530 S MAPLETON DR 90024
Certificate Information: 530 S MAPLETON DR 90024
- Application / Permit
- 15047-20000-02076
- Plan Check / Job No.
- B15VN16951
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH SPA AT BASEMENT.
- Permit Issued
- Issued on 1/20/2016
- Issuing Office
- Valley
- Current Status
- Issued on 1/20/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2015 | RODNEY SAMIIAN |
| Corrections Issued | 12/21/2015 | RODNEY SAMIIAN |
| Plan Check Approved | 1/20/2016 | RODNEY SAMIIAN |
| Issued | 1/20/2016 | LADBS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Tyler Development Corporation; Lic. No.: 451882-B | 1932 COTNER AVE LOS ANGELES, CA 90025 |
| Engineer | Liston, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Naraghi-Arani, Kamran; Lic. No.: C40985 | 30423 CANWOOD STREET SUITE 223 AGOURA HILLS, CA 91301 |
| Geologist | Van, Meter James L.; Lic. No.: EG2031 | 4517 COLBATH AVE #5 SHERMAN OAKS, CA 91423 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2016 | Approved | JOHN REGAN |
| Grounding or Bonding | 5/17/2016 | Conditional Approval | JOHN REGAN |
| Pre-Gunite | 5/17/2016 | Approved | JOHN REGAN |
| Deputy Shotcrete | 5/23/2016 | Approved | DANIEL ORRANTE |
| Final | 9/26/2019 | No Access for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2019 | SGSOV Not Ready | MATT KELLERMAN |
| Special/Order Compliance | 3/10/2025 | Corrections Issued | MICHAEL PELHAM |
| Pool Piping | 10/20/2025 | Corrections Issued | DANIEL VERA |
| Pool Piping | 11/6/2025 | Not Ready for Inspection | DANIEL VERA |
| Rough-Plumbing | 11/6/2025 | Not Ready for Inspection | DANIEL VERA |
| Pre-Inspection | 5/14/2026 | Not Ready for Inspection | DAVID SCANTLIN |