3010 N PAULCREST DR 90046
Certificate Information: 3010 N PAULCREST DR 90046
- Application / Permit
- 15014-70000-05450
- Plan Check / Job No.
- B15SL01626
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert the existing attached carport into living area and construct an attached 2-car carport. Remodel the existing kitchen and bathroom.
- Permit Issued
- Issued on 1/11/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2015 | ALBERT SERVIN |
| Corrections Issued | 11/25/2015 | ALBERT SERVIN |
| Plan Check Approved | 1/8/2016 | ALBERT SERVIN |
| Issued | 1/11/2016 | LADBS |
| CofO in Progress | 5/5/2026 | SCOTT FINNILA |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
| CofO Issued | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/3/2015 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 12/3/2015 | RICHARD SOUTHERLAND |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2015 | RICHARD SOUTHERLAND |
| Roof/Waste drainage to street | Cleared | 12/3/2015 | RICHARD SOUTHERLAND |
| Sewer availability | Cleared | 12/3/2015 | RICHARD SOUTHERLAND |
| Specific Plan | Cleared | 12/9/2015 | TOM GLICK |
| Grading Pre-Inspection | Cleared | 1/8/2016 | ALBERT SERVIN |
Contact Information
| Contractor | West Coast Building Constructors Inc; Lic. No.: 657580-B | 2425 ALBERT WAY ARCADIA, CA 91007 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/29/2016 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/2/2016 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/12/2016 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/12/2016 | Approved | RAUL BARAJAS |
| Green Building Rough | 4/12/2016 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/12/2016 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/12/2016 | Partial Approval | RAUL BARAJAS |
| Insulation | 4/18/2016 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/18/2016 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/19/2016 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/19/2016 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 2/22/2017 | Approved | RAUL BARAJAS |
| Final | 2/22/2017 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 2/22/2017 | Approved | RAUL BARAJAS |
| HVAC-Final | 2/22/2017 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 2/22/2017 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2017 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 2/22/2017 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 2/2/2026 | Corrections Issued | SCOTT FINNILA |
| Final | 3/25/2026 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 3/25/2026 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 5/4/2026 | OK to Issue CofO | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 5/4/2026 | Approved | SCOTT FINNILA |