9510 S VERMONT AVE 90044
Certificate Information: 9510 S VERMONT AVE 90044
- Application / Permit
- 15014-10000-05927
- Plan Check / Job No.
- B15LA17937
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- RENOVATION AND ADDITION TO EXISTING RETAIL BLDG. CORE AND SHELL ONLY FOR NEW ADDITION AREA.
- Permit Issued
- Issued on 1/9/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2015 | APPLICANT |
| Disabled Access Plans Picked Up | 1/7/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2016 | LARRY LEE |
| Corrections Issued | 1/20/2016 | LARRY LEE |
| Green Plans Picked Up | 1/21/2016 | APPLICANT |
| Quality Review Completed | 1/27/2016 | BILL STUTSMAN |
| Building Plans Picked Up | 2/2/2016 | APPLICANT |
| Applicant returned to address corrections | 4/18/2016 | LARRY LEE |
| Applicant returned to address corrections | 4/4/2018 | LARRY LEE |
| Plan Check Approved | 1/2/2019 | LARRY LEE |
| Issued | 1/9/2019 | LADBS |
| TCO Issued (Expire Date: 01-23-2021) | 7/27/2020 | DAVID TSAU |
| CofO in Progress | 2/2/2021 | ERNESTO CORRAL |
| Permit Finaled | 2/2/2021 | ERNESTO CORRAL |
| CofO Issued | 2/2/2021 | ERNESTO CORRAL |
| Permit Finaled | 2/2/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/2/2016 | SHINE LIN |
| Green Code | Cleared | 2/2/2016 | ROLLIN GETTLE III |
| Hydrant and Access approval | Cleared | 3/31/2016 | JOHN CONNEALLY |
| Permit | Cleared | 3/31/2016 | ARNULFO NUNO |
| Work Adjacent to Public Way | Cleared | 3/31/2016 | WARREN LIU |
| ZA Case | Cleared | 3/31/2016 | ERIC CLAROS |
| ZA Case | Cleared | 3/31/2016 | ERIC CLAROS |
| Comm Cor/Mini-Mall | Cleared | 4/9/2018 | SEAN VEAL |
| Comm Cor/Mini-Mall | Cleared | 4/9/2018 | SEAN VEAL |
| Prkng lot landscape/Water mgmt | Cleared | 4/9/2018 | SEAN VEAL |
| ZA Case | Cleared | 4/9/2018 | SEAN VEAL |
| Driveway location | Cleared | 4/19/2018 | MOHAMMAD HASAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2018 | CELINA MORENO |
| Highway dedication | Cleared | 6/6/2018 | CELINA MORENO |
| Sewer availability | Cleared | 7/9/2018 | JAMES MORALEZ |
| Low Impact Development | Cleared | 7/16/2018 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 7/16/2018 | CARLA VALLADARES |
| Bicycle Parking | Cleared | 1/3/2019 | KARAN PATEL |
Contact Information
| Architect | Sigler, Shannon Kendel; Lic. No.: C21861 | 4849 EDGEWARE RD SAN DIEGO, CA 92116 |
| Contractor | Mc Guan Construction & Plumbing; Lic. No.: 862056-B | 27634 SYCAMORE CREEK DR VALENCIA, CA 91354 |
| Engineer | Tran, Cong Hoai; Lic. No.: C75730 | 8021 EPPICK CT LEMON GROVE, CA 91945 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/21/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/9/2019 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 4/9/2019 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 4/12/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 5/2/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 5/3/2019 | Approved | JOEY BUCHANAN |
| Green Building Rough | 5/8/2019 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 5/8/2019 | Partial Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 5/14/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 5/16/2019 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 5/20/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 6/13/2019 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 6/17/2019 | Partial Approval | JOEY BUCHANAN |
| Pre-Inspection | 6/19/2019 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/8/2019 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 9/3/2019 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/3/2019 | Partial Approval | JAMES POWERS |
| Wood Frame | 10/1/2019 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/22/2019 | Corrections Issued | JOEY BUCHANAN |
| Drywall Nailing | 12/23/2019 | Partial Approval | DARRYL ARNOLD |
| Drywall Nailing | 1/7/2020 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 2/20/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Reinforced Masonry Frame | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Smoke Detectors | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Structural Steel Frame | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 4/23/2020 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 5/6/2020 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Pre-Inspection | 5/8/2020 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 5/8/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Drywall Nailing | 5/18/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 5/20/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 5/20/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 5/20/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 5/20/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Drywall Nailing | 7/8/2020 | Approved | LEOPOLDO MENDOZA |
| Final | 7/8/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 7/8/2020 | Approved | LEOPOLDO MENDOZA |
| Green Building Final | 7/8/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 7/8/2020 | Approved | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV No Gas | LEOPOLDO MENDOZA |
| Smoke Detectors | 7/8/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Structural Steel Frame | 7/8/2020 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 7/8/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 7/10/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 7/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 7/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Smoke Detectors | 7/15/2020 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 7/15/2020 | Approved | LEOPOLDO MENDOZA |
| Final | 7/20/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 7/20/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 7/29/2020 | OK for TCO | LEOPOLDO MENDOZA |
| Green Building Final | 7/29/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Special/Order Compliance | 1/4/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 1/21/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 1/26/2021 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 1/26/2021 | Conditional Approval | LANNY MERRICK |
| Final | 1/28/2021 | Conditional Approval | LANNY MERRICK |
| Green Building Final | 1/28/2021 | Approved | LANNY MERRICK |
| Final | 2/2/2021 | OK to Issue CofO | ERNESTO CORRAL |