9510 S VERMONT AVE 90044

Certificate Information: 9510 S VERMONT AVE 90044

Application / Permit
15014-10000-05927
Plan Check / Job No.
B15LA17937
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
RENOVATION AND ADDITION TO EXISTING RETAIL BLDG. CORE AND SHELL ONLY FOR NEW ADDITION AREA.
Permit Issued
Issued on 1/9/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2015 APPLICANT
Disabled Access Plans Picked Up 1/7/2016 APPLICANT
Assigned to Plan Check Engineer 1/14/2016 LARRY LEE
Corrections Issued 1/20/2016 LARRY LEE
Green Plans Picked Up 1/21/2016 APPLICANT
Quality Review Completed 1/27/2016 BILL STUTSMAN
Building Plans Picked Up 2/2/2016 APPLICANT
Applicant returned to address corrections 4/18/2016 LARRY LEE
Applicant returned to address corrections 4/4/2018 LARRY LEE
Plan Check Approved 1/2/2019 LARRY LEE
Issued 1/9/2019 LADBS
TCO Issued (Expire Date: 01-23-2021) 7/27/2020 DAVID TSAU
CofO in Progress 2/2/2021 ERNESTO CORRAL
Permit Finaled 2/2/2021 ERNESTO CORRAL
CofO Issued 2/2/2021 ERNESTO CORRAL
Permit Finaled 2/2/2021 ERNESTO CORRAL

Permit Application Clearance Information

DAS Clearance Cleared 2/2/2016 SHINE LIN
Green Code Cleared 2/2/2016 ROLLIN GETTLE III
Hydrant and Access approval Cleared 3/31/2016 JOHN CONNEALLY
Permit Cleared 3/31/2016 ARNULFO NUNO
Work Adjacent to Public Way Cleared 3/31/2016 WARREN LIU
ZA Case Cleared 3/31/2016 ERIC CLAROS
ZA Case Cleared 3/31/2016 ERIC CLAROS
Comm Cor/Mini-Mall Cleared 4/9/2018 SEAN VEAL
Comm Cor/Mini-Mall Cleared 4/9/2018 SEAN VEAL
Prkng lot landscape/Water mgmt Cleared 4/9/2018 SEAN VEAL
ZA Case Cleared 4/9/2018 SEAN VEAL
Driveway location Cleared 4/19/2018 MOHAMMAD HASAN
Eng Process Fee Ord 176,300 Cleared 6/6/2018 CELINA MORENO
Highway dedication Cleared 6/6/2018 CELINA MORENO
Sewer availability Cleared 7/9/2018 JAMES MORALEZ
Low Impact Development Cleared 7/16/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 7/16/2018 CARLA VALLADARES
Bicycle Parking Cleared 1/3/2019 KARAN PATEL

Contact Information

Architect Sigler, Shannon Kendel; Lic. No.: C21861 4849 EDGEWARE RD      SAN DIEGO, CA 92116
Contractor Mc Guan Construction & Plumbing; Lic. No.: 862056-B 27634 SYCAMORE CREEK DR      VALENCIA, CA 91354
Engineer Tran, Cong Hoai; Lic. No.: C75730 8021 EPPICK CT      LEMON GROVE, CA 91945

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/21/2019 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 4/9/2019 Approved JOEY BUCHANAN
Deputy Steel/Welding 4/9/2019 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 4/12/2019 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 5/2/2019 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 5/3/2019 Approved JOEY BUCHANAN
Green Building Rough 5/8/2019 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/8/2019 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 5/14/2019 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 5/16/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 5/20/2019 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 6/13/2019 Approved JOEY BUCHANAN
Pre-Inspection 6/17/2019 Partial Approval JOEY BUCHANAN
Pre-Inspection 6/19/2019 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 7/8/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/3/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/3/2019 Partial Approval JAMES POWERS
Wood Frame 10/1/2019 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 11/22/2019 Corrections Issued JOEY BUCHANAN
Drywall Nailing 12/23/2019 Partial Approval DARRYL ARNOLD
Drywall Nailing 1/7/2020 Approved JOEY BUCHANAN
Light Gage Steel Frame 2/20/2020 Partial Approval RUSSELL BONVOULOIR
Final 4/23/2020 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection LANNY MERRICK
Green Building Final 4/23/2020 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 4/23/2020 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 4/23/2020 Not Ready for Inspection LANNY MERRICK
Smoke Detectors 4/23/2020 Not Ready for Inspection LANNY MERRICK
Structural Steel Frame 4/23/2020 Not Ready for Inspection LANNY MERRICK
Wood Frame 4/23/2020 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 5/6/2020 SGSOV Not Ready LEOPOLDO MENDOZA
Pre-Inspection 5/8/2020 Approved JOEY BUCHANAN
T-Bar Ceiling 5/8/2020 Corrections Issued LEOPOLDO MENDOZA
Drywall Nailing 5/18/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 5/20/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 5/20/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Pre-Inspection 5/20/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 5/20/2020 Corrections Issued LEOPOLDO MENDOZA
Drywall Nailing 7/8/2020 Approved LEOPOLDO MENDOZA
Final 7/8/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 7/8/2020 Approved LEOPOLDO MENDOZA
Green Building Final 7/8/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Reinforced Masonry Frame 7/8/2020 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV No Gas LEOPOLDO MENDOZA
Smoke Detectors 7/8/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Structural Steel Frame 7/8/2020 Approved LEOPOLDO MENDOZA
Wood Frame 7/8/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Pre-Inspection 7/10/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Final 7/15/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 7/15/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Smoke Detectors 7/15/2020 Approved LEOPOLDO MENDOZA
Wood Frame 7/15/2020 Approved LEOPOLDO MENDOZA
Final 7/20/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 7/20/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Final 7/29/2020 OK for TCO LEOPOLDO MENDOZA
Green Building Final 7/29/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Special/Order Compliance 1/4/2021 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 1/21/2021 Not Ready for Inspection LANNY MERRICK
Final 1/26/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 1/26/2021 Conditional Approval LANNY MERRICK
Final 1/28/2021 Conditional Approval LANNY MERRICK
Green Building Final 1/28/2021 Approved LANNY MERRICK
Final 2/2/2021 OK to Issue CofO ERNESTO CORRAL