865 N STRADELLA ROAD 90077

Certificate Information: 865 N STRADELLA ROAD 90077

Application / Permit
15010-30000-04704
Plan Check / Job No.
B15WL06637
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD.
Permit Issued
Issued on 5/11/2017
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2015 APPLICANT
Assigned to Plan Check Engineer 1/7/2016 VLADIMIR ARUTYUNYAN
Corrections Issued 1/11/2016 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 1/13/2016 APPLICANT
Quality Review Completed 1/15/2016 DOUGLAS NAKATANI
Building Plans Picked Up 1/15/2016 APPLICANT
Plan Check Approved 4/28/2017 VLADIMIR ARUTYUNYAN
Issued 5/11/2017 LADBS
CofO in Progress 3/27/2021 CHRISTOPHER WILSON
CofO Issued-Status Void 4/22/2021 VINCENT COTTON
Permit Finaled-Status Void 4/22/2021 VINCENT COTTON
Re-Activate Permit 7/2/2021 VINCENT COTTON
CofO Corrected 7/20/2021 VINCENT COTTON
Permit Finaled 7/20/2021 VINCENT COTTON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/12/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 7/12/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 7/12/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 7/12/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 7/12/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 7/12/2016 ROBERT DUFF
Permit Cleared 7/12/2016 RAVIL MANAPOV
Sewer availability Cleared 7/12/2016 RAVIL MANAPOV
Low Impact Development Cleared 11/3/2016 SAM NAVID
Green Code Cleared 12/15/2016 BRYAN MEYER
Roof/Waste drainage to street Cleared 12/15/2016 RICHARD SOUTHERLAND
ZA Case Cleared 12/16/2016 CASSANDRA ZWEEP
Excavation more than 5-ft deep Cleared 12/20/2016 CALOSHA APPROVED

Contact Information

Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/25/2018 Approved ANTHONY ANDERSON
Piling/Pier/Caisson 2/14/2018 Corrections Issued ANTHONY ANDERSON
Piling/Pier/Caisson 2/21/2018 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 2/27/2018 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 3/1/2018 Approved ANTHONY ANDERSON
Reinforced Concrete Frame 6/13/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/15/2018 Conditional Approval JOEL LAUNCHBAUGH
Piling/Pier/Caisson 8/9/2018 Partial Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 8/30/2018 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 9/12/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/14/2018 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 9/26/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/27/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/27/2018 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/11/2018 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/11/2018 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/25/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/26/2018 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 11/28/2018 Partial Inspection JOEL LAUNCHBAUGH
Footing/Foundation/Slab 12/6/2018 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 12/12/2018 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 12/12/2018 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 12/14/2018 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 12/27/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/28/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/11/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 1/30/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 2/1/2019 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 2/11/2019 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/12/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/19/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/22/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/22/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/13/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/14/2019 Approved ROBERT SHELLY
ELECTRICAL-Rough 3/18/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/20/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 3/20/2019 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/8/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Other (see comments) 4/10/2019 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 4/11/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/18/2019 Conditional Approval MICHAEL TEMPLE
Deputy Reinf. Concrete 4/18/2019 Conditional Approval MICHAEL TEMPLE
Reinforced Concrete Frame 4/18/2019 Partial Approval MICHAEL TEMPLE
Reinforced Masonry Frame 4/18/2019 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 4/23/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 4/23/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 4/23/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/23/2019 Partial Inspection CHRISTOPHER WILSON
Wood Frame 4/23/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/25/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 4/26/2019 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 4/29/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 4/29/2019 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/3/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 5/3/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/3/2019 Partial Inspection CHRISTOPHER WILSON
Wood Frame 5/3/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/6/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 5/6/2019 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/8/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/8/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/8/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/8/2019 Partial Inspection CHRISTOPHER WILSON
Sewer 5/8/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/14/2019 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 5/23/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/31/2019 Corrections Issued MICHAEL TEMPLE
Sewer 5/31/2019 Not Ready for Inspection MICHAEL TEMPLE
Sewer 6/3/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/5/2019 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/6/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/11/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 6/14/2019 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/21/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 6/21/2019 Partial Approval CHRISTOPHER WILSON
Deputy Pre-Stress Concrete 6/24/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/24/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/25/2019 Conditional Approval CARLOS MATAMOROS
Deputy Pre-Stress Concrete 6/26/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/26/2019 Partial Approval CHRISTOPHER WILSON
Gas Test 7/10/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/10/2019 Approved CHRISTOPHER WILSON
Deputy Shotcrete 7/16/2019 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 7/17/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Masonry Frame 7/17/2019 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/22/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/23/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/23/2019 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/26/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/26/2019 Partial Approval CHRISTOPHER WILSON
Sewer 8/2/2019 Approved CHRISTOPHER WILSON
Sewer 8/5/2019 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 8/12/2019 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 8/22/2019 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 8/22/2019 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 8/23/2019 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 8/23/2019 Approved MATTHEW NUCKOLLS
HVAC-Rough 9/4/2019 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 9/4/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/4/2019 Partial Inspection CHRISTOPHER WILSON
Wood Frame 9/4/2019 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/11/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Shotcrete 9/11/2019 Partial Approval CHRISTOPHER WILSON
Insulation 9/11/2019 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 9/16/2019 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 9/23/2019 Conditional Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 9/23/2019 Partial Approval CARLOS MATAMOROS
Insulation 9/25/2019 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 9/25/2019 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/28/2019 Partial Approval ANTHONY MCDOWALL
Green Building Rough 10/28/2019 Partial Approval ANTHONY MCDOWALL
Shower Pan 11/1/2019 Corrections Issued CHRISTOPHER WILSON
Shower Pan 11/5/2019 Partial Approval MATT KELLERMAN
Underground Mechanical 11/25/2019 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/26/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 11/26/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/16/2019 Partial Approval MATT KELLERMAN
Drywall Nailing 1/7/2020 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/7/2020 Approved CHRISTOPHER WILSON
Deputy Wood Construction 1/21/2020 Conditional Approval CHRISTOPHER WILSON
Drywall Nailing 1/29/2020 Partial Approval MATT KELLERMAN
Service/Power Release 5/13/2020 Partial Inspection ANTHONY MCDOWALL
Service/Power Release 6/29/2020 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 6/30/2020 Approved CHRISTOPHER WILSON
Gas Test 7/8/2020 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/26/2020 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/22/2020 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 10/20/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 10/28/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 11/2/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 11/5/2020 Approved CHRISTOPHER WILSON
PLUMBING-Final 11/5/2020 Approved CHRISTOPHER WILSON
HVAC-Final 12/2/2020 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/23/2021 Approved CHRISTOPHER WILSON
Drywall Nailing 2/23/2021 Approved CHRISTOPHER WILSON
Final 2/23/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 2/23/2021 Approved CHRISTOPHER WILSON
Green Building Final 2/23/2021 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved MATT KELLERMAN
Smoke Detectors 2/23/2021 Approved CHRISTOPHER WILSON
Structural Steel Frame 2/23/2021 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/23/2021 Approved CHRISTOPHER WILSON
Final 3/2/2021 Corrections Issued CHRISTOPHER WILSON
Final 3/12/2021 Conditional Approval CHRISTOPHER WILSON