2527 N ROSCOMARE ROAD 90077

Certificate Information: 2527 N ROSCOMARE ROAD 90077

Application / Permit
15010-30000-03818
Plan Check / Job No.
B15WL05500
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD WITH BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 8/12/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2015 APPLICANT
Assigned to Plan Check Engineer 11/24/2015 RICHARD GARCIA
Corrections Issued 11/26/2015 RICHARD GARCIA
Quality Review Completed 12/3/2015 DOUGLAS NAKATANI
Building Plans Picked Up 1/27/2016 APPLICANT
Applicant returned to address corrections 2/10/2016 RICHARD GARCIA
Applicant returned to address corrections 2/12/2016 RICHARD GARCIA
Plan Check Approved 2/12/2016 RICHARD GARCIA
No Progress 3/2/2016 RICHARD GARCIA
Plan Check Approved 6/30/2016 RICHARD GARCIA
Issued 8/12/2016 LADBS
CofO in Progress 8/23/2022 CARLOS MATAMOROS
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/11/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 1/11/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 1/11/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 1/11/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 1/11/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 1/11/2016 RAVIL MANAPOV
Permit Cleared 1/11/2016 RAVIL MANAPOV
ZI Cleared 1/11/2016 ERIC CLAROS
Eng Process Fee Ord 176,300 Cleared 1/20/2016 ARMENIA HERNANDEZ
Hydrant and Access approval Cleared 1/20/2016 JOHN CONNEALLY
Sewer availability Cleared 1/20/2016 ARMENIA HERNANDEZ
Specific Plan Cleared 2/3/2016 ANNA VIDAL
Low Impact Development Cleared 2/8/2016 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/9/2016 LEE GUILBEAUX
Excavation more than 5-ft deep Cleared 2/12/2016 CALOSHA APPROVED
GPI Written Notices Cleared 2/12/2016 RICHARD GARCIA
Grading Pre-Inspection Cleared 2/12/2016 RICHARD GARCIA
Green Code Cleared 2/12/2016 RICHARD GARCIA

Contact Information

Contractor Gotham Developments Llc; Lic. No.: 1011034-B 8306 WILSHIRE BLVD #602      BEVERLY HILLS, CA 90211
Engineer Adams, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304
Engineer Robinson, Rory Anthony; Lic. No.: GE2491 963 EAST SANTA CLARA ST      VENTURA, CA 93001

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 1/18/2017 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 2/3/2017 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 2/9/2017 Partial Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 5/18/2017 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 5/22/2017 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/2/2017 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 6/5/2017 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 6/8/2017 Partial Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 7/17/2017 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/24/2017 Conditional Approval THOMAS FINNILA
Masonry Wall/Backfill 8/3/2017 Partial Inspection ANTHONY ANDERSON
Masonry Wall/Backfill 8/7/2017 No Access for Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 8/31/2017 Partial Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/6/2017 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 9/15/2017 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/19/2017 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/29/2017 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 9/29/2017 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/3/2017 Not Ready for Inspection THOMAS FINNILA
Piling/Pier/Caisson 10/3/2017 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/4/2017 Partial Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 10/20/2017 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/20/2017 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/20/2017 Partial Inspection THOMAS FINNILA
Deputy Steel/Welding 10/31/2017 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 11/1/2017 No Access for Inspection MATT KELLERMAN
Footing/Foundation/Slab 11/6/2017 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 11/7/2017 Conditional Approval THOMAS FINNILA
Special/Order Compliance 1/13/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/23/2018 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/13/2018 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/23/2018 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 5/26/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/18/2018 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 7/2/2018 Approved JONATHAN HOM
PLUMBING-Rough 7/2/2018 Partial Inspection JONATHAN HOM
Interior/Exterior Lathing 7/19/2018 Corrections Issued CHRISTOPHER WILSON
Shower Pan 7/19/2018 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 7/30/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 7/30/2018 Approved CHRISTOPHER WILSON
Special/Order Compliance 8/22/2019 Corrections Issued ANTHONY MCDOWALL
Special/Order Compliance 7/18/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 7/25/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/1/2020 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/28/2020 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 10/28/2020 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 3/1/2021 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 3/15/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 3/15/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 3/18/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/18/2021 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 3/23/2021 Partial Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Corrections Issued CARLOS MATAMOROS
Green Building Rough 3/23/2021 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 3/23/2021 Approved CARLOS MATAMOROS
Gas Test 3/26/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/26/2021 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 4/6/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 4/6/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 4/19/2021 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 5/4/2021 Approved CARLOS MATAMOROS
Drywall Nailing 5/28/2021 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 9/7/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 9/9/2021 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 9/10/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/14/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 7/8/2022 Approved CARLOS MATAMOROS
HVAC-Final 7/8/2022 Approved CARLOS MATAMOROS
Gas Test 7/11/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 7/11/2022 Approved CARLOS MATAMOROS
Service/Power Release 7/11/2022 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 7/13/2022 Approved CARLOS MATAMOROS
Final 8/23/2022 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 8/23/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 8/23/2022 Approved CARLOS MATAMOROS