1318 E 7TH ST 90021

Certificate Information: 1318 E 7TH ST 90021

Application / Permit
15016-10000-06687
Plan Check / Job No.
B15LA04485
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
RENOVATION AND CHANGE OF USE OF REAR PORTION OF EXISTING 2 STORY BUILDING FOR GROUND FLOOR COMMERCIAL (RETAIL/RESTAURANT) USES AND SECOND FLOOR OFFICE. * CORE AND SHELL WORK ONLY *
Permit Issued
Issued on 5/20/2015
Issuing Office
Metro
Current Status
CofO Issued on 4/4/2017
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2015 APPLICANT
Disabled Access Plans Picked Up 4/17/2015 APPLICANT
Assigned to Plan Check Engineer 4/24/2015 JOE VO
Corrections Issued 5/3/2015 JOE VO
Quality Review Completed 5/7/2015 LINCOLN LEE
Green Plans Picked Up 5/7/2015 APPLICANT
Plan Check Approved 5/19/2015 JOE VO
Issued 5/20/2015 LADBS
TCO Issued (Expire Date: 03-11-2017) 9/12/2016 RICKEY JACKSON
TCO Issued (Expire Date: 06-21-2017) 12/23/2016 HENRY BAGHDASSARIAN
CofO in Progress 3/7/2017 NICK DANERI
Permit Finaled 4/4/2017 HENRY BAGHDASSARIAN
CofO Issued 4/4/2017 HENRY BAGHDASSARIAN
Permit Finaled 4/4/2017 HENRY BAGHDASSARIAN

Permit Application Clearance Information

"D" conditions Cleared 5/5/2015 ANDY RODRIGUEZ
ZI Cleared 5/5/2015 ANDY RODRIGUEZ
ZI Cleared 5/5/2015 ANDY RODRIGUEZ
Historical monument Cleared 5/7/2015 JIM URQUHART
Project located in CRA area Cleared 5/7/2015 JIM URQUHART
Historic monument Cleared 5/12/2015 LAMBERT GIESSINGER
Hydrant and Access approval Cleared 5/13/2015 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 5/14/2015 ARMENIA HERNANDEZ
Food Service Establishment Cleared 5/14/2015 WILFREDO VALDEZ
Green Code Cleared 5/14/2015 ROLLIN GETTLE III
DAS Clearance Cleared 5/15/2015 SHINE LIN
Fire Marshall Fire Life Safety Cleared 5/15/2015 ANDREW KO
Sewer availability Cleared 5/18/2015 ARMENIA HERNANDEZ
Food establishment approval Cleared 5/19/2015 LACDHS APPROVED

Contact Information

Architect Rios, Mark William; Lic. No.: C15744 639 N LARCHMONT BLVD SUITE 100      LOS ANGELES, CA 90004
Contractor O'Neil W E Construction Co Of California; Lic. No.: 494031-B 909 N SEPULVEDA BLVD SUITE 400      EL SEGUNDO, CA 90245
Engineer Ho, Lawrence Ying Kuen; Lic. No.: S3259 888 S FIGUEROA STREET      LOS ANGELES, CA 90017

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2015 No Access for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 10/29/2015 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/24/2015 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/22/2015 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/23/2015 Conditional Approval NICK DANERI
Wood Frame 1/5/2016 Corrections Issued NICK DANERI
Wood Frame 1/6/2016 Partial Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 1/15/2016 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/28/2016 Conditional Approval NICK DANERI
Drywall Nailing 2/2/2016 Partial Approval NICK DANERI
Wood Frame 2/23/2016 Partial Approval NICK DANERI
Insulation 2/25/2016 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/17/2016 Partial Approval MICHAEL KUHN
Wood Frame 3/22/2016 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/1/2016 Partial Approval NICK DANERI
Light Gage Steel Frame 4/1/2016 Partial Approval NICK DANERI
Deputy Steel/Welding 4/6/2016 Conditional Approval NICK DANERI
Wall Anchors 4/7/2016 Partial Inspection NICK DANERI
Structural Steel Frame 4/19/2016 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/22/2016 Partial Approval NICK DANERI
Wood Frame 4/27/2016 Partial Approval NICK DANERI
Green Building Final 5/5/2016 Not Ready for Inspection DAVID MATSON
Drywall Nailing 5/11/2016 Partial Approval NICK DANERI
Green Building Rough 5/11/2016 Approved DONALD CRICHLOW
Special/Order Compliance 6/2/2016 Partial Inspection NICK DANERI
Drywall Nailing 6/8/2016 Partial Approval NICK DANERI
Light Gage Steel Frame 6/16/2016 Partial Approval NICK DANERI
Light Gage Steel Frame 6/27/2016 Partial Approval NICK DANERI
Drywall Nailing 6/29/2016 Partial Approval NICK DANERI
Light Gage Steel Frame 7/11/2016 Partial Approval NICK DANERI
Deputy Steel/Welding 7/13/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 7/14/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 7/15/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 7/18/2016 Approved TIMOTHY LYNN
Deputy Steel/Welding 7/19/2016 Conditional Approval NICK DANERI
Green Building Final 7/20/2016 Partial Inspection DONALD CRICHLOW
Green Building Final 7/21/2016 Partial Approval DONALD CRICHLOW
Light Gage Steel Frame 7/27/2016 Partial Inspection NICK DANERI
Light Gage Steel Frame 8/2/2016 Partial Approval NICK DANERI
Drywall Nailing 8/15/2016 Partial Approval NICK DANERI
Light Gage Steel Frame 8/15/2016 Partial Approval NICK DANERI
Special/Order Compliance 9/6/2016 Corrections Issued NICK DANERI
Pre-Inspection 9/8/2016 Partial Inspection NICK DANERI
Pre-Inspection 9/19/2016 Partial Inspection NICK DANERI
Final 9/20/2016 Not Ready for Inspection NICK DANERI
Green Building Final 9/20/2016 Conditional Approval JOHN KLARIN
Reinforced Masonry Frame 9/20/2016 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 9/20/2016 SGSOV Not Ready NICK DANERI
Special/Order Compliance 9/22/2016 Partial Inspection NICK DANERI
Final 12/1/2016 Partial Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 12/1/2016 SGSOV Not Ready NICK DANERI
Final 12/14/2016 Partial Inspection NICK DANERI
Green Building Final 12/14/2016 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/14/2016 SGSOV Approved NICK DANERI
Special/Order Compliance 2/14/2017 Partial Inspection NICK DANERI
Final 3/6/2017 OK to Issue CofO NICK DANERI