Excavation/Setback/Form/Re-Bar
|
4/5/2017
|
Partial Approval
|
JOHN LUMB
|
|
Pre-Inspection
|
5/3/2017
|
Partial Inspection
|
KENNETH NAGLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/25/2017
|
Partial Approval
|
JOHN LUMB
|
|
Masonry Wall/Backfill
|
6/12/2017
|
Partial Approval
|
VINCENT SCIPIONI
|
|
Pre-Inspection
|
6/12/2017
|
Corrections Issued
|
VINCENT SCIPIONI
|
|
Pre-Inspection
|
6/19/2017
|
Partial Approval
|
CRAIG DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2017
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2017
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
7/5/2017
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
7/14/2017
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
8/2/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
8/3/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
8/4/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
8/4/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
8/8/2017
|
No Access for Inspection
|
VINCENT SCIPIONI
|
|
Footing/Foundation/Slab
|
8/11/2017
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2017
|
Partial Approval
|
JOHN LUMB
|
|
BUILDING-Rough-Frame
|
9/6/2017
|
Not Ready for Inspection
|
DANIEL ORRANTE
|
|
Green Building Rough
|
9/6/2017
|
Not Ready for Inspection
|
DANIEL ORRANTE
|
|
Verify Sprinkler Sign Off
|
9/6/2017
|
Not Ready for Inspection
|
DANIEL ORRANTE
|
|
Excavation/Setback/Form/Re-Bar
|
9/19/2017
|
Approved
|
DANIEL ORRANTE
|
|
Excavation/Setback/Form/Re-Bar
|
9/29/2017
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
10/10/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
10/16/2017
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
1/29/2018
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
1/29/2018
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
2/1/2018
|
Approved
|
JOHN LUMB
|
|
Deputy Steel/Welding
|
2/28/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Footing/Foundation/Slab
|
8/31/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2018
|
Corrections Issued
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
9/25/2018
|
Partial Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
11/13/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
11/13/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Verify Sprinkler Sign Off
|
11/13/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Pre-Inspection
|
11/15/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
Deputy Steel/Welding
|
11/20/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Deputy Steel/Welding
|
11/27/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2019
|
Partial Approval
|
KENNETH NAGLE
|
|
HVAC-Rough
|
4/1/2019
|
Partial Inspection
|
MICHAEL TEMPLE
|
|
Underground Mechanical
|
5/1/2019
|
Partial Inspection
|
RICHARD STEINBACH
|
|
ELECTRICAL-Rough
|
7/5/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
PLUMBING-Rough
|
7/18/2019
|
Corrections Issued
|
TIM CHRISTENSEN
|
|
PLUMBING-Rough
|
8/12/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
HVAC-Rough
|
8/20/2019
|
Corrections Issued
|
TIM CHRISTENSEN
|
|
PLUMBING-Rough
|
8/20/2019
|
Approved
|
TIM CHRISTENSEN
|
|
BUILDING-Rough-Frame
|
8/29/2019
|
Corrections Issued
|
TIM CHRISTENSEN
|
|
Green Building Rough
|
8/29/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Verify Sprinkler Sign Off
|
8/29/2019
|
Not Ready for Inspection
|
TIM CHRISTENSEN
|
|
Insulation
|
9/23/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
BUILDING-Rough-Frame
|
10/23/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Green Building Rough
|
10/23/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
HVAC-Rough
|
10/23/2019
|
Approved
|
TIM CHRISTENSEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2019
|
Corrections Issued
|
TIM CHRISTENSEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Footing/Foundation/Slab
|
11/19/2019
|
Approved
|
TIM CHRISTENSEN
|
|
Insulation
|
11/19/2019
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Drywall Nailing
|
1/9/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
ELECTRICAL-Rough
|
1/9/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Green Building Rough
|
1/9/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Interior/Exterior Lathing
|
1/9/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Verify Sprinkler Sign Off
|
1/9/2020
|
Not Ready for Inspection
|
TIM CHRISTENSEN
|
|
BUILDING-Rough-Frame
|
3/3/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Insulation
|
3/3/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Verify Sprinkler Sign Off
|
3/3/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Drywall Nailing
|
3/17/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Shower Pan
|
4/6/2020
|
Not Ready for Inspection
|
TIM CHRISTENSEN
|
|
Shower Pan
|
4/7/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Drywall Nailing
|
4/14/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Interior/Exterior Lathing
|
4/27/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Interior/Exterior Lathing
|
6/9/2020
|
Partial Approval
|
TIM CHRISTENSEN
|
|
Interior/Exterior Lathing
|
7/7/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Pre-Inspection
|
8/17/2020
|
Approved
|
TIM CHRISTENSEN
|
|
Excavation/Setback/Form/Re-Bar
|
10/20/2020
|
Not Ready for Inspection
|
TIM CHRISTENSEN
|
|
ELECTRICAL-Rough
|
10/29/2020
|
Conditional Approval
|
TIM CHRISTENSEN
|
|
Drywall Nailing
|
11/5/2020
|
Partial Approval
|
PIERRE VEGA
|
|
Shower Pan
|
12/10/2020
|
Partial Approval
|
DAVID HEINE
|
|
Interior/Exterior Lathing
|
1/14/2021
|
Approved
|
PIERRE VEGA
|
|
Sewer
|
3/22/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Sewer
|
3/30/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Sewer
|
4/15/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Underground Mechanical
|
5/20/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Underground Mechanical
|
5/27/2021
|
Partial Inspection
|
JUAN VALENZUELA
|
|
ELECTRICAL-Rough
|
5/28/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Underground Mechanical
|
5/28/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Underground Mechanical
|
6/1/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Gas Test
|
6/7/2021
|
Approved
|
ANDREW NAVE
|
|
ELECTRICAL-Rough
|
6/15/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Sewer
|
7/12/2021
|
Approved
|
PIERRE VEGA
|
|
Pre-Inspection
|
10/5/2021
|
Partial Inspection
|
JUAN VALENZUELA
|
|
ELECTRICAL-Rough
|
12/8/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Rough-Elec/Plmb/HVAC
|
1/13/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
Special/Order Compliance
|
1/13/2022
|
Partial Inspection
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
1/21/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
ELECTRICAL-Final
|
1/25/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Pre-Inspection
|
2/11/2022
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Pre-Inspection
|
4/7/2022
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Service/Power Release
|
4/18/2022
|
Approved
|
KENNETH NAGLE
|
|
Deputy Steel/Welding
|
4/27/2022
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Service/Power Release
|
4/28/2022
|
Approved
|
KENNETH NAGLE
|
|
HVAC-Final
|
7/6/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
HVAC-Final
|
7/14/2022
|
Approved
|
JUAN VALENZUELA
|
|
ELECTRICAL-Final
|
7/19/2022
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Green Building Final
|
7/22/2022
|
Approved
|
JUAN VALENZUELA
|
|
PLUMBING-Final
|
7/22/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
ELECTRICAL-Final
|
7/26/2022
|
Approved
|
JUAN VALENZUELA
|
|
PLUMBING-Final
|
7/26/2022
|
Approved
|
JUAN VALENZUELA
|
|
Drywall Nailing
|
10/4/2022
|
Approved
|
JUAN VALENZUELA
|
|
Final
|
10/4/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/4/2022
|
SGSOV Not Ready
|
JUAN VALENZUELA
|
|
Smoke Detectors
|
10/4/2022
|
Approved
|
JUAN VALENZUELA
|
|
Final
|
10/18/2022
|
OK to Issue CofO
|
JUAN VALENZUELA
|
|
SGSOV-Seismic Gas S/O Valve
|
10/18/2022
|
SGSOV Approved
|
JUAN VALENZUELA
|