2265 N FAIR OAK VIEW TER 90039
Certificate Information: 2265 N FAIR OAK VIEW TER 90039
- Application / Permit
- 16010-10000-00073
- Plan Check / Job No.
- B16LA00339
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SINGLE FAMILY HOUSE
- Permit Issued
- Issued on 1/5/2018
- Issuing Office
- Metro
- Current Status
- Issued on 1/5/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/12/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2016 | HASMIK KORKIS |
| Green Plans Picked Up | 2/3/2016 | APPLICANT |
| Corrections Issued | 2/12/2016 | HASMIK KORKIS |
| Quality Review Completed | 2/17/2016 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/22/2016 | APPLICANT |
| Applicant returned to address corrections | 2/24/2016 | HASMIK KORKIS |
| Applicant returned to address corrections | 4/7/2016 | LARRY LEE |
| Applicant returned to address corrections | 4/21/2016 | LARRY LEE |
| Applicant returned to address corrections | 5/11/2016 | LARRY LEE |
| Applicant returned to address corrections | 5/24/2016 | LARRY LEE |
| Applicant returned to address corrections | 6/22/2017 | LARRY LEE |
| Applicant returned to address corrections | 10/11/2017 | LARRY LEE |
| Applicant returned to address corrections | 10/25/2017 | LARRY LEE |
| Plan Check Approved | 11/27/2017 | LARRY LEE |
| Issued | 1/5/2018 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2016 | JACOB BIGLER |
| Address approval | Cleared | 6/27/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 6/27/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 6/27/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 6/27/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 6/27/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 6/27/2016 | JACOB BIGLER |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2016 | JACOB BIGLER |
| Sewer availability | Cleared | 6/27/2016 | JACOB BIGLER |
| Green Code | Cleared | 9/12/2017 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 9/18/2017 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/25/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/25/2017 | CELINA MORENO |
Contact Information
| Architect | Heeb, Derek M; Lic. No.: C32338 | 3974 SAN RAFAEL AVENUE LOS ANGELES, CA 90065 |
| Contractor | Owner-Builder | , |
| Engineer | Manesh, Behnam Abraham; Lic. No.: C38454 | 6911 HAYVENHURST AVE STE 201 VAN NUYS, CA 91406 |
| Engineer | Tsai, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Fishburn, Scott David; Lic. No.: EG2114 | 1545 VICTORY BLVD. GLENDALE, CA 91201 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2018 | Not Ready for Inspection | DAVID CHAN |
| Piling/Pier/Caisson | 5/20/2019 | Approved | DAVID CHAN |
| Deputy Reinf. Concrete | 5/21/2019 | Conditional Approval | DAVID CHAN |
| Footing/Foundation/Slab | 5/29/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 5/31/2019 | Conditional Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2019 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 6/10/2019 | Not Ready for Inspection | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 6/19/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 6/19/2019 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 7/16/2019 | Conditional Approval | DAVID CHAN |
| Footing/Foundation/Slab | 7/16/2019 | Partial Approval | DAVID CHAN |
| Deputy Steel/Welding | 7/17/2019 | Conditional Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 7/22/2019 | Conditional Approval | DAVID CHAN |
| PLUMBING-Rough | 9/24/2019 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 10/2/2019 | Partial Approval | DAVID CHAN |
| Masonry Wall/Backfill | 10/23/2019 | Partial Approval | DAVID CHAN |
| Masonry Wall/Backfill | 4/13/2020 | Partial Inspection | DAVID CHAN |
| Masonry Wall/Backfill | 10/8/2020 | Corrections Issued | DONALD CRICHLOW |
| Masonry Wall/Backfill | 10/22/2020 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 12/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Masonry Wall/Backfill | 1/14/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Masonry Wall/Backfill | 1/20/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Masonry Wall/Backfill | 2/3/2021 | No Access for Inspection | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 2/4/2021 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 3/4/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/28/2021 | Partial Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Partial Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 8/3/2021 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 8/3/2021 | Approved | RUBEN SALAS |
| Masonry Wall/Backfill | 8/17/2021 | Corrections Issued | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 8/20/2021 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 8/31/2021 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/16/2021 | Partial Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 10/12/2021 | Partial Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 10/25/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 10/27/2021 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 11/3/2021 | Approved | AMY COLIN |
| Special/Order Compliance | 11/5/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 12/21/2021 | Partial Inspection | AMY COLIN |
| Masonry Wall/Backfill | 12/28/2021 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | THOMAS LOGRASSO |
| Structural Steel Frame | 3/17/2022 | Partial Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 4/25/2022 | Partial Inspection | ADAM ESCOTO |
| Special/Order Compliance | 4/28/2022 | Corrections Issued | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/9/2022 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/26/2022 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Rough | 5/26/2022 | Partial Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 5/26/2022 | Partial Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 5/26/2022 | Partial Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 1/17/2023 | Partial Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/9/2023 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 5/9/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/9/2023 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/23/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 6/27/2023 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 6/27/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 6/27/2023 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 6/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 7/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 7/13/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/20/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 9/22/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 9/22/2023 | Approved | THOMAS LOGRASSO |
| Pre-Inspection | 10/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 10/16/2023 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/24/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 10/24/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 10/24/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 12/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/7/2024 | Partial Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 2/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 5/15/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 5/31/2024 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 6/3/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/28/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/25/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 11/6/2024 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 1/13/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/31/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/31/2025 | Partial Inspection | HAMIK HARTOUNIAN |