1907 N BEVERLY GLEN BLVD 90077
Certificate Information: 1907 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 15014-20000-01620
- Plan Check / Job No.
- B15VN04729
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 28' X 20'10" 2 STORY ADDITION TO (E) 1 STORY SFD. RECREATION ROOM ON 1ST FLOOR OF ADDITION
- Permit Issued
- Issued on 9/2/2015
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2015 | APPLICANT |
| Green Plans Picked Up | 5/6/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2015 | HERNAN ARREOLA |
| Building Plans Picked Up | 5/21/2015 | APPLICANT |
| Corrections Issued | 5/22/2015 | HERNAN ARREOLA |
| Quality Review Completed | 5/22/2015 | STEVEN KIM |
| Applicant returned to address corrections | 8/18/2015 | HERNAN ARREOLA |
| Plan Check Approved | 8/27/2015 | HERNAN ARREOLA |
| Issued | 9/2/2015 | LADBS |
| CofO in Progress | 12/5/2024 | SEAN HAUPT |
| Permit Finaled | 1/2/2025 | RICHARD STEINBACH |
| CofO Issued | 1/2/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/2/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/3/2015 | HELEN FRANCISCO |
| BHO/Hillside ordinance | Cleared | 6/3/2015 | HELEN FRANCISCO |
| BHO/Hillside ordinance | Cleared | 6/3/2015 | HELEN FRANCISCO |
| BHO/Hillside ordinance | Cleared | 6/3/2015 | HELEN FRANCISCO |
| BHO/Hillside ordinance | Cleared | 6/3/2015 | HELEN FRANCISCO |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2015 | MIKE KOUYOUMDJIAN |
| Sewer availability | Cleared | 6/3/2015 | MIKE KOUYOUMDJIAN |
| Distance to fire station | Cleared | 7/20/2015 | JOHN DALLAS |
| Low Impact Development | Cleared | 7/23/2015 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 7/23/2015 | JAMES MORALEZ |
| GPI Written Notices | Cleared | 8/18/2015 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 8/18/2015 | HERNAN ARREOLA |
| Green Code | Cleared | 8/25/2015 | BRYAN MEYER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barr, Joseph Daniel Iii; Lic. No.: C70708 | 1910 20TH AVE DRIVE NE #109 HICKORY, NC 28601 |
| Engineer | Kennedy, Thomas James; Lic. No.: C74144 | 5105 E LOS ANGELES AVE 207 SIMI VALLEY, CA 93063 |
| Geologist | Miller, Jonathan Steven; Lic. No.: EG2391 | 2800 NEILSON WAY #210 SANTA MONICA, CA 90405 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2015 | Partial Approval | JOHN REGAN |
| Reinforced Masonry Frame | 10/13/2015 | Partial Approval | JOHN REGAN |
| Footing/Foundation/Slab | 10/27/2015 | Partial Approval | JOHN REGAN |
| Footing/Foundation/Slab | 12/11/2015 | Partial Approval | JOHN REGAN |
| Reinforced Masonry Frame | 12/23/2015 | Approved | DANIEL ORRANTE |
| Masonry Wall/Backfill | 1/20/2016 | Partial Inspection | JOHN REGAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2016 | Partial Approval | JOHN REGAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2016 | Corrections Issued | ERWIN LARRANAGA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2016 | Approved | JOHN REGAN |
| Footing/Foundation/Slab | 2/29/2016 | Partial Approval | JOHN LUMB |
| Interior/Exterior Lathing | 2/29/2016 | Partial Approval | JOHN LUMB |
| ELECTRICAL-Rough | 4/25/2016 | Corrections Issued | JOHN REGAN |
| BUILDING-Rough-Frame | 5/4/2016 | Approved | JOHN REGAN |
| Green Building Rough | 5/4/2016 | Approved | JOHN REGAN |
| Drywall Nailing | 5/27/2016 | Approved | DAVID JAMES |
| PLUMBING-Rough | 5/27/2016 | Partial Inspection | DAVID JAMES |
| PLUMBING-Rough | 6/7/2016 | Approved | JOHN REGAN |
| Final | 9/13/2016 | Corrections Issued | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 9/13/2016 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| Green Building Final | 9/13/2016 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| SGSOV-Seismic Gas S/O Valve | 9/13/2016 | SGSOV Not Ready | JOEL LAUNCHBAUGH |
| Smoke Detectors | 9/13/2016 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| Final | 1/25/2017 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 1/25/2017 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| Green Building Final | 1/25/2017 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| SGSOV-Seismic Gas S/O Valve | 1/25/2017 | SGSOV Not Ready | JOEL LAUNCHBAUGH |
| Smoke Detectors | 1/25/2017 | Not Ready for Inspection | JOEL LAUNCHBAUGH |
| Final | 3/7/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 3/7/2018 | Approved | JOEL LAUNCHBAUGH |
| Green Building Final | 3/7/2018 | Approved | JOEL LAUNCHBAUGH |
| SGSOV-Seismic Gas S/O Valve | 3/7/2018 | SGSOV Approved | JOEL LAUNCHBAUGH |
| Smoke Detectors | 3/7/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Final | 11/14/2024 | Corrections Issued | MICHAEL PELHAM |
| Smoke Detectors | 11/14/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Final | 12/6/2024 | OK to Issue CofO | SEAN HAUPT |
| Smoke Detectors | 12/6/2024 | Approved | SEAN HAUPT |