7331 W VALMONT ST 91042
Certificate Information: 7331 W VALMONT ST 91042
- Application / Permit
- 15016-30000-01257
- Plan Check / Job No.
- B15WL00285
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- Interior and exterior alteration to existing single story boarding house. Alterations include, kitchen remodel, new exterior doors and remodeled bathrooms for ADA compliance.
- Permit Issued
- Issued on 3/3/2015
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2015 | RODOLFO ARIAS |
| Corrections Issued | 2/3/2015 | RODOLFO ARIAS |
| Quality Review Completed | 2/11/2015 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 2/12/2015 | APPLICANT |
| Applicant returned to address corrections | 2/25/2015 | RODOLFO ARIAS |
| Plan Check Approved | 3/2/2015 | RODOLFO ARIAS |
| Issued | 3/3/2015 | LADBS |
| Permit Finaled | 8/29/2025 | ANDREW DORSO |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/24/2015 | FARUK SEZER |
| Specific Plan | Cleared | 2/24/2015 | MILENA ZASADZIEN |
| Grading Pre-Inspection | Cleared | 3/2/2015 | RODOLFO ARIAS |
Contact Information
| Architect | Diradourian, Richard C; Lic. No.: C10336 | 2618 HERMOSA AVENUE MONTROSE, CA 91020 |
| Contractor | Owner-Builder | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 4/7/2015 | Partial Inspection | STEPHEN REED |
| Wood Frame | 5/6/2015 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 5/22/2015 | Approved | DANNY RODRIGUEZ |
| Insulation | 6/2/2015 | Approved | DANNY RODRIGUEZ |
| Drywall Nailing | 6/17/2015 | Partial Inspection | TIMOTHY KEY |
| Final | 6/17/2020 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/17/2020 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 6/17/2020 | Not Ready for Inspection | ANDREW DORSO |
| Final | 7/13/2022 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 7/13/2022 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 7/13/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 9/16/2022 | Partial Approval | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 9/16/2022 | Approved | ANDREW DORSO |
| Final | 8/29/2025 | Permit Finaled | ANDREW DORSO |