124 N UDINE WAY 90077
Certificate Information: 124 N UDINE WAY 90077
- Application / Permit
- 15014-30000-03045
- Plan Check / Job No.
- B15WL03557
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st story addition to (E) 2-story SFD
- Permit Issued
- Issued on 9/17/2015
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/17/2015
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2015 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 7/27/2015 | APPLICANT |
| Corrections Issued | 7/28/2015 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 7/28/2015 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 7/28/2015 | APPLICANT |
| Plan Check Approved | 9/17/2015 | VLADIMIR ARUTYUNYAN |
| Issued | 9/17/2015 | LADBS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/27/2015 | HUGO RICO |
| BHO/Hillside ordinance | Cleared | 8/27/2015 | HUGO RICO |
| BHO/Hillside ordinance | Cleared | 8/27/2015 | HUGO RICO |
| BHO/Hillside ordinance | Cleared | 8/27/2015 | HUGO RICO |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2015 | HUGO RICO |
| Hydrant and Access approval | Cleared | 9/10/2015 | ROBERT DUFF |
| Green Code | Cleared | 9/14/2015 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 9/14/2015 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/14/2015 | KELTON KIRBY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Resnick, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/28/2015 | Conditional Approval | ANTHONY ANDERSON |
| FLOOD-Elevation Certificate | 10/1/2015 | Approved | RONALD MYRICK |
| Footing/Foundation/Slab | 10/1/2015 | Partial Approval | RONALD MYRICK |
| PLUMBING-Rough | 10/13/2015 | Partial Approval | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 10/15/2015 | Approved | ANTHONY ANDERSON |
| BUILDING-Rough-Frame | 11/20/2015 | Not Ready for Inspection | ANTHONY ANDERSON |
| FLOOD-Proofing Certificate | 11/20/2015 | Not Ready for Inspection | ANTHONY ANDERSON |
| Green Building Rough | 11/20/2015 | Not Ready for Inspection | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2015 | Partial Approval | ANTHONY ANDERSON |
| Wood Frame | 11/23/2015 | Partial Approval | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 1/19/2016 | Partial Approval | DAVID JAMES |
| BUILDING-Rough-Frame | 1/22/2016 | No Access for Inspection | RONALD MYRICK |
| FLOOD-Proofing Certificate | 1/22/2016 | No Access for Inspection | RONALD MYRICK |
| Green Building Rough | 1/22/2016 | No Access for Inspection | RONALD MYRICK |
| Rough-Elec/Plmb/HVAC | 1/22/2016 | No Access for Inspection | RONALD MYRICK |
| BUILDING-Rough-Frame | 1/25/2016 | Corrections Issued | ANTHONY ANDERSON |
| Rough-Elec/Plmb/HVAC | 1/25/2016 | Corrections Issued | ANTHONY ANDERSON |
| BUILDING-Rough-Frame | 2/3/2016 | Partial Inspection | ANTHONY ANDERSON |
| Deputy Drilled-In Anchors | 2/3/2016 | Approved | ANTHONY ANDERSON |
| ELECTRICAL-Rough | 2/3/2016 | Partial Inspection | ANTHONY ANDERSON |
| FLOOD-Proofing Certificate | 2/3/2016 | Approved | ANTHONY ANDERSON |
| Green Building Rough | 2/3/2016 | Not Ready for Inspection | ANTHONY ANDERSON |
| HVAC-Rough | 2/3/2016 | Approved | ANTHONY ANDERSON |
| PLUMBING-Rough | 2/3/2016 | Corrections Issued | ANTHONY ANDERSON |
| BUILDING-Rough-Frame | 2/5/2016 | Approved | ANTHONY ANDERSON |
| Green Building Rough | 2/5/2016 | Approved | ANTHONY ANDERSON |
| Rough-Elec/Plmb/HVAC | 2/5/2016 | Approved | ANTHONY ANDERSON |
| Insulation | 2/10/2016 | Approved | ANTHONY ANDERSON |
| Insulation | 2/11/2016 | Approved | ANTHONY ANDERSON |
| Drywall Nailing | 2/24/2016 | Approved | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 2/26/2016 | Partial Inspection | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 2/29/2016 | Approved | ANTHONY ANDERSON |
| Deputy Steel/Welding | 4/18/2016 | Conditional Approval | ANTHONY ANDERSON |
| ELECTRICAL-Rough | 4/22/2016 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 5/12/2016 | Approved | ANTHONY ANDERSON |
| Final | 7/25/2017 | Partial Inspection | ANTHONY ANDERSON |
| Green Building Final | 7/25/2017 | Approved | ANTHONY ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/25/2017 | SGSOV Approved | ANTHONY ANDERSON |
| Smoke Detectors | 7/25/2017 | Approved | ANTHONY ANDERSON |
| Final | 8/23/2018 | Partial Approval | MATT KELLERMAN |
| Final | 8/18/2020 | Corrections Issued | MATT KELLERMAN |
| Final | 8/21/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 9/1/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 8/5/2022 | Corrections Issued | CHRISTOPHER WILSON |