1648 N SUMMITRIDGE DR 90210

Certificate Information: 1648 N SUMMITRIDGE DR 90210

Application / Permit
15014-20000-00812
Plan Check / Job No.
B15VN02389
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel entire (E)SFD. 38'-10" x 12' irreg. shaped addition with 3'-6" x 13'-5" and 12' x 4' deck on top level. 33' x 4' roofed deck at 2nd floor level above (E)garage.
Permit Issued
Issued on 11/18/2015
Issuing Office
Valley
Current Status
Issued on 11/18/2015
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/26/2015 APPLICANT
Assigned to Plan Check Engineer 3/12/2015 STEVEN KIM
Green Plans Picked Up 3/12/2015 APPLICANT
Corrections Issued 3/17/2015 STEVEN KIM
Quality Review Completed 3/18/2015 BINH PHAN
Building Plans Picked Up 3/23/2015 APPLICANT
Applicant returned to address corrections 4/7/2015 STEVEN KIM
Applicant returned to address corrections 9/23/2015 STEVEN KIM
Applicant returned to address corrections 9/25/2015 STEVEN KIM
Plan Check Approved 11/18/2015 STEVEN KIM
Issued 11/18/2015 LADBS

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/29/2015 ROBERT DUFF
Low Impact Development Cleared 4/29/2015 MARTIN FRAGOSO
Sewer availability Cleared 4/29/2015 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 11/6/2015 RICHARD SOUTHERLAND
Permit Cleared 11/6/2015 RICHARD SOUTHERLAND
Roof/Waste drainage to street Cleared 11/6/2015 RICHARD SOUTHERLAND
Green Code Cleared 11/18/2015 BRYAN MEYER

Contact Information

Architect Heinritz, Christopher Arthur; Lic. No.: C23507 P.O. BOX 1207      NEWCASTLE, CA 95658
Contractor Owner-Builder       ,
Engineer Lopez, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786
Engineer Rybak, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Geologist Haenschke, Eirik Francis; Lic. No.: EG1597 9001 MONOGRAM AVENUE      NORTH HILLS, CA 91343

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/7/2015 Corrections Issued JOHN REGAN
ELECTRICAL-Rough 12/7/2015 Not Ready for Inspection JOHN REGAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2015 Not Ready for Inspection JOHN REGAN
Green Building Rough 12/7/2015 Approved JOHN REGAN
PLUMBING-Rough 12/7/2015 Not Ready for Inspection JOHN REGAN
ELECTRICAL-Rough 12/9/2015 Not Ready for Inspection JOHN REGAN
PLUMBING-Rough 12/9/2015 Corrections Issued JOHN REGAN
ELECTRICAL-Rough 12/15/2015 Not Ready for Inspection JOHN REGAN
PLUMBING-Rough 12/15/2015 Not Ready for Inspection JOHN REGAN
ELECTRICAL-Rough 12/16/2015 Approved JOHN REGAN
Insulation 12/16/2015 Partial Approval JOHN REGAN
PLUMBING-Rough 12/16/2015 Approved JOHN REGAN
Drywall Nailing 12/28/2015 Approved JOHN REGAN
Footing/Foundation/Slab 2/4/2016 No Access for Inspection RONALD MYRICK
Footing/Foundation/Slab 2/5/2016 Not Ready for Inspection RONALD MYRICK
Interior/Exterior Lathing 2/16/2016 Approved JOHN REGAN
BUILDING-Rough-Frame 4/18/2016 Approved JOHN REGAN
Interior/Exterior Lathing 4/18/2016 Approved JOHN REGAN
Rough-Elec/Plmb/HVAC 4/18/2016 Approved JOHN REGAN
Interior/Exterior Lathing 5/11/2016 Corrections Issued JOHN JANSON
Interior/Exterior Lathing 5/18/2016 Approved JOHN REGAN
PLUMBING-Rough 10/29/2018 Approved CARLOS MATAMOROS
Pre-Inspection 11/25/2020 OK to Expire Permit ANTHONY MCDOWALL
Special/Order Compliance 1/8/2021 Partial Approval ANTHONY MCDOWALL
Final 3/11/2024 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 3/11/2024 Approved SEAN HAUPT
Green Building Final 3/11/2024 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 3/11/2024 Not Ready for Inspection SEAN HAUPT
Final 3/22/2024 Corrections Issued SEAN HAUPT
Green Building Final 3/22/2024 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 3/22/2024 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 2/18/2026 Not Ready for Inspection CARLOS MATAMOROS
Final 3/17/2026 Corrections Issued CARLOS MATAMOROS
Green Building Final 3/17/2026 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 3/17/2026 Corrections Issued CARLOS MATAMOROS