1829 S LONGWOOD AVE 90019
Certificate Information: 1829 S LONGWOOD AVE 90019
- Application / Permit
- 15014-10000-05879
- Plan Check / Job No.
- B15LA17774
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION 376 SF AND NEW REAR PORCH 60 SF.
- Permit Issued
- Issued on 1/4/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2016
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 12/21/2015 | APPLICANT |
Assigned to Plan Check Engineer | 12/21/2015 | JAMES DETCHMENDY |
Corrections Issued | 12/21/2015 | JAMES DETCHMENDY |
Plan Check Approved | 1/4/2016 | SERGIO SILVA |
Issued | 1/4/2016 | LADBS |
CofO in Progress | 12/10/2016 | ROBERT MCDOWELL |
CofO Issued | 12/14/2016 | MARK CASEY |
Permit Finaled | 12/14/2016 | MARK CASEY |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 12/29/2015 | RAVIL MANAPOV |
Roof/Waste drainage to street | Cleared | 12/29/2015 | RAVIL MANAPOV |
Sewer availability | Cleared | 12/29/2015 | RAVIL MANAPOV |
Contact Information
Contractor | West Coast Rivers Construction Co; Lic. No.: 892174-B | P O BOX 146 DOWNEY, CA 90241 |
Engineer | Mena, Rolando A; Lic. No.: C50331 | 544 1/2 BRITTANIA ST #A LOS ANGELES, CA 90033 |
Inspector Information
JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 1/7/2016 | Approved | DAVID CHAN |
METHANE-Barrier | 1/7/2016 | Approved | DAVID CHAN |
METHANE-Subgrade | 1/7/2016 | Approved | DAVID CHAN |
HVAC-Rough | 3/25/2016 | Approved | DAVID CHAN |
METHANE-Rough | 3/25/2016 | Approved | DAVID CHAN |
PLUMBING-Rough | 3/25/2016 | Not Ready for Inspection | DAVID CHAN |
BUILDING-Rough-Frame | 4/4/2016 | Approved | DAVID CHAN |
ELECTRICAL-Rough | 4/4/2016 | Approved | DAVID CHAN |
PLUMBING-Rough | 4/4/2016 | Approved | DAVID CHAN |
ELECTRICAL-Final | 10/3/2016 | Approved | ROBERT MCDOWELL |
Final | 10/3/2016 | Corrections Issued | ROBERT MCDOWELL |
HVAC-Final | 10/3/2016 | Approved | ROBERT MCDOWELL |
PLUMBING-Final | 10/3/2016 | Approved | ROBERT MCDOWELL |
SGSOV-Seismic Gas S/O Valve | 10/3/2016 | SGSOV Not Ready | ROBERT MCDOWELL |
Service/Power Release | 10/3/2016 | Approved | ROBERT MCDOWELL |
Smoke Detectors | 10/3/2016 | Approved | ROBERT MCDOWELL |
Final | 10/17/2016 | Not Ready for Inspection | MATTHEW NUCKOLLS |
SGSOV-Seismic Gas S/O Valve | 10/17/2016 | SGSOV Not Ready | MATTHEW NUCKOLLS |
Final | 12/9/2016 | OK to Issue CofO | ROBERT MCDOWELL |
SGSOV-Seismic Gas S/O Valve | 12/9/2016 | SGSOV Approved | ROBERT MCDOWELL |