17567 W CHASE ST 91325
Certificate Information: 17567 W CHASE ST 91325
- Application / Permit
- 15014-20002-03850
- Plan Check / Job No.
- B17VN18319
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENT TO 15014-20000-03850. REVISE PREVIOUSLY APPROVED ARCHITECTURAL & STRUCTURAL PLANS. DEMOLISH MOST OF THE STRUCTURE & ONLY MAINTAIN PORTION OF EXISTING WESTERLY EXTERIOR WALL & FOUNDATION
- Permit Issued
- Issued on 2/12/2018
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2017 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 12/11/2017 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 12/22/2017 | TIEN JEN WANG |
| Building Plans Picked Up | 12/22/2017 | APPLICANT |
| Plan Check Approved | 2/2/2018 | RUDOLF KINAR MELIKOFF |
| Issued | 2/12/2018 | LADBS |
| Permit Finaled | 9/17/2024 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/22/2018 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2018 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/23/2018 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/30/2018 | MARTIN FRAGOSO |
| Green Code | Cleared | 1/31/2018 | RUDOLF KINAR MELIKOFF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aramark, Concepts; Lic. No.: C82796 | 145 S. GLENOAKS BLVD BURBANK, CA 91502 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2018 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 4/18/2018 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/1/2018 | Partial Approval | MICHAEL YOUNG |
| PLUMBING-Rough | 5/1/2018 | Not Ready for Inspection | MICHAEL YOUNG |
| BUILDING-Rough-Frame | 5/4/2018 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 5/4/2018 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 5/7/2018 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2018 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/6/2018 | Partial Approval | MICHAEL YOUNG |
| PLUMBING-Rough | 8/6/2018 | Approved | MICHAEL YOUNG |
| ELECTRICAL-Rough | 9/18/2018 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2019 | Partial Approval | MATTHEW NUCKOLLS |
| Pre-Inspection | 1/11/2023 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 1/11/2023 | Not Ready for Inspection | JAVIER RAMOS JR |