10600 N LEMONA AVE 91345

Certificate Information: 10600 N LEMONA AVE 91345

Application / Permit
15014-20000-00027
Plan Check / Job No.
B15VN00093
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Propose 14'9" x 25'6" 2-story addition at South-East corner for family room on ground floor and new master bed/bathroom on 2nd floor.
Permit Issued
Issued on 4/14/2015
Issuing Office
Valley
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2015 APPLICANT
Assigned to Plan Check Engineer 1/29/2015 ALDOUS CHIC
Corrections Issued 2/2/2015 ALDOUS CHIC
Quality Review Completed 2/6/2015 BINH PHAN
Building Plans Picked Up 2/11/2015 APPLICANT
Green Plans Picked Up 2/11/2015 APPLICANT
Plan Check Approved 4/13/2015 ALDOUS CHIC
Issued 4/14/2015 LADBS
Permit Expired-Status Void 1/30/2020 ROBERT MINASSIANS
Re-Activate Permit 2/5/2020 ALDO UBAU
CofO in Progress 10/22/2021 JENNIFER RABUCHIN
CofO Issued 3/10/2022 RONALD MYRICK
Permit Finaled 3/10/2022 RONALD MYRICK

Permit Application Clearance Information

Abandoned oil well Cleared 2/11/2015 JOSEPH JACKSON
Eng Process Fee Ord 176,300 Cleared 3/13/2015 SANDRA FIGUEROA
Permit Cleared 3/13/2015 SANDRA FIGUEROA
Roof/Waste drainage to street Cleared 3/13/2015 SANDRA FIGUEROA
Sewer availability Cleared 3/13/2015 SANDRA FIGUEROA
Public Works-Highway Ded. Cleared 3/13/2015 SANDRA FIGUEROA
Public Works-Open Permits Cleared 3/13/2015 SANDRA FIGUEROA
Public Works-Sewers Cleared 3/13/2015 SANDRA FIGUEROA
Green Code Cleared 4/1/2015 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Adams, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2015 Not Ready for Inspection BRUCE ROZAK
Footing/Foundation/Slab 8/27/2015 Approved BRUCE ROZAK
Underground Mechanical 9/22/2015 Not Ready for Inspection BRUCE ROZAK
PLUMBING-Rough 9/28/2015 Not Ready for Inspection BRUCE ROZAK
PLUMBING-Rough 9/30/2015 Partial Approval PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 10/13/2015 Partial Approval BRUCE ROZAK
BUILDING-Rough-Frame 1/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Drywall Nailing 1/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Final 1/30/2020 Permit Expired-Status Void ROBERT MINASSIANS
Green Building Final 1/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Green Building Rough 1/30/2020 Not Ready for Inspection ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 1/30/2020 No Access for Inspection ROBERT MINASSIANS
Smoke Detectors 1/30/2020 Not Ready for Inspection ROBERT MINASSIANS
Special/Order Compliance 3/18/2020 Approved ROBERT MINASSIANS
Special/Order Compliance 3/18/2020 Partial Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/25/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/25/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/25/2020 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 3/25/2020 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/25/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 4/7/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/8/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 10/8/2021 Approved JENNIFER RABUCHIN
Final 10/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 10/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/8/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 10/8/2021 Approved JENNIFER RABUCHIN
Final 10/15/2021 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 10/15/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/22/2021 Approved JENNIFER RABUCHIN
Final 10/22/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/22/2021 Approved JENNIFER RABUCHIN
HVAC-Final 10/22/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/22/2021 Approved JENNIFER RABUCHIN