1318 E 7TH ST 90021
Certificate Information: 1318 E 7TH ST 90021
- Application / Permit
- 15016-10000-06687
- Plan Check / Job No.
- B15LA04485
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- RENOVATION AND CHANGE OF USE OF REAR PORTION OF EXISTING 2 STORY BUILDING FOR GROUND FLOOR COMMERCIAL (RETAIL/RESTAURANT) USES AND SECOND FLOOR OFFICE. * CORE AND SHELL WORK ONLY *
- Permit Issued
- Issued on 5/20/2015
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/4/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2015 | APPLICANT |
| Disabled Access Plans Picked Up | 4/17/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2015 | JOE VO |
| Corrections Issued | 5/3/2015 | JOE VO |
| Quality Review Completed | 5/7/2015 | LINCOLN LEE |
| Green Plans Picked Up | 5/7/2015 | APPLICANT |
| Plan Check Approved | 5/19/2015 | JOE VO |
| Issued | 5/20/2015 | LADBS |
| TCO Issued (Expire Date: 03-11-2017) | 9/12/2016 | RICKEY JACKSON |
| TCO Issued (Expire Date: 06-21-2017) | 12/23/2016 | HENRY BAGHDASSARIAN |
| CofO in Progress | 3/7/2017 | NICK DANERI |
| Permit Finaled | 4/4/2017 | HENRY BAGHDASSARIAN |
| CofO Issued | 4/4/2017 | HENRY BAGHDASSARIAN |
| Permit Finaled | 4/4/2017 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| "D" conditions | Cleared | 5/5/2015 | ANDY RODRIGUEZ |
| ZI | Cleared | 5/5/2015 | ANDY RODRIGUEZ |
| ZI | Cleared | 5/5/2015 | ANDY RODRIGUEZ |
| Historical monument | Cleared | 5/7/2015 | JIM URQUHART |
| Project located in CRA area | Cleared | 5/7/2015 | JIM URQUHART |
| Historic monument | Cleared | 5/12/2015 | LAMBERT GIESSINGER |
| Hydrant and Access approval | Cleared | 5/13/2015 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2015 | ARMENIA HERNANDEZ |
| Food Service Establishment | Cleared | 5/14/2015 | WILFREDO VALDEZ |
| Green Code | Cleared | 5/14/2015 | ROLLIN GETTLE III |
| DAS Clearance | Cleared | 5/15/2015 | SHINE LIN |
| Fire Marshall Fire Life Safety | Cleared | 5/15/2015 | ANDREW KO |
| Sewer availability | Cleared | 5/18/2015 | ARMENIA HERNANDEZ |
| Food establishment approval | Cleared | 5/19/2015 | LACDHS APPROVED |
Contact Information
| Architect | Rios, Mark William; Lic. No.: C15744 | 639 N LARCHMONT BLVD SUITE 100 LOS ANGELES, CA 90004 |
| Contractor | O'Neil W E Construction Co Of California; Lic. No.: 494031-B | 909 N SEPULVEDA BLVD SUITE 400 EL SEGUNDO, CA 90245 |
| Engineer | Ho, Lawrence Ying Kuen; Lic. No.: S3259 | 888 S FIGUEROA STREET LOS ANGELES, CA 90017 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2015 | No Access for Inspection | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2015 | Partial Approval | NICK DANERI |
| Footing/Foundation/Slab | 11/24/2015 | Partial Approval | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 12/22/2015 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 12/23/2015 | Conditional Approval | NICK DANERI |
| Wood Frame | 1/5/2016 | Corrections Issued | NICK DANERI |
| Wood Frame | 1/6/2016 | Partial Inspection | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 1/15/2016 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 1/28/2016 | Conditional Approval | NICK DANERI |
| Drywall Nailing | 2/2/2016 | Partial Approval | NICK DANERI |
| Wood Frame | 2/23/2016 | Partial Approval | NICK DANERI |
| Insulation | 2/25/2016 | Partial Approval | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 3/17/2016 | Partial Approval | MICHAEL KUHN |
| Wood Frame | 3/22/2016 | Partial Approval | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 4/1/2016 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 4/1/2016 | Partial Approval | NICK DANERI |
| Deputy Steel/Welding | 4/6/2016 | Conditional Approval | NICK DANERI |
| Wall Anchors | 4/7/2016 | Partial Inspection | NICK DANERI |
| Structural Steel Frame | 4/19/2016 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/22/2016 | Partial Approval | NICK DANERI |
| Wood Frame | 4/27/2016 | Partial Approval | NICK DANERI |
| Green Building Final | 5/5/2016 | Not Ready for Inspection | DAVID MATSON |
| Drywall Nailing | 5/11/2016 | Partial Approval | NICK DANERI |
| Green Building Rough | 5/11/2016 | Approved | DONALD CRICHLOW |
| Special/Order Compliance | 6/2/2016 | Partial Inspection | NICK DANERI |
| Drywall Nailing | 6/8/2016 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 6/16/2016 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 6/27/2016 | Partial Approval | NICK DANERI |
| Drywall Nailing | 6/29/2016 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 7/11/2016 | Partial Approval | NICK DANERI |
| Deputy Steel/Welding | 7/13/2016 | Conditional Approval | NICK DANERI |
| Deputy Steel/Welding | 7/14/2016 | Conditional Approval | NICK DANERI |
| Deputy Steel/Welding | 7/15/2016 | Conditional Approval | NICK DANERI |
| Deputy Steel/Welding | 7/18/2016 | Approved | TIMOTHY LYNN |
| Deputy Steel/Welding | 7/19/2016 | Conditional Approval | NICK DANERI |
| Green Building Final | 7/20/2016 | Partial Inspection | DONALD CRICHLOW |
| Green Building Final | 7/21/2016 | Partial Approval | DONALD CRICHLOW |
| Light Gage Steel Frame | 7/27/2016 | Partial Inspection | NICK DANERI |
| Light Gage Steel Frame | 8/2/2016 | Partial Approval | NICK DANERI |
| Drywall Nailing | 8/15/2016 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 8/15/2016 | Partial Approval | NICK DANERI |
| Special/Order Compliance | 9/6/2016 | Corrections Issued | NICK DANERI |
| Pre-Inspection | 9/8/2016 | Partial Inspection | NICK DANERI |
| Pre-Inspection | 9/19/2016 | Partial Inspection | NICK DANERI |
| Final | 9/20/2016 | Not Ready for Inspection | NICK DANERI |
| Green Building Final | 9/20/2016 | Conditional Approval | JOHN KLARIN |
| Reinforced Masonry Frame | 9/20/2016 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 9/20/2016 | SGSOV Not Ready | NICK DANERI |
| Special/Order Compliance | 9/22/2016 | Partial Inspection | NICK DANERI |
| Final | 12/1/2016 | Partial Inspection | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2016 | SGSOV Not Ready | NICK DANERI |
| Final | 12/14/2016 | Partial Inspection | NICK DANERI |
| Green Building Final | 12/14/2016 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2016 | SGSOV Approved | NICK DANERI |
| Special/Order Compliance | 2/14/2017 | Partial Inspection | NICK DANERI |
| Final | 3/6/2017 | OK to Issue CofO | NICK DANERI |