12311 W 11TH HELENA DR 90049
Certificate Information: 12311 W 11TH HELENA DR 90049
- Application / Permit
- 15016-20000-28272
- Plan Check / Job No.
- B15VN17070
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- REDUCE OF (E) DET. GARAGE
- Permit Issued
- Issued on 6/20/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2015 | APPLICANT |
| Green Plans Picked Up | 1/8/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2016 | CHON CHIO KUO |
| Corrections Issued | 1/25/2016 | CHON CHIO KUO |
| Quality Review Completed | 1/28/2016 | TIEN JEN WANG |
| Building Plans Picked Up | 1/29/2016 | APPLICANT |
| Applicant returned to address corrections | 4/14/2016 | CHON CHIO KUO |
| Applicant returned to address corrections | 8/16/2016 | CHON CHIO KUO |
| Plan Check Approved | 8/18/2016 | CHON CHIO KUO |
| Issued | 6/20/2017 | LADBS |
| CofO in Progress | 4/9/2020 | DANNY TOLENTINO |
| Permit Finaled | 5/8/2020 | VINCENT COTTON |
| CofO Issued | 5/8/2020 | VINCENT COTTON |
| Permit Finaled | 5/8/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2016 | SEVAK ISAKHAYAN |
| Sewer availability | Cleared | 2/1/2016 | SEVAK ISAKHAYAN |
| Roof/Waste drainage to street | Cleared | 4/19/2016 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 8/18/2016 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 8/18/2016 | CHON CHIO KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarbin, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Engineer | Jitechian, Ara; Lic. No.: C54893 | 9433 VIA PATRICIA BURBANK, CA 91504 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/7/2020 | Corrections Issued | DANNY TOLENTINO |
| Smoke Detectors | 2/7/2020 | Approved | DANNY TOLENTINO |
| Wood Frame | 2/7/2020 | Corrections Issued | DANNY TOLENTINO |
| Footing/Foundation/Slab | 3/24/2020 | Partial Inspection | DANNY TOLENTINO |
| Final | 3/26/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| Wood Frame | 3/26/2020 | Corrections Issued | DANNY TOLENTINO |
| Final | 4/2/2020 | Conditional Approval | DANNY TOLENTINO |
| Wood Frame | 4/2/2020 | Approved | DANNY TOLENTINO |
| Final | 4/9/2020 | OK to Issue CofO | DANNY TOLENTINO |