11027 N MEMORY PARK AVE 91345
Certificate Information: 11027 N MEMORY PARK AVE 91345
- Application / Permit
- 15014-10000-04767
- Plan Check / Job No.
- B15LA14603
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 799 SQ FT ADDITION TO (E) 1-STORY SFD. See comments.
- Permit Issued
- Issued on 12/3/2015
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2015 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/16/2015 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/12/2015 | TU HUA |
| Applicant returned to address corrections | 11/30/2015 | MINYE PAK |
| Issued | 12/3/2015 | LADBS |
| CofO in Progress | 9/6/2019 | JENNIFER RABUCHIN |
| CofO in Progress | 9/6/2019 | JENNIFER RABUCHIN |
| Permit Finaled | 2/19/2020 | MICHAEL SMITH |
| CofO Issued | 2/19/2020 | MICHAEL SMITH |
| Permit Finaled | 2/19/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2015 | PAMELA TENEZA |
| Low Impact Development | Cleared | 11/30/2015 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/30/2015 | AVALYN KAMACHI |
| Sewer availability | Cleared | 11/30/2015 | PAMELA TENEZA |
Contact Information
| Engineer | Perez, Thomas E; Lic. No.: C67549 | 1521 FRANZEN AVE SANTA ANA, CA 92703 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2015 | Approved | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 1/6/2016 | Not Ready for Inspection | DONALD GALLAGHER |
| PLUMBING-Rough | 1/6/2016 | Partial Approval | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 1/13/2016 | Partial Approval | DONALD GALLAGHER |
| PLUMBING-Rough | 1/13/2016 | Partial Approval | DONALD GALLAGHER |
| Insulation | 1/19/2016 | Partial Approval | DONALD GALLAGHER |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2016 | Partial Approval | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 2/11/2016 | Not Ready for Inspection | DONALD GALLAGHER |
| ELECTRICAL-Rough | 2/11/2016 | Corrections Issued | DONALD GALLAGHER |
| Green Building Rough | 2/11/2016 | Corrections Issued | DONALD GALLAGHER |
| PLUMBING-Rough | 2/11/2016 | Corrections Issued | DONALD GALLAGHER |
| ELECTRICAL-Rough | 2/25/2016 | Approved | DONALD GALLAGHER |
| Interior/Exterior Lathing | 2/25/2016 | Partial Approval | DONALD GALLAGHER |
| PLUMBING-Rough | 2/25/2016 | Approved | DONALD GALLAGHER |
| Drywall Nailing | 2/29/2016 | Not Ready for Inspection | DONALD GALLAGHER |
| Green Building Rough | 2/29/2016 | Approved | DONALD GALLAGHER |
| Insulation | 2/29/2016 | Not Ready for Inspection | DONALD GALLAGHER |
| Drywall Nailing | 3/3/2016 | Approved | DONALD GALLAGHER |
| Insulation | 3/3/2016 | Approved | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 3/24/2016 | Partial Inspection | LEE HELLINGER |
| BUILDING-Rough-Frame | 4/18/2016 | Partial Approval | MATT KELLERMAN |
| Final | 4/18/2016 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 4/18/2016 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2016 | SGSOV Not Ready | MATT KELLERMAN |
| Smoke Detectors | 4/18/2016 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 4/21/2016 | Approved | PIERRE VEGA |
| Final | 4/21/2016 | Corrections Issued | PIERRE VEGA |
| Green Building Final | 4/21/2016 | Corrections Issued | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2016 | SGSOV Approved | PIERRE VEGA |
| Final | 4/27/2016 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 4/27/2016 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 1/30/2019 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Final | 1/30/2019 | Not Ready for Inspection | CHARLES POWELL |
| Final | 2/7/2019 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 2/7/2019 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/21/2019 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/21/2019 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/23/2019 | Approved | JENNIFER RABUCHIN |
| Final | 8/23/2019 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/23/2019 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/23/2019 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/23/2019 | Approved | JENNIFER RABUCHIN |