1422 N DEVLIN DR 90069
Certificate Information: 1422 N DEVLIN DR 90069
- Application / Permit
- 15047-10003-00331
- Plan Check / Job No.
- B18LA22431
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- SUPPLEMENTAL TO PERMIT# 15047-10000-00331, STRUCTURAL POOL SHELL (N) SWIMMING POOL UNDER (N) SFD
- Permit Issued
- Issued on 12/18/2018
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | LARRY LEE |
| Corrections Issued | 11/6/2018 | LARRY LEE |
| Quality Review Completed | 11/15/2018 | WING SUEN |
| Building Plans Picked Up | 11/19/2018 | APPLICANT |
| Plan Check Approved | 12/12/2018 | LARRY LEE |
| Issued | 12/18/2018 | LADBS |
| Permit Finaled | 4/15/2021 | BRAD BESCOS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Scott, L. Utterstrom; Lic. No.: C34658 | , |
| Contractor | Steiner Douglas Construction Inc; Lic. No.: 916002-B | 1541 PARKWAY LOOP STE A TUSTIN, CA 92780 |
| Engineer | Fischer, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
| Engineer | J, Shniderman; Lic. No.: C20524 | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 2/12/2019 | Conditional Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 7/31/2020 | Partial Approval | RAUL BARAJAS |
| Final | 7/31/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Gunite | 7/31/2020 | Approved | RAUL BARAJAS |