112 N JUNE ST 90004

Certificate Information: 112 N JUNE ST 90004

Application / Permit
15014-10000-01724
Plan Check / Job No.
B15LA05592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR AND 2ND FLOOR ADDITIONS TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/13/2016
Issuing Office
Metro
Current Status
CofO Issued on 12/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2015 APPLICANT
Assigned to Plan Check Engineer 5/14/2015 RICARDO SUPAN
Corrections Issued 6/9/2015 RICARDO SUPAN
Quality Review Completed 6/9/2015 BILL STUTSMAN
Building Plans Picked Up 6/9/2015 APPLICANT
Green Plans Picked Up 6/9/2015 APPLICANT
Applicant returned to address corrections 4/27/2016 RICARDO SUPAN
Applicant returned to address corrections 10/17/2016 RICARDO SUPAN
Plan Check Approved 12/13/2016 RICARDO SUPAN
Issued 12/13/2016 LADBS
CofO in Progress 12/1/2020 JOSEPH MCGARRY
Permit Finaled 12/24/2020 DEROLD HAUFF
CofO Issued 12/24/2020 DEROLD HAUFF
Permit Finaled 12/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 9/14/2016 DENNIS CHEW
Eng Process Fee Ord 176,300 Cleared 11/3/2016 ERIK MUNOZ
Miscellaneous Cleared 11/9/2016 DENNIS CHEW
Miscellaneous Cleared 11/9/2016 DENNIS CHEW
ZA Case Cleared 11/9/2016 DENNIS CHEW
Low Impact Development Cleared 11/15/2016 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/15/2016 ERIK MUNOZ
Stormwater Pollution Mitigatn Cleared 11/15/2016 MARTIN FRAGOSO
Green Code Cleared 11/18/2016 RICHARD DOCKUS
CPC Cleared 12/12/2016 KIMBERLY HENRY
HPOZ Cleared 12/12/2016 KIMBERLY HENRY
Miscellaneous Cleared 12/12/2016 KIMBERLY HENRY

Contact Information

Architect Spiegel, Todd Brian; Lic. No.: C30855 4531 BELHAM COURT      WESTLAKE VILLAGE, CA 91361
Contractor Consert Inc; Lic. No.: 940977-B 31822 VILLAGE CENTER ROAD #202      WESTLAKE VILLAGE, CA 91361
Engineer Greco, Adam Matthew; Lic. No.: S4077 1470 WESTERLY TERRACE      LOS ANGELES, CA 90026

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2017 Not Ready for Inspection DANNY TOLENTINO
METHANE-Barrier 12/12/2017 Not Ready for Inspection DANNY TOLENTINO
METHANE-Subgrade 12/12/2017 Not Ready for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 6/7/2018 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 6/29/2018 No Access for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 7/17/2018 Corrections Issued DANNY TOLENTINO
Footing/Foundation/Slab 7/17/2018 Corrections Issued DANNY TOLENTINO
METHANE-Barrier 7/17/2018 Not Ready for Inspection DANNY TOLENTINO
METHANE-Subgrade 7/17/2018 Not Ready for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 7/25/2018 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 7/25/2018 Partial Approval DANNY TOLENTINO
METHANE-Barrier 7/25/2018 Partial Inspection DANNY TOLENTINO
METHANE-Subgrade 7/25/2018 Partial Inspection DANNY TOLENTINO
Piling/Pier/Caisson 7/25/2018 Not Ready for Inspection DANNY TOLENTINO
Pre-Inspection 8/8/2018 Partial Inspection DANNY TOLENTINO
Pre-Inspection 8/13/2018 Not Ready for Inspection BRAD BESCOS
BUILDING-Rough-Frame 8/28/2018 Partial Inspection DANNY TOLENTINO
Green Building Rough 8/28/2018 Not Ready for Inspection DANNY TOLENTINO
METHANE-Rough 8/28/2018 Partial Inspection DANNY TOLENTINO
Deputy Reinf. Concrete 8/29/2018 Conditional Approval DANNY TOLENTINO
METHANE-Subgrade 9/20/2018 Partial Approval BRAD BESCOS
METHANE-Barrier 9/27/2018 Corrections Issued DANNY TOLENTINO
METHANE-Rough 9/27/2018 Not Ready for Inspection DANNY TOLENTINO
PLUMBING-Rough 9/27/2018 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 10/1/2018 Partial Approval DANNY TOLENTINO
METHANE-Subgrade 10/1/2018 Approved DANNY TOLENTINO
Special/Order Compliance 10/9/2018 Partial Inspection DANNY TOLENTINO
BUILDING-Rough-Frame 10/16/2018 Partial Approval DANNY TOLENTINO
Green Building Rough 10/16/2018 Not Ready for Inspection DANNY TOLENTINO
METHANE-Rough 10/16/2018 Not Ready for Inspection DANNY TOLENTINO
Special/Order Compliance 10/16/2018 Approved DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Partial Approval ROBERT MINASSIANS
PLUMBING-Rough 12/5/2018 Partial Inspection DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Inspection DANNY TOLENTINO
PLUMBING-Rough 1/17/2019 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 2/21/2019 Partial Approval DANIEL GONZALEZ
METHANE-Barrier 2/21/2019 Partial Inspection DANIEL GONZALEZ
PLUMBING-Rough 5/20/2019 Partial Approval DANIEL GONZALEZ
Special/Order Compliance 5/21/2019 Corrections Issued DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 6/14/2019 Not Ready for Inspection DANIEL GONZALEZ
Gas Test 6/14/2019 Not Ready for Inspection DANIEL GONZALEZ
Wood Frame 6/14/2019 Not Ready for Inspection DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 6/28/2019 Partial Approval DANIEL GONZALEZ
Gas Test 6/28/2019 Not Ready for Inspection DANIEL GONZALEZ
Gas Test 7/1/2019 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 7/9/2019 Partial Approval DANIEL GONZALEZ
BUILDING-Rough-Frame 7/12/2019 Partial Approval DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2019 Partial Approval DANIEL GONZALEZ
Green Building Rough 7/12/2019 Not Ready for Inspection DANIEL GONZALEZ
METHANE-Rough 7/12/2019 Not Ready for Inspection DANIEL GONZALEZ
ELECTRICAL-Rough 7/18/2019 Partial Approval DANIEL GONZALEZ
HVAC-Rough 7/18/2019 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 7/18/2019 Partial Approval DANIEL GONZALEZ
ELECTRICAL-Rough 7/25/2019 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 8/2/2019 Conditional Approval DANIEL GONZALEZ
Green Building Rough 8/2/2019 Approved DANIEL GONZALEZ
Rough-Elec/Plmb/HVAC 8/2/2019 Approved DANIEL GONZALEZ
Drywall Nailing 8/7/2019 Partial Approval DANIEL GONZALEZ
Shower Pan 9/16/2019 Partial Approval DANIEL GONZALEZ
Drywall Nailing 9/27/2019 Approved PIERRE VEGA
Shower Pan 9/27/2019 Approved PIERRE VEGA
BUILDING-Rough-Frame 10/15/2019 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 11/19/2019 Partial Approval DANIEL GONZALEZ
Shower Pan 12/13/2019 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 4/2/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 6/30/2020 Approved ARTHUR SARGSYAN
Final 10/19/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 10/19/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 10/19/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 11/5/2020 Not Ready for Inspection DONALD CRICHLOW
Green Building Final 11/5/2020 Corrections Issued DONALD CRICHLOW
Smoke Detectors 11/5/2020 Not Ready for Inspection DONALD CRICHLOW
Final 11/12/2020 Corrections Issued DONALD CRICHLOW
Green Building Final 11/12/2020 Not Ready for Inspection DONALD CRICHLOW
Smoke Detectors 11/12/2020 Not Ready for Inspection DONALD CRICHLOW
Final 11/19/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 11/19/2020 Approved JOSEPH MCGARRY
Smoke Detectors 11/19/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 11/30/2020 OK to Issue CofO JOSEPH MCGARRY
Smoke Detectors 11/30/2020 Approved JOSEPH MCGARRY
Special/Order Compliance 12/4/2020 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 12/18/2020 Approved JOSEPH MCGARRY