17567 W CHASE ST 91325

Certificate Information: 17567 W CHASE ST 91325

Application / Permit
15014-20000-03850
Plan Check / Job No.
B15VN11244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE EXISTING GARAGE TO PART OF DWELLING UNIT. REMOVE EXISTING ROOF FRAMING AND RE-FRAME. ADDITION TO EXISTING SINGLE FAMILY DWELLING UNIT AND CHANGE OF USE TO COMMUNITY CARE FACILITY ( " AMBULATORY RESIDENTIAL FACILITY"
Permit Issued
Issued on 7/18/2016
Issuing Office
Valley
Current Status
CofO Issued on 10/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2015 APPLICANT
Assigned to Plan Check Engineer 9/10/2015 RUDOLF KINAR MELIKOFF
Corrections Issued 9/22/2015 RUDOLF KINAR MELIKOFF
Quality Review Completed 9/24/2015 TIEN JEN WANG
Building Plans Picked Up 9/30/2015 APPLICANT
Green Plans Picked Up 9/30/2015 APPLICANT
Applicant returned to address corrections 12/4/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 3/4/2016 RUDOLF KINAR MELIKOFF
Plan Check Approved 4/26/2016 FARUK SEZER
Issued 7/18/2016 LADBS
CofO in Progress 9/26/2024 JAVIER RAMOS JR
Permit Finaled 10/21/2024 DANIEL ORRANTE
CofO Issued 10/21/2024 DANIEL ORRANTE
Permit Finaled 10/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/8/2015 RICHARD SOUTHERLAND
Eng Process Fee Ord 176,300 Cleared 10/8/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 10/8/2015 RICHARD SOUTHERLAND
Green Code Cleared 11/4/2015 MICHAEL AYERS
Metro Rail approval Cleared 11/13/2015 THAN WIN
Hydrant and Access approval Cleared 11/30/2015 JOHN DALLAS
Roof/Waste drainage to street Cleared 11/30/2015 RICHARD SOUTHERLAND
Low Impact Development Cleared 1/14/2016 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Aramark, Concepts; Lic. No.: C82796 145 S. GLENOAKS BLVD      BURBANK, CA 91502

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/5/2016 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 12/7/2016 Approved MARK JOHNSON
Wood Frame 12/13/2016 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 1/30/2017 Partial Inspection MARK JOHNSON
Piling/Pier/Caisson 1/31/2017 Corrections Issued MARK JOHNSON
Deputy Drilled-In Anchors 4/17/2018 Conditional Approval MARK JOHNSON
Interior/Exterior Lathing 10/7/2019 Approved MARK JOHNSON
Insulation 7/14/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 7/16/2020 Corrections Issued MARK JOHNSON
Green Building Rough 7/16/2020 Approved MARK JOHNSON
HVAC-Rough 7/16/2020 Not Ready for Inspection MARK JOHNSON
Insulation 7/16/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 9/14/2020 Approved VINCENT HANLEY
HVAC-Rough 9/14/2020 Partial Approval VINCENT HANLEY
Insulation 9/14/2020 Approved VINCENT HANLEY
Drywall Nailing 10/27/2020 Approved MARK JOHNSON
Shower Pan 4/26/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 5/20/2021 Approved MARK JOHNSON
ELECTRICAL-Final 7/25/2024 Approved JAVIER RAMOS JR
Final 7/25/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/25/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 7/25/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 7/25/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 7/25/2024 Approved JAVIER RAMOS JR
Final 9/16/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 9/16/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 9/16/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 9/16/2024 Approved JAVIER RAMOS JR
Final 9/25/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/25/2024 Approved JAVIER RAMOS JR