2347 S OVERLAND AVE 90064

Certificate Information: 2347 S OVERLAND AVE 90064

Application / Permit
15010-30000-04115
Plan Check / Job No.
B15WL05808
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED GARAGE WITH RECREATION ROOM ABOVE
Permit Issued
Issued on 1/5/2016
Issuing Office
West Los Angeles
Current Status
Issued on 1/5/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/12/2015 APPLICANT
Assigned to Plan Check Engineer 11/24/2015 VLADIMIR ARUTYUNYAN
Corrections Issued 12/2/2015 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/2/2015 DOUGLAS NAKATANI
Building Plans Picked Up 12/3/2015 APPLICANT
Green Plans Picked Up 12/4/2015 APPLICANT
Plan Check Approved 1/5/2016 VLADIMIR ARUTYUNYAN
Issued 1/5/2016 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2015 PHONG NGUYEN
Roof/Waste drainage to street Cleared 12/3/2015 PHONG NGUYEN
CPC Cleared 12/22/2015 ANDY RODRIGUEZ
Low Impact Development Cleared 12/22/2015 VIJAY DESAI
Green Code Cleared 12/23/2015 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Lisowski, Andrew George; Lic. No.: C35021 11328 BIONA DR      LOS ANGELES, CA 90066

Inspector Information

WILBER ROSALES, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/6/2016 Approved ROBERT VORHIS
METHANE-Barrier 1/6/2016 Approved ROBERT VORHIS
METHANE-Subgrade 1/6/2016 Approved ROBERT VORHIS
BUILDING-Rough-Frame 1/27/2016 Not Ready for Inspection ROBERT VORHIS
ELECTRICAL-Rough 1/27/2016 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 1/27/2016 Approved ROBERT VORHIS
Green Building Rough 1/27/2016 Approved ROBERT VORHIS
METHANE-Rough 1/27/2016 Approved ROBERT VORHIS
PLUMBING-Rough 1/27/2016 Approved ROBERT VORHIS
ELECTRICAL-Rough 1/29/2016 Not Ready for Inspection ROBERT VORHIS
HVAC-Rough 1/29/2016 Approved ROBERT VORHIS
ELECTRICAL-Final 2/2/2016 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 2/2/2016 Approved ROBERT VORHIS
BUILDING-Rough-Frame 2/4/2016 Approved ROBERT VORHIS
Insulation 2/8/2016 Approved MARK FERRARI
Interior/Exterior Lathing 2/8/2016 Approved MARK FERRARI
Drywall Nailing 2/9/2016 Approved MARK FERRARI
Final 5/9/2016 Corrections Issued ROBERT VORHIS
Green Building Final 5/9/2016 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 5/9/2016 SGSOV Approved ROBERT VORHIS
Service/Power Release 5/9/2016 Approved ROBERT VORHIS
Smoke Detectors 5/9/2016 Approved ROBERT VORHIS
ELECTRICAL-Rough 5/13/2016 Not Ready for Inspection ROBERT VORHIS
Final 5/13/2016 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 5/13/2016 Approved ROBERT VORHIS
Service/Power Release 5/13/2016 Not Required ROBERT VORHIS
Final 7/21/2016 Conditional Approval VINCENT SCIPIONI
Service/Power Release 7/21/2016 Approved VINCENT SCIPIONI