4240 N LAUREL CANYON BLVD 91604
Certificate Information: 4240 N LAUREL CANYON BLVD 91604
- Application / Permit
- 15030-10000-06135
- Plan Check / Job No.
- B15LA09247
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Site grading for backfill and drainage for new 4 story 32 unit condo.
- Permit Issued
- Issued on 11/17/2015
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/16/2017
Permit Application Status History
Submitted | 7/7/2015 | APPLICANT |
Assigned to Plan Check Engineer | 7/9/2015 | CELESTE MORRIS |
Corrections Issued | 7/13/2015 | CELESTE MORRIS |
Green Plans Picked Up | 7/30/2015 | APPLICANT |
Building Plans Picked Up | 8/19/2015 | APPLICANT |
Quality Review Completed | 9/8/2015 | CATHERINE NUEZCA GABA |
Applicant returned to address corrections | 9/8/2015 | CELESTE MORRIS |
Applicant returned to address corrections | 10/13/2015 | CELESTE MORRIS |
Plan Check Approved | 11/17/2015 | CELESTE NGUYEN |
Issued | 11/17/2015 | LADBS |
Permit Finaled | 5/15/2017 | MANUEL TEJADA |
Permit Application Clearance Information
No Data Available. |
Contact Information
Architect | Stockton, Kenneth; Lic. No.: C19870 | 26500 W AGOURA RD. PMB # 844 CALABASAS, CA 91302 |
Contractor | Owner-Builder | , |
Engineer | Liston, Leonard Irvin; Lic. No.: C31902 | 889 PEIRCE CT SUITE 101 THOUSAND OAKS, CA 91360 |
Inspector Information
ALEXANDER HELFER, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Initial Grading | 11/18/2015 | Approved | MANUEL TEJADA |
Initial Grading | 12/4/2015 | Approved | BRIAN MILLER |
Excavation | 12/7/2015 | Partial Inspection | MANUEL TEJADA |
Excavation | 12/30/2015 | Partial Inspection | MANUEL TEJADA |
Excavation | 1/4/2016 | No Access for Inspection | MANUEL TEJADA |
Bottom/Toe | 1/21/2016 | Not Ready for Inspection | MANUEL TEJADA |
Drainage Devices/Catch Basin | 1/21/2016 | Conditional Approval | MANUEL TEJADA |
Bottom/Toe | 2/23/2016 | Partial Inspection | MANUEL TEJADA |
Bottom/Toe | 5/15/2017 | Approved | MANUEL TEJADA |
Final | 5/15/2017 | Permit Finaled | MANUEL TEJADA |
Rough | 5/15/2017 | Approved | MANUEL TEJADA |