8808 W THRASHER AVE 90069

Certificate Information: 8808 W THRASHER AVE 90069

Application / Permit
15014-30000-02925
Plan Check / Job No.
B15WL03432
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 12 SF AT FIRST FLOOR, 80 SF ON 2ND FLOOR, ADDITION OF UNCOVERED DECK 337 S.F, AND 207S.F. COVERD FRON PORCH). AND INTERIOR TENANT IMPROVEMENT.
Permit Issued
Issued on 8/27/2015
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2015 APPLICANT
Assigned to Plan Check Engineer 7/1/2015 TARIK SAOUD
Corrections Issued 7/1/2015 TARIK SAOUD
Plan Check Approved 8/27/2015 TARIK SAOUD
Issued 8/27/2015 LADBS
CofO in Progress 2/5/2021 BRAD BESCOS
Permit Finaled 2/13/2021 DEROLD HAUFF
CofO Issued 2/13/2021 DEROLD HAUFF
Permit Finaled 2/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/1/2015 TARIK SAOUD
Eng Process Fee Ord 176,300 Cleared 7/16/2015 OSCAR GUTIERREZ
Sewer availability Cleared 7/16/2015 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 8/12/2015 KELTON KIRBY

Contact Information

Contractor Rener Construction & Design Inc; Lic. No.: 903760-B 10715 FARRALONE AVE      CHATSWORTH, CA 91311
Engineer Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/14/2015 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 10/8/2015 Partial Approval CRAIG DAVIS
HVAC-Rough 11/13/2015 Partial Approval BRAD BESCOS
HVAC-Rough 11/18/2015 Not Ready for Inspection BRAD BESCOS
Insulation 11/25/2015 Not Ready for Inspection BRAD BESCOS
Insulation 12/1/2015 Partial Approval ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 12/10/2015 Approved ALEXANDER ANDREWS
HVAC-Rough 12/18/2015 Approved BRAD BESCOS
ELECTRICAL-Rough 1/13/2016 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 1/13/2016 Not Ready for Inspection BRAD BESCOS
ELECTRICAL-Rough 1/22/2016 Approved BRAD BESCOS
PLUMBING-Rough 2/9/2016 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 2/22/2016 Corrections Issued BRAD BESCOS
Deputy Wood Construction 2/23/2016 No Access for Inspection BRAD BESCOS
BUILDING-Rough-Frame 2/25/2016 Corrections Issued BRAD BESCOS
Green Building Rough 2/25/2016 Not Ready for Inspection BRAD BESCOS
Deputy Wood Construction 3/4/2016 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 3/4/2016 Approved BRAD BESCOS
BUILDING-Rough-Frame 3/8/2016 Partial Approval ALEXANDER ANDREWS
Green Building Rough 3/8/2016 Approved ALEXANDER ANDREWS
BUILDING-Rough-Frame 3/14/2016 Approved BRAD BESCOS
Drywall Nailing 4/11/2016 Approved BRAD BESCOS
Interior/Exterior Lathing 4/11/2016 Partial Approval BRAD BESCOS
Special/Order Compliance 9/18/2017 Corrections Issued BRAD BESCOS
Special/Order Compliance 9/22/2017 Not Ready for Inspection BRAD BESCOS
ELECTRICAL-Final 6/20/2018 Not Ready for Inspection DANIEL GONZALEZ
HVAC-Final 6/20/2018 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Final 6/20/2018 Not Ready for Inspection DANIEL GONZALEZ
Service/Power Release 6/20/2018 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Rough 7/5/2018 Partial Inspection DANNY TOLENTINO
Service/Power Release 7/26/2018 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Final 9/16/2019 Approved RICHARD STEINBACH
Final 9/16/2019 Corrections Issued RICHARD STEINBACH
Green Building Final 9/16/2019 Approved RICHARD STEINBACH
HVAC-Final 9/16/2019 Approved RICHARD STEINBACH
PLUMBING-Final 9/16/2019 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 9/16/2019 SGSOV Approved RICHARD STEINBACH
Smoke Detectors 9/16/2019 Approved RICHARD STEINBACH
Final 2/6/2020 Not Ready for Inspection RICHARD STEINBACH
Final 3/2/2020 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Final 10/22/2020 Approved RAUL BARAJAS
Final 10/22/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 10/22/2020 Approved RAUL BARAJAS
PLUMBING-Final 10/22/2020 Approved RAUL BARAJAS
Final 2/4/2021 Conditional Approval BRAD BESCOS