206 N LUCERNE BLVD 90004
Certificate Information: 206 N LUCERNE BLVD 90004
- Application / Permit
- 15014-20000-05185
- Plan Check / Job No.
- B15VN15143
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 9' X 22'-6" TO THE REAR OF (E) ONE STORY DWELLING, INTERIOR REMODEL TO RE-ARRANGE ALL INTERIOR SPACES. ADD 36'-6" X 37'-10" NEW SECOND FLOOR CONSISTS OF THREE BEDROOMS, THREE BATHROOMS AND WALK-IN-CLOSETS - SEE COMMENTS
- Permit Issued
- Issued on 2/2/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/19/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/10/2015 | APPLICANT |
Assigned to Plan Check Engineer | 11/24/2015 | MOURAD AZIZ |
Corrections Issued | 11/30/2015 | MOURAD AZIZ |
Quality Review Completed | 11/30/2015 | STEVEN KIM |
Building Plans Picked Up | 12/1/2015 | APPLICANT |
Green Plans Picked Up | 12/4/2015 | APPLICANT |
Applicant returned to address corrections | 12/15/2015 | MOURAD AZIZ |
Applicant returned to address corrections | 1/14/2016 | MOURAD AZIZ |
Applicant returned to address corrections | 1/20/2016 | MOURAD AZIZ |
Plan Check Approved | 1/29/2016 | MOURAD AZIZ |
Issued | 2/2/2016 | LADBS |
CofO in Progress | 6/11/2018 | DANNY TOLENTINO |
Permit Finaled | 6/19/2018 | RONALD MYRICK |
CofO Issued | 6/19/2018 | RONALD MYRICK |
Permit Finaled | 6/19/2018 | RONALD MYRICK |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 12/15/2015 | LEE GUILBEAUX |
Roof/Waste drainage to street | Cleared | 12/15/2015 | LEE GUILBEAUX |
Sewer availability | Cleared | 12/15/2015 | LEE GUILBEAUX |
HPOZ | Cleared | 12/21/2015 | KIMBERLY HENRY |
ZI | Cleared | 12/21/2015 | KIMBERLY HENRY |
ZI | Cleared | 12/21/2015 | KIMBERLY HENRY |
Green Code | Cleared | 1/27/2016 | RICHARD DOCKUS |
Contact Information
Architect | Mac, Laren Michael Bruce; Lic. No.: C29858 | 23705 VANOWEN # 309 WEST HILLS, CA 91307 |
Contractor | Owner-Builder | , |
Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 6/26/2017 | Partial Approval | DANNY TOLENTINO |
METHANE-Barrier | 6/26/2017 | Approved | DANNY TOLENTINO |
METHANE-Subgrade | 6/26/2017 | Approved | DANNY TOLENTINO |
BUILDING-Rough-Frame | 7/11/2017 | Partial Approval | DANNY TOLENTINO |
Green Building Rough | 7/11/2017 | Not Ready for Inspection | DANNY TOLENTINO |
METHANE-Rough | 7/11/2017 | Not Ready for Inspection | DANNY TOLENTINO |
PLUMBING-Rough | 7/11/2017 | Partial Approval | DANNY TOLENTINO |
BUILDING-Rough-Frame | 10/26/2017 | Corrections Issued | DANNY TOLENTINO |
ELECTRICAL-Rough | 10/26/2017 | Corrections Issued | DANNY TOLENTINO |
Green Building Rough | 10/26/2017 | Not Ready for Inspection | DANNY TOLENTINO |
METHANE-Rough | 10/26/2017 | Not Ready for Inspection | DANNY TOLENTINO |
PLUMBING-Rough | 10/26/2017 | Approved | DANNY TOLENTINO |
BUILDING-Rough-Frame | 11/2/2017 | Partial Inspection | DANNY TOLENTINO |
Green Building Rough | 11/2/2017 | Not Ready for Inspection | DANNY TOLENTINO |
METHANE-Rough | 11/2/2017 | Not Ready for Inspection | DANNY TOLENTINO |
Floor/Roof Diaphrgm/Shear Wall | 11/3/2017 | Partial Approval | JOSEPH MCGARRY |
BUILDING-Rough-Frame | 11/22/2017 | Approved | DANNY TOLENTINO |
ELECTRICAL-Rough | 11/22/2017 | Approved | DANNY TOLENTINO |
Green Building Rough | 11/22/2017 | Approved | DANNY TOLENTINO |
Interior/Exterior Lathing | 11/22/2017 | Partial Approval | DANNY TOLENTINO |
METHANE-Rough | 11/22/2017 | Approved | DANNY TOLENTINO |
Insulation | 12/1/2017 | Approved | DANNY TOLENTINO |
Drywall Nailing | 12/20/2017 | Approved | DANNY TOLENTINO |
Shower Pan | 2/22/2018 | Approved | DANNY TOLENTINO |
Gas Test | 4/18/2018 | Approved | DANNY TOLENTINO |
ELECTRICAL-Final | 5/16/2018 | Approved | DANNY TOLENTINO |
Final | 5/16/2018 | OK to Issue CofO | DANNY TOLENTINO |
Footing/Foundation/Slab | 5/16/2018 | Approved | DANNY TOLENTINO |
Green Building Final | 5/16/2018 | Approved | DANNY TOLENTINO |
HVAC-Final | 5/16/2018 | Approved | DANNY TOLENTINO |
PLUMBING-Final | 5/16/2018 | Approved | DANNY TOLENTINO |
SGSOV-Seismic Gas S/O Valve | 5/16/2018 | SGSOV Approved | DANNY TOLENTINO |
Service/Power Release | 5/16/2018 | Approved | DANNY TOLENTINO |
Smoke Detectors | 5/16/2018 | Approved | DANNY TOLENTINO |