4980 N ALATAR DR 91364
Certificate Information: 4980 N ALATAR DR 91364
- Application / Permit
- 15014-20000-01492
- Plan Check / Job No.
- B15VN04342
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADD (N) 499 SF 2ND FLOOR ACCESSORY LIVING QUARTER ON THE TOP OF EXISTING DETACHED 2-CAR GARAGE. & 208 SF ROOFED PATIO @ 1ST FLOOR. <<SPRINKLERS REQ'D THROUGHOUT>>
- Permit Issued
- Issued on 4/6/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2015 | ABDUL CHEGENI |
| Corrections Issued | 5/29/2015 | ABDUL CHEGENI |
| Quality Review Completed | 6/4/2015 | TIEN JEN WANG |
| Building Plans Picked Up | 7/15/2015 | APPLICANT |
| Green Plans Picked Up | 7/15/2015 | APPLICANT |
| Applicant returned to address corrections | 8/19/2015 | ABDUL CHEGENI |
| Applicant returned to address corrections | 9/23/2015 | ABDUL CHEGENI |
| Applicant returned to address corrections | 11/17/2015 | ABDUL CHEGENI |
| Applicant returned to address corrections | 12/1/2015 | ABDUL CHEGENI |
| Plan Check Approved | 8/9/2016 | ABDUL CHEGENI |
| Issued | 4/6/2017 | LADBS |
| CofO in Progress | 2/20/2020 | DAVID STEPANYAN |
| Permit Finaled | 2/20/2020 | JOHN JANSON |
| CofO Issued | 2/20/2020 | JOHN JANSON |
| Permit Finaled | 2/20/2020 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/25/2015 | MIKE KOUYOUMDJIAN |
| BHO/Hillside ordinance | Cleared | 9/25/2015 | MIKE KOUYOUMDJIAN |
| Roof/Waste drainage to street | Cleared | 11/17/2015 | LEE GUILBEAUX |
| Specific Plan | Cleared | 11/17/2015 | ISAIAH ROSS |
| Specific Plan | Cleared | 11/17/2015 | ISAIAH ROSS |
| Green Code | Cleared | 11/20/2015 | MICKEY YAMASHITA |
| GPI Written Notices | Cleared | 12/1/2015 | ABDUL CHEGENI |
| Grading Pre-Inspection | Cleared | 12/1/2015 | ABDUL CHEGENI |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2016 | ROBERT SAMONTE |
| Sewer availability | Cleared | 8/9/2016 | ROBERT SAMONTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amoroso, Michael Joseph; Lic. No.: L5392 | 16145 ROSCOE BLVD NORTH HILLS, CA 91343 |
| Engineer | Vasquez, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/1/2017 | No Access for Inspection | ROBERT SHELLY |
| Footing/Foundation/Slab | 6/8/2017 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/22/2017 | No Access for Inspection | VINCENT HANLEY |
| Green Building Rough | 6/22/2017 | No Access for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/22/2017 | No Access for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/26/2017 | Partial Inspection | JOHN COLEMAN |
| Green Building Rough | 6/26/2017 | Partial Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 6/26/2017 | Partial Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2017 | Not Ready for Inspection | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2017 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 7/26/2017 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 8/7/2017 | Conditional Approval | JOHN COLEMAN |
| Green Building Rough | 8/7/2017 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 8/7/2017 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 8/7/2017 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 8/8/2017 | Approved | JOHN COLEMAN |
| Gas Test | 8/8/2017 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 8/8/2017 | Approved | JOHN COLEMAN |
| Smoke Detectors | 8/8/2017 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/15/2018 | Approved | MICHAEL TEMPLE |
| Drywall Nailing | 5/15/2018 | Approved | MICHAEL TEMPLE |
| Final | 5/15/2018 | No Access for Inspection | MICHAEL TEMPLE |
| Green Building Final | 5/15/2018 | No Access for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/15/2018 | SGSOV Not Ready | MICHAEL TEMPLE |
| ELECTRICAL-Final | 6/5/2018 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 6/5/2018 | Approved | MICHAEL TEMPLE |
| Final | 1/8/2020 | Not Ready for Inspection | JOHN JANSON |
| SGSOV-Seismic Gas S/O Valve | 1/8/2020 | SGSOV Not Ready | JOHN JANSON |
| Special/Order Compliance | 1/8/2020 | Corrections Issued | JOHN JANSON |
| Final | 2/19/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 2/19/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/19/2020 | SGSOV Approved | DAVID STEPANYAN |