10341 S KALMIA ST 90002
Certificate Information: 10341 S KALMIA ST 90002
- Application / Permit
- 15014-10000-03498
- Plan Check / Job No.
- B15LA10636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY STUDY ROOM & GARAGE ADDITION TO EXISTING 1-STORY SFD REMODEL EXISITNG ALL PER W.F.P.P.
- Permit Issued
- Issued on 8/10/2015
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2015 | ALYSSA N NARCISO |
| Plan Check Approved | 7/31/2015 | MANUEL MONTUFAR |
| Issued | 8/10/2015 | LADBS |
| CofO in Progress | 3/9/2018 | JOHN KLARIN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2015 | KARAN PATEL |
| Roof/Waste drainage to street | Cleared | 7/31/2015 | KARAN PATEL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2016 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 8/4/2017 | Not Ready for Inspection | MARK HATFIELD |
| PLUMBING-Rough | 8/4/2017 | Not Ready for Inspection | MARK HATFIELD |
| PLUMBING-Rough | 8/8/2017 | Partial Approval | MARK HATFIELD |
| Footing/Foundation/Slab | 8/10/2017 | Approved | MARK HATFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2017 | Approved | MARK HATFIELD |
| Green Building Rough | 10/13/2017 | Not Ready for Inspection | MARK HATFIELD |
| BUILDING-Rough-Frame | 12/4/2017 | Corrections Issued | MARK HATFIELD |
| ELECTRICAL-Rough | 12/4/2017 | Approved | MARK HATFIELD |
| Green Building Rough | 12/4/2017 | Approved | MARK HATFIELD |
| PLUMBING-Rough | 12/4/2017 | Corrections Issued | MARK HATFIELD |
| BUILDING-Rough-Frame | 12/18/2017 | Approved | MARK HATFIELD |
| Insulation | 12/18/2017 | Approved | MARK HATFIELD |
| PLUMBING-Rough | 12/18/2017 | Approved | MARK HATFIELD |
| Drywall Nailing | 12/21/2017 | Not Ready for Inspection | MARK HATFIELD |
| Drywall Nailing | 12/22/2017 | Approved | MARK HATFIELD |
| Interior/Exterior Lathing | 12/28/2017 | Approved | MARK HATFIELD |
| Final | 3/2/2018 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 3/2/2018 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2018 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 3/2/2018 | Approved | JOHN KLARIN |