6429 W SELMA AVE 90028

Certificate Information: 6429 W SELMA AVE 90028

Application / Permit
15014-10000-03880
Plan Check / Job No.
B15LA11904
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CONSTRUCTION OF TYPE 1A ONE STORY RATIL OCCUPANCY W/ 3 BELOW GRADE PARKING GARAGE
Permit Issued
Issued on 3/2/2016
Issuing Office
Metro
Current Status
Issued on 3/2/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2015 APPLICANT
Disabled Access Plans Picked Up 9/1/2015 APPLICANT
Assigned to Plan Check Engineer 9/17/2015 DEAN LEE
Corrections Issued 9/28/2015 DEAN LEE
Quality Review Completed 10/1/2015 LAWRENCE QUIRANTE
Building Plans Picked Up 10/1/2015 APPLICANT
Green Plans Picked Up 10/9/2015 APPLICANT
Applicant returned to address corrections 10/16/2015 DEAN LEE
Applicant returned to address corrections 10/23/2015 DEAN LEE
Applicant returned to address corrections 2/12/2016 DEAN LEE
Applicant returned to address corrections 2/24/2016 DEAN LEE
Plan Check Approved 2/25/2016 DEAN LEE
Issued 3/2/2016 LADBS

Permit Application Clearance Information

Encroachment in public way Cleared 9/28/2015 ARMENIA HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/28/2015 ARMENIA HERNANDEZ
"D" conditions Cleared 10/13/2015 ANDY RODRIGUEZ
Hydrant and Access approval Cleared 10/13/2015 ROBERT DUFF
ZA Case Cleared 10/13/2015 ANDY RODRIGUEZ
ZA Case Cleared 10/13/2015 ANDY RODRIGUEZ
ZA Case Cleared 10/13/2015 ANDY RODRIGUEZ
ZI Cleared 10/13/2015 ANDY RODRIGUEZ
Green Code Cleared 11/5/2015 JOHN KLARIN
DAS Clearance Cleared 11/13/2015 WAI LAU
Highway dedication Cleared 12/22/2015 JAMES KHO
Permit Cleared 12/24/2015 JAMES KHO
Sewer availability Cleared 12/24/2015 JAMES KHO
Driveway location Cleared 12/29/2015 COLLINS ALLAN
Internal circulation Cleared 12/29/2015 COLLINS ALLAN
Roof/Waste drainage to street Cleared 1/21/2016 NATALIE MOORE
Low Impact Development Cleared 2/2/2016 IDA MEISAMI-FARD
Project located in CRA area Cleared 2/10/2016 JIM URQUHART
Work Adjacent to Public Way Cleared 2/12/2016 WARREN LIU
Excavation more than 5-ft deep Cleared 2/19/2016 CALOSHA APPROVED

Contact Information

Architect Flammang, Barbara Hansen; Lic. No.: C13422 1625 OLYMPIC BLVD      SANTA MONICA, CA 90404
Contractor Five Chairs Construction; Lic. No.: 488672-B 1605 CAHUENGA BLVD      LOS ANGELES, CA 90028
Engineer Petroni, Matthew Brian; Lic. No.: C69473 1809 GOODMAN AVE      REDONDO BEACH, CA 90278
Engineer Wahba, Wahba Faris; Lic. No.: C33667 10041 SYLVIA AVE      NORTHRIDGE, CA 91324
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/13/2017 Approved SAKO AGHAZARIAN
Pre-Inspection 4/10/2017 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 11/21/2017 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/27/2017 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/2/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/3/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/4/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/5/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/8/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/9/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/10/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/11/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/12/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/16/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/17/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/18/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/19/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 1/19/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/6/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/7/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/8/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 2/9/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 2/12/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/13/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/14/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/15/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/16/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/16/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/22/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/23/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/26/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 2/27/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/27/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/28/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/28/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 3/1/2018 Conditional Approval TED RIES
Deputy Shotcrete 3/1/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 3/2/2018 No Access for Inspection TED RIES
Deputy Reinf. Concrete 3/23/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/27/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/28/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/29/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 3/29/2018 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 3/30/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 3/30/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/4/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/5/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/6/2018 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/10/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/10/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/11/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/12/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/13/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/19/2018 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/24/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 5/25/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/29/2018 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 6/6/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 6/22/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/28/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/28/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/29/2018 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/3/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 8/8/2018 Partial Approval JEFF BYTHEWAY
Green Building Rough 8/13/2018 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 8/13/2018 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 8/16/2018 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 8/27/2018 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/31/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/12/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/18/2018 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/18/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/19/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/20/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/21/2018 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 1/9/2019 Partial Inspection JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 7/25/2019 Partial Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 7/25/2019 Partial Inspection JEFF BYTHEWAY
Masonry Wall/Backfill 7/25/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 7/26/2019 Partial Approval JEFF BYTHEWAY
Pre-Inspection 8/9/2019 Approved JEFF BYTHEWAY
Drywall Nailing 1/10/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 1/10/2022 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 2/25/2022 Partial Approval DAVID BURKHEAD
Posting Pre-Inspection 8/7/2025 Not Ready for Inspection DAVID BURKHEAD