12730 W MONTANA AVE 90049
Certificate Information: 12730 W MONTANA AVE 90049
- Application / Permit
- 15014-20000-05592
- Plan Check / Job No.
- B15VN16234
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 40' X 61' IRR SHAPE ADDITION TO ENLARGE (E) FAMILY ROOM AND ADD 2 BEDROOMS AND 2 BATHROOMS TO THE REAR OF THE (E) SFD. 7' X 32' IRR SHAPE ADDITION TO ENLARGE THE KITCHEN AND ADD AN ENTRY PORCH TO THE FRONT OF THE (E) SFD. INTERIOR REMODEL.
- Permit Issued
- Issued on 3/29/2016
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2015 | SARAH YOUSSEF |
| Corrections Issued | 12/21/2015 | SARAH YOUSSEF |
| Quality Review Completed | 12/22/2015 | ABDUL CHEGENI |
| Building Plans Picked Up | 12/28/2015 | APPLICANT |
| Green Plans Picked Up | 12/28/2015 | APPLICANT |
| Applicant returned to address corrections | 1/25/2016 | SARAH YOUSSEF |
| Applicant returned to address corrections | 2/26/2016 | SARAH YOUSSEF |
| Plan Check Approved | 3/2/2016 | SARAH YOUSSEF |
| No Progress | 3/3/2016 | SARAH YOUSSEF |
| Plan Check Approved | 3/3/2016 | SARAH YOUSSEF |
| Issued | 3/29/2016 | LADBS |
| CofO in Progress | 10/1/2024 | MICHAEL PELHAM |
| Permit Finaled | 10/1/2024 | RICHARD STEINBACH |
| CofO Issued | 10/1/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/1/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/29/2016 | ANNA VIDAL |
| Green Code | Cleared | 2/10/2016 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2016 | VALENTINO PUEBLOS |
| Low Impact Development | Cleared | 2/25/2016 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 2/25/2016 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 2/25/2016 | VALENTINO PUEBLOS |
| Grading Pre-Inspection | Cleared | 3/2/2016 | SARAH YOUSSEF |
Contact Information
| Architect | Toufanian, Hamid; Lic. No.: C26445 | 2908 NEBRASKA AVENUE SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2016 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/17/2016 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/23/2016 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/20/2016 | Partial Approval | GRANT WOODS |
| Green Building Rough | 7/20/2016 | Not Ready for Inspection | GRANT WOODS |
| PLUMBING-Rough | 7/20/2016 | Partial Approval | GRANT WOODS |
| BUILDING-Rough-Frame | 9/14/2016 | Not Ready for Inspection | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2016 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 9/14/2016 | Not Ready for Inspection | EDWIN GREGORYONA |
| PLUMBING-Rough | 9/14/2016 | Not Ready for Inspection | EDWIN GREGORYONA |
| ELECTRICAL-Rough | 9/29/2016 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 9/29/2016 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 9/29/2016 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/17/2016 | Approved | MICHAEL PELHAM |
| Green Building Rough | 10/17/2016 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 10/17/2016 | Partial Approval | MICHAEL PELHAM |
| Insulation | 10/21/2016 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 11/1/2016 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 11/21/2016 | Partial Approval | MICHAEL PELHAM |
| Shower Pan | 11/21/2016 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 4/18/2017 | Not Ready for Inspection | MICHAEL PELHAM |
| Final | 4/18/2017 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Final | 4/18/2017 | Not Ready for Inspection | MICHAEL PELHAM |
| PLUMBING-Final | 4/18/2017 | Not Ready for Inspection | MICHAEL PELHAM |
| ELECTRICAL-Final | 4/25/2017 | Approved | MICHAEL PELHAM |
| HVAC-Final | 4/25/2017 | Approved | MICHAEL PELHAM |
| PLUMBING-Final | 4/25/2017 | Approved | MICHAEL PELHAM |
| Final | 3/7/2024 | Corrections Issued | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Not Ready | MICHAEL PELHAM |
| Smoke Detectors | 3/7/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 3/7/2024 | Approved | STEPHANIE SWANSON |
| Final | 9/18/2024 | OK to Issue CofO | MICHAEL PELHAM |
| Green Building Final | 9/18/2024 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | MICHAEL PELHAM |
| Smoke Detectors | 9/18/2024 | Approved | MICHAEL PELHAM |