648 N ENCHANTED WAY 90272
Certificate Information: 648 N ENCHANTED WAY 90272
- Application / Permit
- 15014-30000-05661
- Plan Check / Job No.
- B15WL06279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 story addition to SFD with attached garage.
- Permit Issued
- Issued on 5/3/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2015 | SHANGQIN XIE |
| Corrections Issued | 1/6/2016 | SHANGQIN XIE |
| Quality Review Completed | 1/7/2016 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 1/8/2016 | APPLICANT |
| Green Plans Picked Up | 1/11/2016 | APPLICANT |
| Applicant returned to address corrections | 10/18/2016 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/1/2017 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/21/2017 | SHANGQIN XIE |
| Plan Check Approved | 5/3/2017 | SHANGQIN XIE |
| Issued | 5/3/2017 | LADBS |
| CofO in Progress | 2/7/2020 | ANDREW NAVE |
| Permit Finaled | 2/19/2020 | VINCENT COTTON |
| CofO Issued | 2/19/2020 | VINCENT COTTON |
| Permit Finaled | 2/19/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/29/2016 | MARTIN FRAGOSO |
| Green Code | Cleared | 5/3/2016 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 10/18/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 10/18/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 10/18/2016 | ERIK MUNOZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2016 | ERIK MUNOZ |
| Permit | Cleared | 10/18/2016 | ERIK MUNOZ |
| Roof/Waste drainage to street | Cleared | 10/18/2016 | ERIK MUNOZ |
| Sewer availability | Cleared | 10/18/2016 | ERIK MUNOZ |
| Coastal Zone | Cleared | 3/6/2017 | EDBER MACEDO |
| BHO/Hillside ordinance | Cleared | 4/14/2017 | CHEN ZHANG |
| Coastal Zone | Cleared | 4/28/2017 | SARAH GOLDMAN |
Contact Information
| Architect | Walters, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Tjc Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PARKWAY, 100 ALISO VIEJO, CA 92656 |
| Engineer | Messiha, Hany Gamil; Lic. No.: C56766 | 10834 ROSE AVE 9 LOS ANGELES, CA 90034 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/11/2017 | Corrections Issued | VINCENT SCIPIONI |
| Footing/Foundation/Slab | 12/12/2017 | Partial Approval | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 12/13/2017 | No Access for Inspection | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 12/15/2017 | No Access for Inspection | VINCENT SCIPIONI |
| Deputy Drilled-In Anchors | 2/2/2018 | No Access for Inspection | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 2/6/2018 | Conditional Approval | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 4/23/2018 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/23/2018 | Partial Approval | MICHAEL PELHAM |
| Underground Mechanical | 8/9/2018 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 8/23/2018 | Partial Approval | DANIEL ORRANTE |
| Underground Mechanical | 12/27/2018 | Not Ready for Inspection | ANDREW NAVE |
| Underground Mechanical | 1/2/2019 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 1/24/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 1/28/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2019 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 4/23/2019 | Partial Approval | ANDREW NAVE |
| Sewer | 4/23/2019 | Partial Inspection | ANDREW NAVE |
| PLUMBING-Rough | 4/30/2019 | Corrections Issued | ANDREW NAVE |
| Sewer | 4/30/2019 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/6/2019 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 5/6/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2019 | Corrections Issued | ANDREW NAVE |
| Gas Test | 5/9/2019 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2019 | Conditional Approval | ANDREW NAVE |
| HVAC-Rough | 5/15/2019 | Conditional Approval | ANDREW NAVE |
| Shower Pan | 5/15/2019 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/28/2019 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 5/28/2019 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 5/28/2019 | Approved | ANDREW NAVE |
| Wood Frame | 5/28/2019 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/5/2019 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 6/5/2019 | Not Ready for Inspection | ANDREW NAVE |
| Wood Frame | 6/5/2019 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/1/2019 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 7/8/2019 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 7/15/2019 | Partial Inspection | ANDREW NAVE |
| Insulation | 7/19/2019 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 7/23/2019 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/25/2019 | Not Ready for Inspection | ANDREW NAVE |
| Drywall Nailing | 7/30/2019 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/30/2019 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 7/30/2019 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 10/1/2019 | Corrections Issued | ANDREW NAVE |
| Gas Test | 10/1/2019 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 10/1/2019 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 10/3/2019 | Approved | ANDREW NAVE |
| Gas Test | 10/3/2019 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 10/3/2019 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 10/9/2019 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 10/9/2019 | Partial Approval | ANDREW NAVE |
| PLUMBING-Final | 10/9/2019 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 10/15/2019 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 10/15/2019 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 10/15/2019 | Approved | ANDREW NAVE |
| Gas Test | 1/6/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 1/6/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 1/15/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/27/2020 | Approved | ANDREW NAVE |
| Final | 1/27/2020 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 1/27/2020 | Approved | ANDREW NAVE |
| Green Building Final | 1/27/2020 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 1/27/2020 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 1/27/2020 | Approved | ANDREW NAVE |
| Final | 2/5/2020 | Conditional Approval | ANDREW NAVE |