOTBI RAVANDI |
| Issued | 4/18/2018 | LADBS |
| CofO in Progress | 12/21/2021 | SCOTT FINNILA |
| Permit Finaled | 12/22/2021 | RONALD MYRICK |
| CofO Issued | 12/22/2021 | RONALD MYRICK |
| Permit Finaled | 12/22/2021 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| Highway dedication | Cleared | 3/24/2016 | SEVAK ISAKHAYAN |
| Sewer availability | Cleared | 3/25/2016 | JAMES KHO |
| Address approval | Cleared | 1/3/2017 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 1/3/2017 | JACOB BIGLER |
| Low Impact Development | Cleared | 9/26/2017 | MICHAEL SCADUTO |
| Hydrant and Access approval | Cleared | 2/5/2018 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 2/8/2018 | ZEMAMU GEBREWOLD |
| Green Code | Cleared | 2/13/2018 | MARCUS LEVIAS |
| Miscellaneous | Cleared | 2/13/2018 | BRIAN CARR |
| Tract Map conditions | Cleared | 2/13/2018 | BRIAN CARR |
| ZA Case | Cleared | 2/13/2018 | BRIAN CARR |
| ZI | Cleared | 2/13/2018 | BRIAN CARR |
| ZI | Cleared | 2/13/2018 | BRIAN CARR |
| Miscellaneous | Cleared | 4/11/2018 | ZEMAMU GEBREWOLD |
| Permit | Cleared | 4/11/2018 | ZEMAMU GEBREWOLD |
Contact Information
| Contractor | Completely Concrete Structures; Lic. No.: 1012623-C-8 | PO BOX 862010 LOS ANGELES, CA 90086 |
| Engineer | Lothrop, Shawn Duane; Lic. No.: S5627 | 29970 TECHNOLOGY DRIVE SUITE 212 MURRIETA, CA 92563 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Barrier | 8/10/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Subgrade | 8/10/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/17/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Barrier | 8/17/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Subgrade | 8/17/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Barrier | 8/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Subgrade | 8/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/29/2018 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/29/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/29/2018 | Partial Approval | SCOTT FINNILA |
| METHANE-Barrier | 8/29/2018 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Subgrade | 8/29/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/30/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/15/2018 | No Access for Inspection | MICHAEL FAUNCE |
| METHANE-Barrier | 10/15/2018 | No Access for Inspection | MICHAEL FAUNCE |
| METHANE-Subgrade | 10/15/2018 | No Access for Inspection | MICHAEL FAUNCE |
| Footing/Foundation/Slab | 10/19/2018 | Corrections Issued | SCOTT FINNILA |
| METHANE-Barrier | 10/19/2018 | Partial Approval | SCOTT FINNILA |
| METHANE-Subgrade | 10/19/2018 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 3/22/2019 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/4/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/9/2019 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/17/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/17/2019 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 12/11/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 12/16/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 12/16/2019 | Approved | SCOTT FINNILA |
| Green Building Rough | 12/16/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 5/28/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 6/4/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 6/10/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 6/11/2021 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 6/11/2021 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 7/6/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/31/2021 | Approved | SCOTT FINNILA |
| Final | 8/31/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/31/2021 | Approved | SCOTT FINNILA |
| Green Building Final | 8/31/2021 | Approved | SCOTT FINNILA |
| MERV13>=Final | 8/31/2021 | Approved | SCOTT FINNILA |
| MERV13>=Rough | 8/31/2021 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 8/31/2021 | Approved | SCOTT FINNILA |
| METHANE-Final | 8/31/2021 | Approved | SCOTT FINNILA |
| METHANE-Rough | 8/31/2021 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 8/31/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 8/31/2021 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 8/31/2021 | Approved | SCOTT FINNILA |
| Final | 12/6/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 12/20/2021 | Approved | SCOTT FINNILA |
| Final | 12/20/2021 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 12/20/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/20/2021 | Approved | SCOTT FINNILA |