240 N ROCKINGHAM AVE 90049

Certificate Information: 240 N ROCKINGHAM AVE 90049

Application / Permit
15010-30000-04622
Plan Check / Job No.
B15WL06569
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 story s.f.d. w/ basement and att. garage
Permit Issued
Issued on 10/18/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2015 APPLICANT
Assigned to Plan Check Engineer 12/30/2015 VLADIMIR ARUTYUNYAN
Corrections Issued 1/5/2016 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/12/2016 DOUGLAS NAKATANI
Green Plans Picked Up 3/10/2016 APPLICANT
Plan Check Approved 10/4/2016 VLADIMIR ARUTYUNYAN
Issued 10/18/2016 LADBS
Building Plans Picked Up 5/22/2020 APPLICANT
CofO in Progress 10/18/2022 JUAN VALENZUELA
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/13/2016 BRIAN KELLY
Sewer availability Cleared 6/13/2016 BRIAN KELLY
Hydrant and Access approval Cleared 6/14/2016 ROBERT DUFF
Permit Cleared 7/20/2016 HISASHI KOBAYAKAWA
Green Code Cleared 7/28/2016 RICHARD GARCIA
Low Impact Development Cleared 8/19/2016 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 9/6/2016 OSCAR GUTIERREZ
Excavation more than 5-ft deep Cleared 10/4/2016 CALOSHA APPROVED

Contact Information

Contractor Dover Hills Construction; Lic. No.: 629105-B P O BOX 16561      BEVERLY HILLS, CA 902092561
Engineer Dejban, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/5/2017 Partial Approval JOHN LUMB
Pre-Inspection 5/3/2017 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/25/2017 Partial Approval JOHN LUMB
Masonry Wall/Backfill 6/12/2017 Partial Approval VINCENT SCIPIONI
Pre-Inspection 6/12/2017 Corrections Issued VINCENT SCIPIONI
Pre-Inspection 6/19/2017 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 6/29/2017 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 7/5/2017 Partial Approval JOHN LUMB
Footing/Foundation/Slab 7/5/2017 Partial Approval JOHN LUMB
Footing/Foundation/Slab 7/14/2017 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 7/27/2017 Partial Approval JOHN LUMB
Deputy Shotcrete 8/2/2017 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 8/3/2017 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 8/4/2017 Partial Approval JOHN LUMB
Deputy Shotcrete 8/4/2017 Partial Approval JOHN LUMB
Deputy Shotcrete 8/8/2017 No Access for Inspection VINCENT SCIPIONI
Footing/Foundation/Slab 8/11/2017 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 8/16/2017 Partial Approval JOHN LUMB
BUILDING-Rough-Frame 9/6/2017 Not Ready for Inspection DANIEL ORRANTE
Green Building Rough 9/6/2017 Not Ready for Inspection DANIEL ORRANTE
Verify Sprinkler Sign Off 9/6/2017 Not Ready for Inspection DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 9/19/2017 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 9/29/2017 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 10/10/2017 Partial Approval JOHN LUMB
Deputy Shotcrete 10/16/2017 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 1/29/2018 Partial Approval JOHN LUMB
Footing/Foundation/Slab 1/29/2018 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 2/1/2018 Approved JOHN LUMB
Deputy Steel/Welding 2/28/2018 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/18/2018 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 8/31/2018 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 9/25/2018 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 9/25/2018 Partial Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 10/1/2018 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 11/13/2018 No Access for Inspection KENNETH NAGLE
Green Building Rough 11/13/2018 No Access for Inspection KENNETH NAGLE
Verify Sprinkler Sign Off 11/13/2018 No Access for Inspection KENNETH NAGLE
Pre-Inspection 11/15/2018 Partial Inspection KENNETH NAGLE
Deputy Steel/Welding 11/20/2018 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 11/27/2018 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 12/12/2018 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 2/14/2019 Partial Approval KENNETH NAGLE
HVAC-Rough 4/1/2019 Partial Inspection MICHAEL TEMPLE
Underground Mechanical 5/1/2019 Partial Inspection RICHARD STEINBACH
ELECTRICAL-Rough 7/5/2019 Partial Approval TIM CHRISTENSEN
PLUMBING-Rough 7/18/2019 Corrections Issued TIM CHRISTENSEN
PLUMBING-Rough 8/12/2019 Partial Approval TIM CHRISTENSEN
HVAC-Rough 8/20/2019 Corrections Issued TIM CHRISTENSEN
PLUMBING-Rough 8/20/2019 Approved TIM CHRISTENSEN
BUILDING-Rough-Frame 8/29/2019 Corrections Issued TIM CHRISTENSEN
Green Building Rough 8/29/2019 Partial Approval TIM CHRISTENSEN
Verify Sprinkler Sign Off 8/29/2019 Not Ready for Inspection TIM CHRISTENSEN
Insulation 9/23/2019 Partial Approval TIM CHRISTENSEN
BUILDING-Rough-Frame 10/23/2019 Partial Approval TIM CHRISTENSEN
Green Building Rough 10/23/2019 Partial Approval TIM CHRISTENSEN
HVAC-Rough 10/23/2019 Approved TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/4/2019 Corrections Issued TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/7/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 11/19/2019 Approved TIM CHRISTENSEN
Insulation 11/19/2019 Partial Approval TIM CHRISTENSEN
Drywall Nailing 1/9/2020 Partial Approval TIM CHRISTENSEN
ELECTRICAL-Rough 1/9/2020 Approved TIM CHRISTENSEN
Green Building Rough 1/9/2020 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 1/9/2020 Partial Approval TIM CHRISTENSEN
Verify Sprinkler Sign Off 1/9/2020 Not Ready for Inspection TIM CHRISTENSEN
BUILDING-Rough-Frame 3/3/2020 Approved TIM CHRISTENSEN
Insulation 3/3/2020 Approved TIM CHRISTENSEN
Verify Sprinkler Sign Off 3/3/2020 Approved TIM CHRISTENSEN
Drywall Nailing 3/17/2020 Partial Approval TIM CHRISTENSEN
Shower Pan 4/6/2020 Not Ready for Inspection TIM CHRISTENSEN
Shower Pan 4/7/2020 Partial Approval TIM CHRISTENSEN
Drywall Nailing 4/14/2020 Partial Approval TIM CHRISTENSEN
Interior/Exterior Lathing 4/27/2020 Partial Approval TIM CHRISTENSEN
Interior/Exterior Lathing 6/9/2020 Partial Approval TIM CHRISTENSEN
Interior/Exterior Lathing 7/7/2020 Approved TIM CHRISTENSEN
Pre-Inspection 8/17/2020 Approved TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/20/2020 Not Ready for Inspection TIM CHRISTENSEN
ELECTRICAL-Rough 10/29/2020 Conditional Approval TIM CHRISTENSEN
Drywall Nailing 11/5/2020 Partial Approval PIERRE VEGA
Shower Pan 12/10/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 1/14/2021 Approved PIERRE VEGA
Sewer 3/22/2021 Partial Approval JUAN VALENZUELA
Sewer 3/30/2021 Partial Approval JUAN VALENZUELA
Sewer 4/15/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 5/20/2021 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 5/27/2021 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 5/28/2021 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 5/28/2021 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 6/1/2021 Partial Approval JUAN VALENZUELA
Gas Test 6/7/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 6/15/2021 Partial Approval JUAN VALENZUELA
Sewer 7/12/2021 Approved PIERRE VEGA
Pre-Inspection 10/5/2021 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 12/8/2021 Not Ready for Inspection JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 1/13/2022 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 1/13/2022 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Final 1/21/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 1/25/2022 Partial Approval JUAN VALENZUELA
Pre-Inspection 2/11/2022 Partial Inspection JUAN VALENZUELA
Pre-Inspection 4/7/2022 Partial Inspection JUAN VALENZUELA
Service/Power Release 4/18/2022 Approved KENNETH NAGLE
Deputy Steel/Welding 4/27/2022 No Access for Inspection KENNETH NAGLE
Service/Power Release 4/28/2022 Approved KENNETH NAGLE
HVAC-Final 7/6/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 7/14/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 7/19/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 7/22/2022 Approved JUAN VALENZUELA
PLUMBING-Final 7/22/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 7/26/2022 Approved JUAN VALENZUELA
PLUMBING-Final 7/26/2022 Approved JUAN VALENZUELA
Drywall Nailing 10/4/2022 Approved JUAN VALENZUELA
Final 10/4/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/4/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 10/4/2022 Approved JUAN VALENZUELA
Final 10/18/2022 OK to Issue CofO JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved JUAN VALENZUELA