Excavation/Setback/Form/Re-Bar
|
9/6/2018
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
9/14/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
9/27/2018
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
10/1/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/3/2018
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
10/4/2018
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
10/9/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/10/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/12/2018
|
Partial Approval
|
TED RIES
|
|
Green Building Rough
|
10/12/2018
|
Not Ready for Inspection
|
TED RIES
|
|
Wood Frame
|
10/12/2018
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Excavation/Setback/Form/Re-Bar
|
10/30/2018
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
11/7/2018
|
Not Ready for Inspection
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
11/9/2018
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
11/9/2018
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2018
|
Partial Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
12/19/2018
|
Partial Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
1/4/2019
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Reinforced Concrete Frame
|
1/24/2019
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
1/28/2019
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
2/4/2019
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
3/7/2019
|
Partial Approval
|
TED RIES
|
|
Insulation
|
3/7/2019
|
Partial Approval
|
TED RIES
|
|
Light Gage Steel Frame
|
3/7/2019
|
Corrections Issued
|
TED RIES
|
|
Drywall Nailing
|
3/20/2019
|
Partial Approval
|
TED RIES
|
|
Green Building Rough
|
3/26/2019
|
Not Ready for Inspection
|
TED RIES
|
|
Light Gage Steel Frame
|
3/26/2019
|
Partial Inspection
|
TED RIES
|
|
Wood Frame
|
3/26/2019
|
Partial Inspection
|
TED RIES
|
|
Footing/Foundation/Slab
|
3/28/2019
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Drywall Nailing
|
4/2/2019
|
Partial Approval
|
TED RIES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/5/2019
|
Partial Approval
|
TED RIES
|
|
Green Building Rough
|
4/5/2019
|
Not Ready for Inspection
|
TED RIES
|
|
Insulation
|
4/5/2019
|
Approved
|
TED RIES
|
|
Light Gage Steel Frame
|
4/5/2019
|
Partial Approval
|
TED RIES
|
|
Reinforced Concrete Frame
|
4/5/2019
|
Partial Approval
|
TED RIES
|
|
Wood Frame
|
4/5/2019
|
Approved
|
TED RIES
|
|
Interior/Exterior Lathing
|
4/9/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/12/2019
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
4/18/2019
|
Partial Approval
|
TED RIES
|
|
Light Gage Steel Frame
|
5/2/2019
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/3/2019
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
5/15/2019
|
Partial Approval
|
TED RIES
|
|
Light Gage Steel Frame
|
5/28/2019
|
Partial Approval
|
TED RIES
|
|
Insulation
|
6/20/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
7/3/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
7/8/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
8/15/2019
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Final
|
8/27/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
8/27/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Final
|
8/27/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
8/27/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
SGSOV-Seismic Gas S/O Valve
|
8/27/2019
|
SGSOV Not Ready
|
DANIEL MC AULIFFE
|
|
Smoke Detectors
|
8/27/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
8/27/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Final
|
9/4/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
9/4/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Final
|
9/4/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
SGSOV-Seismic Gas S/O Valve
|
9/4/2019
|
SGSOV Approved
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
9/4/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
9/6/2019
|
Corrections Issued
|
DANIEL MC AULIFFE
|
|
Final
|
3/16/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
3/16/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Green Building Final
|
3/16/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
3/16/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Special/Order Compliance
|
4/2/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Final
|
1/10/2022
|
Conditional Approval
|
DANIEL MC AULIFFE
|