1325 N CHAUTAUQUA BLVD 90272
Certificate Information: 1325 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 16010-10000-00314
- Plan Check / Job No.
- B16LA01219
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING (3425 SF) WITH BASEMENT AND ATTACHED GARAGE (426 SF) WITH ELEVATOR.
- Permit Issued
- Issued on 6/13/2016
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2016 | PRANITA SHAH |
| Green Plans Picked Up | 2/18/2016 | APPLICANT |
| Corrections Issued | 3/2/2016 | PRANITA SHAH |
| Quality Review Completed | 3/3/2016 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/4/2016 | APPLICANT |
| Applicant returned to address corrections | 3/17/2016 | PRANITA SHAH |
| Applicant returned to address corrections | 4/28/2016 | PRANITA SHAH |
| Plan Check Approved | 5/6/2016 | PRANITA SHAH |
| Issued | 6/13/2016 | LADBS |
| Permit Expired-Status Void | 2/27/2020 | ROBERT SHELLY |
| Re-Activate Permit | 3/2/2020 | VINCENT COTTON |
| CofO in Progress | 6/24/2020 | ROBERT SHELLY |
| Permit Finaled | 6/24/2020 | VINCENT COTTON |
| CofO Issued | 6/24/2020 | VINCENT COTTON |
| Permit Finaled | 6/24/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 3/8/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 3/8/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 3/8/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 3/8/2016 | ERIK MUNOZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2016 | ERIK MUNOZ |
| Permit | Cleared | 3/8/2016 | ERIK MUNOZ |
| Sewer availability | Cleared | 3/8/2016 | ERIK MUNOZ |
| Green Code | Cleared | 4/28/2016 | ALDO UBAU |
| Green Code | Cleared | 4/28/2016 | ALDO UBAU |
| Hydrant and Access approval | Cleared | 4/28/2016 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 4/28/2016 | VIJAY DESAI |
| Roof/Waste drainage to street | Cleared | 4/28/2016 | NATALIE MOORE |
Contact Information
| Contractor | So Cal Custom Construction & Design Inc; Lic. No.: 985849-B | 11990 SAN VICENTE BLVD LOS ANGELES, CA 90049 |
| Engineer | Amoroso, Gregory Michael; Lic. No.: L8771 | 24269 PALO VERDE DR VALENCIA, CA 91354 |
| Engineer | Shepphird, William Reynolds; Lic. No.: C59229 | P O BOX 34455 LOS ANGELES, CA 90034 |
| Geologist | Miller, Jonathan Steven; Lic. No.: EG2391 | 2800 NEILSON WAY #210 SANTA MONICA, CA 90405 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 6/16/2016 | Not Ready for Inspection | DAVID LEE |
| Deputy Grading | 7/8/2016 | No Access for Inspection | KENNETH NAGLE |
| Deputy Grading | 7/13/2016 | No Access for Inspection | KENNETH NAGLE |
| Piling/Pier/Caisson | 8/10/2016 | Partial Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/31/2016 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/3/2016 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 10/5/2016 | No Access for Inspection | KENNETH NAGLE |
| Underground Mechanical | 11/8/2016 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 11/14/2016 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 11/21/2016 | Partial Approval | KENNETH NAGLE |
| Deputy Shotcrete | 12/12/2016 | No Access for Inspection | KENNETH NAGLE |
| Deputy Shotcrete | 12/14/2016 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 1/5/2017 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 1/5/2017 | Corrections Issued | KENNETH NAGLE |
| Deputy Shotcrete | 1/6/2017 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 1/10/2017 | Partial Approval | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 1/17/2017 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 2/24/2017 | Corrections Issued | VINCENT SCIPIONI |
| Footing/Foundation/Slab | 2/24/2017 | Partial Approval | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 2/28/2017 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 3/23/2017 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 3/31/2017 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 4/4/2017 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 4/5/2017 | Partial Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 4/6/2017 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 4/27/2017 | Conditional Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/27/2017 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2017 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/12/2017 | No Access for Inspection | KENNETH NAGLE |
| Green Building Rough | 10/12/2017 | No Access for Inspection | KENNETH NAGLE |
| Verify Sprinkler Sign Off | 10/12/2017 | No Access for Inspection | KENNETH NAGLE |
| Wood Frame | 10/12/2017 | No Access for Inspection | KENNETH NAGLE |
| Wood Frame | 10/19/2017 | Corrections Issued | KENNETH NAGLE |
| Wood Frame | 10/30/2017 | Partial Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2017 | Partial Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 1/25/2018 | No Access for Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 1/26/2018 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2018 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 3/23/2018 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 3/30/2018 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 3/30/2018 | Corrections Issued | RICHARD STEINBACH |
| HVAC-Rough | 4/3/2018 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Rough | 4/6/2018 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 4/11/2018 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 4/19/2018 | Corrections Issued | RICHARD STEINBACH |
| Green Building Rough | 4/19/2018 | Corrections Issued | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 4/19/2018 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 5/9/2018 | Partial Approval | JOHN LUMB |
| Green Building Rough | 5/9/2018 | Approved | JOHN LUMB |
| BUILDING-Rough-Frame | 5/11/2018 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 5/23/2018 | Partial Approval | RICHARD STEINBACH |
| Drywall Nailing | 6/15/2018 | Approved | RICHARD STEINBACH |
| Shower Pan | 6/15/2018 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/19/2018 | Partial Approval | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/22/2018 | Approved | RYAN MCGILL |
| BUILDING-Rough-Frame | 11/21/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/21/2018 | Approved | MICHAEL PELHAM |
| Gas Test | 11/21/2018 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 11/21/2018 | SGSOV Not Ready | MICHAEL PELHAM |
| Service/Power Release | 2/12/2020 | Corrections Issued | DANNY TOLENTINO |
| Gas Test | 2/19/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| Service/Power Release | 2/19/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| Special/Order Compliance | 2/27/2020 | Permit Expired-Status Void | ROBERT SHELLY |
| Final | 4/16/2020 | Conditional Approval | DANNY TOLENTINO |
| Green Building Final | 4/16/2020 | Approved | DANNY TOLENTINO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2020 | SGSOV Approved | DANNY TOLENTINO |
| Service/Power Release | 4/16/2020 | Approved | DANNY TOLENTINO |
| Smoke Detectors | 4/16/2020 | Approved | DANNY TOLENTINO |