7874 S BOEING AVE 90045

Certificate Information: 7874 S BOEING AVE 90045

Application / Permit
15014-30000-04039
Plan Check / Job No.
B15WL04573
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and ground floor addition to existing one story single family dwelling
Permit Issued
Issued on 10/28/2015
Issuing Office
West Los Angeles
Current Status
Issued on 10/28/2015
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/2/2015 APPLICANT
Assigned to Plan Check Engineer 9/10/2015 CHRISTINE MAALOUF
Corrections Issued 9/14/2015 CHRISTINE MAALOUF
Quality Review Completed 9/15/2015 DOUGLAS NAKATANI
Building Plans Picked Up 9/21/2015 APPLICANT
Green Plans Picked Up 9/21/2015 APPLICANT
Applicant returned to address corrections 10/15/2015 CHRISTINE MAALOUF
Plan Check Approved 10/26/2015 CHRISTINE MAALOUF
Issued 10/28/2015 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/25/2015 JAMES MORALEZ
Permit Cleared 9/25/2015 JAMES MORALEZ
Sewer availability Cleared 9/25/2015 JAMES MORALEZ
Green Code Cleared 10/14/2015 CHRISTINE MAALOUF
Low Impact Development Cleared 10/15/2015 VIJAY DESAI
Roof/Waste drainage to street Cleared 10/15/2015 NATALIE MOORE
GPI Written Notices Cleared 10/26/2015 CHRISTINE MAALOUF

Contact Information

Architect Noteware, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2015 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/6/2015 Approved RICHARD STEINBACH
PLUMBING-Rough 11/19/2015 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 11/20/2015 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 2/19/2016 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 4/19/2016 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 4/21/2016 Approved RICHARD STEINBACH
ELECTRICAL-Rough 5/27/2016 Approved RICHARD STEINBACH
PLUMBING-Rough 5/27/2016 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 6/7/2016 Not Ready for Inspection RICHARD STEINBACH
Green Building Rough 6/7/2016 Not Ready for Inspection RICHARD STEINBACH
BUILDING-Rough-Frame 6/8/2016 Approved RICHARD STEINBACH
Green Building Rough 6/8/2016 Approved RICHARD STEINBACH
HVAC-Rough 6/8/2016 Approved RICHARD STEINBACH
Insulation 6/13/2016 Not Ready for Inspection RICHARD STEINBACH
Insulation 6/15/2016 Approved RICHARD STEINBACH
Drywall Nailing 7/28/2016 Approved RICHARD STEINBACH
ELECTRICAL-Final 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
Final 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
Green Building Final 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
HVAC-Final 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
PLUMBING-Final 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 8/18/2016 SGSOV Not Ready RICHARD STEINBACH
Service/Power Release 8/18/2016 Approved RICHARD STEINBACH
Smoke Detectors 8/18/2016 Not Ready for Inspection RICHARD STEINBACH
Gas Test 9/2/2016 Corrections Issued RICHARD STEINBACH
Interior/Exterior Lathing 9/2/2016 Approved RICHARD STEINBACH
Gas Test 9/7/2016 Approved RICHARD STEINBACH
PLUMBING-Final 2/22/2017 Approved RICHARD STEINBACH
ELECTRICAL-Final 2/28/2017 Approved ROBERT VORHIS
Special/Order Compliance 3/25/2026 Corrections Issued DAVID FEILER