3935 N VALLEY MEADOW ROAD 91436
Certificate Information: 3935 N VALLEY MEADOW ROAD 91436
- Application / Permit
- 15014-10000-05364
- Plan Check / Job No.
- B15LA16362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New accessory living quarters with attached 2-car garage.
- Permit Issued
- Issued on 8/29/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2015 | APPLICANT |
| Green Plans Picked Up | 11/30/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2015 | MANUEL GARCIA |
| Corrections Issued | 12/21/2015 | MANUEL GARCIA |
| Quality Review Completed | 12/22/2015 | GARO TELMI |
| Building Plans Picked Up | 12/23/2015 | APPLICANT |
| Applicant returned to address corrections | 2/25/2016 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/9/2016 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/15/2016 | MANUEL GARCIA |
| Plan Check Approved | 4/6/2016 | MANUEL GARCIA |
| Issued | 8/29/2016 | LADBS |
| CofO in Progress | 8/7/2025 | SEAN WIRCH |
| Permit Finaled | 10/4/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/4/2025 | MICHAEL PELHAM |
| CofO Issued | 10/4/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/13/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 1/13/2016 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 1/13/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 1/22/2016 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/26/2016 | MICHAEL SCADUTO |
| Green Code | Cleared | 1/27/2016 | ROLLIN GETTLE III |
| Roof/Waste drainage to street | Cleared | 2/25/2016 | NATALIE MOORE |
| BHO/Hillside ordinance | Cleared | 2/29/2016 | ARMEN DERMENJIAN |
| BHO/Hillside ordinance | Cleared | 3/4/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 3/4/2016 | LEE GUILBEAUX |
| Address approval | Cleared | 3/9/2016 | NATALIE MOORE |
| Grading Pre-Inspection | Cleared | 3/15/2016 | MANUEL GARCIA |
Contact Information
| Contractor | Taz Construction Inc; Lic. No.: 783969-B | 4314 SHERMAN OAKS AVE SHERMAN OAKS, CA 91403 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2016 | No Access for Inspection | ROBERT SHELLY |
| Footing/Foundation/Slab | 10/12/2016 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/14/2016 | Approved | MICHAEL TEMPLE |
| Deputy Reinf. Concrete | 10/19/2016 | Conditional Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 11/2/2016 | No Access for Inspection | ROBERT SHELLY |
| Reinforced Masonry Frame | 11/2/2016 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2016 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2017 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/8/2017 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2017 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 3/9/2017 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/4/2017 | Approved | JOHN HAYES |
| Green Building Rough | 4/4/2017 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/4/2017 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/4/2017 | Approved | JOHN HAYES |
| Insulation | 5/2/2017 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/18/2017 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/26/2017 | Approved | ARTHUR SARGSYAN |
| Gas Test | 6/13/2017 | Approved | JOHN HAYES |
| Underground Mechanical | 6/13/2017 | Approved | JOHN HAYES |
| Sewer | 6/20/2017 | Approved | JOHN HAYES |
| Underground Mechanical | 6/20/2017 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/12/2017 | Approved | JOHN COLEMAN |
| Final | 10/12/2017 | Partial Inspection | JOHN COLEMAN |
| Green Building Final | 10/12/2017 | Approved | JOHN COLEMAN |
| HVAC-Final | 10/12/2017 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 10/12/2017 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2017 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 10/12/2017 | Approved | JOHN COLEMAN |
| Smoke Detectors | 10/12/2017 | Approved | JOHN COLEMAN |
| Final | 2/3/2025 | Corrections Issued | JOHN COLEMAN |
| Special/Order Compliance | 3/19/2025 | Corrections Issued | JOHN COLEMAN |
| Final | 8/8/2025 | OK to Issue CofO | SEAN WIRCH |