Special/Order Compliance
|
5/19/2017
|
Corrections Issued
|
BRAD BESCOS
|
|
Piling/Pier/Caisson
|
6/15/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
7/18/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Excavation/Setback/Form/Re-Bar
|
7/28/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
7/28/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Excavation/Setback/Form/Re-Bar
|
8/14/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Other (see comments)
|
8/16/2017
|
No Access for Inspection
|
JOEL WILLIAMS
|
|
Deputy Shotcrete
|
8/16/2017
|
No Access for Inspection
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
8/18/2017
|
Approved
|
JOEL WILLIAMS
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Excavation/Setback/Form/Re-Bar
|
8/21/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
8/22/2017
|
Approved
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
8/29/2017
|
No Access for Inspection
|
BRAD BESCOS
|
|
Deputy Reinf. Concrete
|
9/18/2017
|
No Access for Inspection
|
BRAD BESCOS
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2017
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Underground Mechanical
|
9/18/2017
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
9/19/2017
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Underground Mechanical
|
9/19/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Reinf. Concrete
|
9/28/2017
|
Approved
|
JOEL WILLIAMS
|
|
Footing/Foundation/Slab
|
9/28/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
10/10/2017
|
Approved
|
JOEL WILLIAMS
|
|
Footing/Foundation/Slab
|
10/10/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Underground Mechanical
|
10/11/2017
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Underground Mechanical
|
10/12/2017
|
Not Ready for Inspection
|
JOEL WILLIAMS
|
|
Excavation/Setback/Form/Re-Bar
|
10/16/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Shotcrete
|
10/19/2017
|
No Access for Inspection
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
10/24/2017
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Excavation/Setback/Form/Re-Bar
|
11/2/2017
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
11/8/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Other (see comments)
|
11/14/2017
|
No Access for Inspection
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
11/14/2017
|
No Access for Inspection
|
JOEL WILLIAMS
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
1/9/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Deputy Reinf. Concrete
|
1/22/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
1/22/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Other (see comments)
|
1/29/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Reinf. Concrete
|
1/29/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Underground Mechanical
|
2/8/2018
|
Partial Approval
|
BRAD BESCOS
|
|
Underground Mechanical
|
2/9/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
2/14/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
2/20/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
2/21/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/9/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Drilled-In Anchors
|
3/12/2018
|
Conditional Approval
|
DANNY TOLENTINO
|
|
Deputy Other (see comments)
|
3/12/2018
|
Conditional Approval
|
DANNY TOLENTINO
|
|
Underground Mechanical
|
3/14/2018
|
Partial Approval
|
JOEL WILLIAMS
|
|
Masonry Wall/Backfill
|
3/19/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Masonry Wall/Backfill
|
3/21/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/22/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
4/13/2018
|
Approved
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
4/25/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Wood Frame
|
5/29/2018
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
5/31/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Wood Construction
|
6/6/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/15/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Deputy Steel/Welding
|
6/26/2018
|
No Access for Inspection
|
DANNY TOLENTINO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
7/5/2018
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Deputy Reinf. Concrete
|
7/19/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
7/20/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Reinf. Concrete
|
7/25/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2018
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/7/2018
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Shotcrete
|
8/8/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
8/30/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
8/30/2018
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
Deputy Reinf. Concrete
|
9/4/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/2/2018
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Green Building Rough
|
10/2/2018
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Verify Sprinkler Sign Off
|
10/2/2018
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
10/4/2018
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/4/2018
|
Partial Approval
|
JOSEPH MCGARRY
|
|
HVAC-Rough
|
10/9/2018
|
Corrections Issued
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
10/12/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
10/12/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Sewer
|
10/19/2018
|
Approved
|
DANIEL GONZALEZ
|
|
HVAC-Rough
|
10/29/2018
|
Partial Inspection
|
DANNY TOLENTINO
|
|
BUILDING-Rough-Frame
|
12/12/2018
|
Partial Approval
|
BRAD BESCOS
|
|
Green Building Rough
|
12/12/2018
|
Approved
|
BRAD BESCOS
|
|
Verify Sprinkler Sign Off
|
12/12/2018
|
Partial Approval
|
BRAD BESCOS
|
|
Pre-Inspection
|
1/22/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
7/2/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
7/2/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
7/2/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
7/8/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
7/8/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
8/13/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
8/19/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
8/25/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
HVAC-Rough
|
8/25/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
8/26/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
HVAC-Rough
|
8/26/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
HVAC-Rough
|
9/1/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
9/9/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
9/10/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
9/25/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
10/13/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
10/13/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Wood Frame
|
10/22/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
12/3/2020
|
Approved
|
RAUL BARAJAS
|
|
Insulation
|
12/3/2020
|
Approved
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
12/3/2020
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
12/10/2020
|
Approved
|
RAUL BARAJAS
|
|
Drywall Nailing
|
12/15/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Drywall Nailing
|
12/21/2020
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
3/2/2021
|
Approved
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
8/3/2021
|
Conditional Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
9/17/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Service/Power Release
|
9/17/2021
|
Partial Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
9/22/2021
|
Not Ready for Inspection
|
RICHARD STEINBACH
|
|
Service/Power Release
|
9/22/2021
|
Approved
|
RICHARD STEINBACH
|
|
ELECTRICAL-Final
|
10/6/2021
|
Partial Inspection
|
RAUL BARAJAS
|
|
Service/Power Release
|
10/29/2021
|
Approved
|
RAUL BARAJAS
|
|
Service/Power Release
|
12/3/2021
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
1/10/2022
|
Approved
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
1/19/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Final
|
4/5/2022
|
Corrections Issued
|
RAUL BARAJAS
|
|
Green Building Final
|
4/5/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
4/5/2022
|
Approved
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
4/5/2022
|
SGSOV Not Ready
|
RAUL BARAJAS
|
|
Smoke Detectors
|
4/5/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Structural Steel Frame
|
4/5/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Final
|
5/9/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Green Building Final
|
5/9/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
5/9/2022
|
SGSOV Not Ready
|
RAUL BARAJAS
|
|
Smoke Detectors
|
5/9/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Structural Steel Frame
|
5/9/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
7/13/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Final
|
7/13/2022
|
Corrections Issued
|
RAUL BARAJAS
|
|
Green Building Final
|
7/13/2022
|
Approved
|
RAUL BARAJAS
|
|
HVAC-Final
|
7/13/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Final
|
7/13/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/13/2022
|
SGSOV Approved
|
RAUL BARAJAS
|
|
Smoke Detectors
|
7/13/2022
|
Approved
|
RAUL BARAJAS
|
|
Structural Steel Frame
|
7/13/2022
|
Approved
|
RAUL BARAJAS
|
|
Final
|
7/20/2022
|
Corrections Issued
|
RAUL BARAJAS
|
|
Final
|
7/28/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Final
|
8/22/2022
|
OK to Issue CofO
|
RAUL BARAJAS
|