8155 N VAN NUYS BLVD 91402
Certificate Information: 8155 N VAN NUYS BLVD 91402
- Application / Permit
- 15016-10001-27090
- Plan Check / Job No.
- B17LA13821
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- CHANGE OF USE OF MECHANICAL (S-2) PENTHOUSE TO 2 JOINT LIVE-WORK QUARTERS (R-2)
- Permit Issued
- Issued on 12/4/2017
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/4/2019
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2017 | SUEN LIEU |
| Disabled Access Plans Picked Up | 8/23/2017 | APPLICANT |
| Green Plans Picked Up | 8/23/2017 | APPLICANT |
| Corrections Issued | 8/28/2017 | SUEN LIEU |
| Quality Review Completed | 9/5/2017 | BILL STUTSMAN |
| Building Plans Picked Up | 9/12/2017 | APPLICANT |
| Applicant returned to address corrections | 10/31/2017 | SUEN LIEU |
| Applicant returned to address corrections | 11/9/2017 | SUEN LIEU |
| Applicant returned to address corrections | 11/15/2017 | SUEN LIEU |
| Applicant returned to address corrections | 11/16/2017 | SUEN LIEU |
| Plan Check Approved | 12/1/2017 | SUEN LIEU |
| Issued | 12/4/2017 | LADBS |
| Permit Finaled | 11/4/2019 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/17/2017 | LAURA FRAZIN-STEELE |
| Address approval | Cleared | 10/17/2017 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2017 | MARKOS PEREZ-BRAN |
| Opn space landscape/Water mgmt | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/17/2017 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 10/17/2017 | LAURA FRAZIN-STEELE |
| Project located in CRA area | Cleared | 10/24/2017 | JIM URQUHART |
| DAS Clearance | Cleared | 10/26/2017 | SUEN LIEU |
| Green Code | Cleared | 10/26/2017 | SUEN LIEU |
| Fire Marshall Fire Life Safety | Cleared | 11/15/2017 | WILLIAM JOHNS |
| Sewer availability | Cleared | 11/22/2017 | LEE GUILBEAUX |
Contact Information
| Architect | Takacs, David Alexander; Lic. No.: C33737 | 600 S SPRING STREET # 410 LOS ANGELES, CA 90014 |
| Contractor | Evocon Engineering Inc; Lic. No.: 1016917-B | 1614 E CHEVY CHASE DRIVE #1 GLENDALE, CA 91206 |
| Engineer | Tan, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
| Engineer | Varela, Gregorio; Lic. No.: C81201 | 111 S OAK AVE #4 PASADENA, CA 91107 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/14/2018 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 3/14/2018 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 3/19/2018 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 3/19/2018 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 8/22/2018 | Not Ready for Inspection | DANNY RODRIGUEZ |