10535 W VESTONE WAY 90077

Certificate Information: 10535 W VESTONE WAY 90077

Application / Permit
15010-40000-04523
Plan Check / Job No.
B15SP00823
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New accessory living quarter
Permit Issued
Issued on 3/31/2016
Issuing Office
Metro
Current Status
Issued on 3/31/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2015 APPLICANT
Assigned to Plan Check Engineer 12/24/2015 YAQUB MIRZA
Corrections Issued 12/26/2015 YAQUB MIRZA
Quality Review Completed 12/30/2015 CHIHARU SUZUKI
Building Plans Picked Up 1/4/2016 APPLICANT
Applicant returned to address corrections 1/19/2016 YAQUB MIRZA
Applicant returned to address corrections 1/26/2016 YAQUB MIRZA
Applicant returned to address corrections 1/27/2016 YAQUB MIRZA
Plan Check Approved 3/30/2016 YAQUB MIRZA
Issued 3/31/2016 LADBS
Green Plans Picked Up 9/2/2016 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/13/2016 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 1/13/2016 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 1/13/2016 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 1/13/2016 ARMENIA HERNANDEZ
Low Impact Development Cleared 1/13/2016 IDA MEISAMI-FARD
Permit Cleared 1/13/2016 ARMENIA HERNANDEZ
Roof/Waste drainage to street Cleared 1/13/2016 ARMENIA HERNANDEZ
Address approval Cleared 1/14/2016 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 1/14/2016 PHILLIP WILSON
Sewer availability Cleared 1/14/2016 PHILLIP WILSON
Street width determination Cleared 1/14/2016 PHILLIP WILSON
Hydrant and Access approval Cleared 1/21/2016 ROBERT DUFF
BHO/Hillside ordinance Cleared 1/22/2016 PHONG NGUYEN
Private street Cleared 1/22/2016 DANIEL SKOLNICK
Green Code Cleared 1/26/2016 JOHN KLARIN
Grading Pre-Inspection Cleared 3/30/2016 YAQUB MIRZA

Contact Information

Architect James, William Douglas; Lic. No.: C28863 415 W NINTH STREET      SAN PEDRO, CA 90731
Contractor Owner-Builder       ,
Engineer Khazra, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/5/2016 Corrections Issued ANTHONY ANDERSON
Deputy Reinf. Concrete 4/7/2016 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 4/7/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 4/22/2016 Partial Approval DANIEL ORRANTE
Deputy Steel/Welding 5/5/2016 Approved ANTHONY ANDERSON
Deputy Steel/Welding 5/5/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 5/9/2016 Conditional Approval ANTHONY ANDERSON
Shower Pan 1/10/2017 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/8/2017 Partial Approval ANTHONY ANDERSON
Green Building Rough 2/8/2017 Not Ready for Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 2/8/2017 Not Ready for Inspection ANTHONY ANDERSON
Insulation 4/13/2017 Not Ready for Inspection DANIEL ORRANTE
Interior/Exterior Lathing 4/13/2017 Not Ready for Inspection DANIEL ORRANTE
Insulation 4/18/2017 Partial Inspection ANTHONY ANDERSON
Interior/Exterior Lathing 4/18/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Rough 4/28/2017 Partial Inspection ANTHONY ANDERSON
HVAC-Rough 4/28/2017 Approved ANTHONY ANDERSON
PLUMBING-Rough 4/28/2017 Approved ANTHONY ANDERSON
ELECTRICAL-Rough 5/3/2017 Partial Approval ANTHONY ANDERSON
HVAC-Rough 5/3/2017 Approved ANTHONY ANDERSON
PLUMBING-Rough 5/3/2017 Approved ANTHONY ANDERSON
Rough-Elec/Plmb/HVAC 5/3/2017 Approved ANTHONY ANDERSON
Wood Frame 5/4/2017 Corrections Issued ANTHONY ANDERSON
ELECTRICAL-Rough 5/18/2017 Approved ANTHONY ANDERSON
HVAC-Rough 5/18/2017 Approved ANTHONY ANDERSON
Insulation 5/18/2017 Partial Inspection ANTHONY ANDERSON
Interior/Exterior Lathing 5/18/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 5/18/2017 Approved ANTHONY ANDERSON
Rough-Elec/Plmb/HVAC 5/18/2017 Approved ANTHONY ANDERSON
Drywall Nailing 6/1/2017 Approved ANTHONY ANDERSON
Special/Order Compliance 8/19/2017 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Final 12/28/2017 Corrections Issued ANTHONY ANDERSON
Footing/Foundation/Slab 12/28/2017 Partial Inspection ANTHONY ANDERSON
Green Building Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Green Building Rough 12/28/2017 Partial Inspection ANTHONY ANDERSON
HVAC-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
PLUMBING-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
SGSOV-Seismic Gas S/O Valve 12/28/2017 SGSOV Not Ready ANTHONY ANDERSON
Service/Power Release 12/28/2017 Partial Inspection ANTHONY ANDERSON
Smoke Detectors 12/28/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 12/28/2017 Partial Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Final 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Final 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 8/14/2018 Partial Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/14/2018 SGSOV Not Ready CHRISTOPHER WILSON
Service/Power Release 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 8/14/2018 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/14/2018 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 8/29/2018 Approved CHRISTOPHER WILSON
Green Building Rough 8/29/2018 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Final 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Final 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 3/11/2019 Corrections Issued MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/11/2019 SGSOV Not Ready CHRISTOPHER WILSON
Service/Power Release 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 3/11/2019 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/10/2020 Not Ready for Inspection MATT KELLERMAN
Final 3/10/2020 Corrections Issued MATT KELLERMAN
Green Building Final 3/10/2020 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 3/10/2020 SGSOV Approved MATT KELLERMAN
Service/Power Release 3/10/2020 Not Required MATT KELLERMAN
Smoke Detectors 3/10/2020 Corrections Issued MATT KELLERMAN
Verify Sprinkler Sign Off 3/10/2020 Approved MATT KELLERMAN
BUILDING-Rough-Frame 3/25/2020 Partial Inspection CHRISTOPHER WILSON
Final 3/25/2020 Partial Inspection CHRISTOPHER WILSON
Green Building Final 3/25/2020 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 3/25/2020 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/5/2021 Approved CHRISTOPHER WILSON
Final 1/5/2021 Corrections Issued CHRISTOPHER WILSON
Green Building Final 1/5/2021 Not Ready for Inspection CHRISTOPHER WILSON
Smoke Detectors 1/5/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 10/22/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 6/27/2022 Corrections Issued CHRISTOPHER WILSON