276 S WINDSOR BLVD 90004

Certificate Information: 276 S WINDSOR BLVD 90004

Application / Permit
15014-10000-00342
Plan Check / Job No.
B15LA01175
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1379 SQFT. 2-STORY ADDITION, COVERED PATIO (466 SQFT.) AND ATTACHED DECK TO (E) 2-STORY SINGLE FAMILY DWELLING. RELATED ELEC/PLUMBING/HVAC.
Permit Issued
Issued on 12/3/2015
Issuing Office
Metro
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2015 APPLICANT
Green Plans Picked Up 2/11/2015 APPLICANT
Assigned to Plan Check Engineer 2/13/2015 EDUARDO RODRIGUEZ
Corrections Issued 2/20/2015 EDUARDO RODRIGUEZ
Quality Review Completed 3/2/2015 CHARLES CHANG
Applicant returned to address corrections 7/22/2015 EDUARDO RODRIGUEZ
Applicant returned to address corrections 11/24/2015 EDUARDO RODRIGUEZ
Plan Check Approved 12/3/2015 EDUARDO RODRIGUEZ
Issued 12/3/2015 LADBS
CofO in Progress 4/26/2024 JOAQUIN GREENOUGH
Permit Finaled 4/29/2024 DEROLD HAUFF
CofO Issued 4/29/2024 DEROLD HAUFF
Permit Finaled 4/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/2/2015 KARAN PATEL
Permit Cleared 7/2/2015 KARAN PATEL
HPOZ Cleared 7/8/2015 TIMOTHY ROSENSTEIN
Green Code Cleared 10/26/2015 RUSSELL KELLY
Low Impact Development Cleared 11/30/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/3/2015 ADRIAN HERNANDEZ
Sewer availability Cleared 12/3/2015 ADRIAN HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2016 Not Ready for Inspection JOEL WILLIAMS
METHANE-Barrier 11/2/2016 Approved JOEL WILLIAMS
METHANE-Subgrade 11/2/2016 Approved JOEL WILLIAMS
Pre-Inspection 11/2/2016 Approved JOEL WILLIAMS
Deputy Drilled-In Anchors 11/10/2016 No Access for Inspection JOEL WILLIAMS
Footing/Foundation/Slab 11/23/2016 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 4/26/2017 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/12/2017 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/12/2017 Partial Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/23/2017 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/15/2017 Approved JOSEPH MCGARRY
Special/Order Compliance 6/19/2017 Partial Approval JOEL WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 7/19/2017 Partial Approval JOEL WILLIAMS
ELECTRICAL-Rough 2/22/2018 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/22/2018 Corrections Issued JOSEPH MCGARRY
Green Building Rough 2/22/2018 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Rough 2/22/2018 Approved JOSEPH MCGARRY
PLUMBING-Rough 2/22/2018 Corrections Issued JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 3/1/2018 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/6/2018 Partial Approval JOEL WILLIAMS
Rough-Elec/Plmb/HVAC 3/6/2018 Not Ready for Inspection JOEL WILLIAMS
BUILDING-Rough-Frame 5/8/2018 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 5/8/2018 Partial Approval JOSEPH MCGARRY
Green Building Rough 5/8/2018 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 5/8/2018 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 5/9/2018 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 6/28/2018 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 6/28/2018 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 8/7/2018 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 8/7/2018 Conditional Approval JOSEPH MCGARRY
Insulation 8/7/2018 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 8/7/2018 Partial Approval JOSEPH MCGARRY
Pre-Inspection 8/30/2018 Partial Approval JOSEPH MCGARRY
Pre-Inspection 10/2/2018 Approved JOSEPH MCGARRY
Special/Order Compliance 10/9/2018 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/15/2018 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 10/15/2018 Corrections Issued JOSEPH MCGARRY
HVAC-Rough 10/15/2018 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/15/2018 Approved JOSEPH MCGARRY
Shower Pan 10/15/2018 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 10/18/2018 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/22/2018 SGSOV Not Ready JOSEPH MCGARRY
BUILDING-Rough-Frame 10/26/2018 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 10/26/2018 Partial Approval JOSEPH MCGARRY
Green Building Rough 10/26/2018 Approved JOSEPH MCGARRY
Insulation 10/26/2018 Approved JOSEPH MCGARRY
Shower Pan 10/26/2018 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 11/7/2018 Partial Approval JOSEPH MCGARRY
Drywall Nailing 1/25/2019 Corrections Issued DANIEL GONZALEZ
Insulation 1/29/2019 Corrections Issued ROBERT MINASSIANS
Drywall Nailing 2/5/2019 No Access for Inspection LUIS BARRALES
Insulation 2/7/2019 Partial Approval LUIS BARRALES
Drywall Nailing 2/26/2019 Not Ready for Inspection PIERRE VEGA
Insulation 2/26/2019 Not Ready for Inspection PIERRE VEGA
Shower Pan 2/26/2019 Not Ready for Inspection PIERRE VEGA
Drywall Nailing 3/4/2019 Approved LUIS BARRALES
Shower Pan 3/4/2019 Approved LUIS BARRALES
Insulation 3/13/2019 No Access for Inspection LUIS BARRALES
Final 3/18/2019 Not Ready for Inspection LUIS BARRALES
Green Building Final 3/18/2019 Not Ready for Inspection LUIS BARRALES
SGSOV-Seismic Gas S/O Valve 3/18/2019 SGSOV Not Ready LUIS BARRALES
Smoke Detectors 3/18/2019 Not Ready for Inspection LUIS BARRALES
Insulation 3/20/2019 Approved LUIS BARRALES
Interior/Exterior Lathing 3/21/2019 Partial Approval LUIS BARRALES
Interior/Exterior Lathing 3/27/2019 Partial Approval LUIS BARRALES
Final 1/13/2020 Not Ready for Inspection LUIS BARRALES
Green Building Final 1/13/2020 Not Ready for Inspection LUIS BARRALES
SGSOV-Seismic Gas S/O Valve 1/13/2020 SGSOV Not Ready LUIS BARRALES
Smoke Detectors 1/13/2020 Not Ready for Inspection LUIS BARRALES
Special/Order Compliance 11/20/2020 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 11/30/2020 No Access for Inspection JOSEPH MCGARRY
Special/Order Compliance 12/9/2020 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 7/18/2022 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 8/19/2022 No Access for Inspection JOSEPH MCGARRY
Special/Order Compliance 12/29/2022 Corrections Issued JEFFREY MEAD
Special/Order Compliance 1/12/2023 Corrections Issued JEFFREY MEAD
Special/Order Compliance 3/8/2023 Corrections Issued JEFFREY MEAD
Special/Order Compliance 3/24/2023 Corrections Issued JEFFREY MEAD
Final 10/12/2023 Corrections Issued JEFFREY MEAD
Green Building Final 10/12/2023 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 10/12/2023 Not Ready for Inspection JEFFREY MEAD
Final 11/28/2023 Not Ready for Inspection JEFFREY MEAD
Green Building Final 11/28/2023 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 11/28/2023 Not Ready for Inspection JEFFREY MEAD
Final 4/25/2024 OK to Issue CofO JOAQUIN GREENOUGH
Green Building Final 4/25/2024 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 4/25/2024 Approved JOAQUIN GREENOUGH